TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/ROAD/11611/2015              (ii). Name of Project for which Forest Land is required : Danoghat sanjha aara Neri Plata              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : CHECK LIST SERIAL NUMBER-4 SHORT NARRATIVE OF ROAD C/o Danoghat Sanjha-Aara(????? ???)–Neri Plata road Km.0/0 to 5/360 This road construction of Danoghat Sanjha-Aara(????? ???)–Neri Plata road km.0/0 to 5/360 qualifies the criteria for inclusion in NABARD. This road bifurcates from NH-205 at              (iv). File no. : 8B/HPB/06/93/2016              (v). State : Himachal Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 3.8423
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HP/ROAD/11611/201511/04/201506/08/2015  06/07/2015  18/04/2015   07/08/2015  05/08/2015  25/06/2015   10/08/2015   24/08/2015 Kunihar :24/08/2015Bilaspur:
  03/03/2016 (Kunihar)

Himachal Pradesh:
08/08/2016
Himachal Pradesh:
21/11/2016
Shimla:
15/12/2016
23/06/2017
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:30/12/2016  
Replied by State Government(Himachal Pradesh) on:31/05/2017  
Query raised by State Government (Himachal Pradesh) on:30/12/2016  
Replied by Nodal Officer (Himachal Pradesh) on:31/05/2017  
Query raised by Nodal Officer (Himachal Pradesh) on:12/08/2016  
Replied by Circle(Bilaspur) on:05/11/2016  
Query raised by Nodal Officer (Himachal Pradesh) on:30/12/2016  
Replied by Circle(Bilaspur) on:20/04/2017  
Query raised by Nodal Officer (Himachal Pradesh) on:21/04/2017  
Replied by Circle(Bilaspur) on:25/04/2017  
Query raised by Nodal Officer (Himachal Pradesh) on:04/05/2017  
Replied by Circle(Bilaspur) on:25/05/2017  
Query raised by Circle (Bilaspur) on:31/03/2016  
Replied by DFO (Kunihar) on:06/04/2016  
Query raised by Circle (Bilaspur) on:11/04/2016  
Replied by DFO (Kunihar) on:08/08/2016  
Query raised by Circle (Bilaspur) on:16/08/2016  
Replied by DFO (Kunihar) on:11/09/2016  
Query raised by Circle (Bilaspur) on:14/09/2016  
Replied by DFO (Kunihar) on:24/09/2016  
Query raised by Circle (Bilaspur) on:04/10/2016  
Replied by DFO (Kunihar) on:03/11/2016  
Query raised by Circle (Bilaspur) on:30/12/2016  
Replied by DFO (Kunihar) on:20/03/2017  
Query raised by Circle (Bilaspur) on:21/03/2017  
Replied by DFO (Kunihar) on:21/03/2017  
Query raised by Circle (Bilaspur) on:28/03/2017  
Replied by DFO (Kunihar) on:13/04/2017  
Query raised by Circle (Bilaspur) on:06/05/2017  
Replied by DFO (Kunihar) on:20/05/2017  
Query raised by Circle (Bilaspur) on:22/05/2017  
Replied by DFO (Kunihar) on:22/05/2017  
Query raised by DFO (Kunihar) on:29/09/2015  
Replied by UA on :20/02/2016  
Query raised by DFO (Kunihar) on:19/04/2016  
Replied by UA on :05/08/2016  
Query raised by DFO (Kunihar) on:18/01/2017  
Replied by UA on :09/02/2017  
Query raised by DFO (Kunihar) on:08/05/2017  
Replied by UA on :12/05/2017  
NOTE:- Stage-I Approval accorded by : Regional Office .