Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
26/11/2018
|
Submit the case after doing the needful.
|
|
2
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
27/11/2018
|
Recommendation letter
|
|
3
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
22/12/2018
|
Please complete the proposal as per copy of EDS is attached.
|
|
4
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
29/12/2018
|
EDS enclosed above
|
|
5
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
03/01/2019
|
Attend the EDS as raised by higher authority
|
|
6
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
11/01/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
11/01/2019
|
Reply of EDS raised by DFO (FCA) O/o CCF (FCA) HP Shimla is attached.
|
|
8
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
17/01/2019
|
Reply attached as per EDS
|
|
9
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
24/01/2019
|
Point No.1, has not been got attended by the user agency. Ask the user agency to make the proposal folder properly with proper index and check list.
|
|
10
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
28/01/2019
|
The user agency has directed to attend and make the proposal folder properly with proper index and check list in the head office Shimla.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
06/05/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
08/05/2020
|
EDS
|
|
13
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
08/05/2020
|
EDS
|
|
14
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
14/05/2020
|
EDS is enclosed
|
|
15
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
09/06/2020
|
EDS is enclosed
|
|
16
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
25/07/2020
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
04/12/2021
|
Certificate of settlement of rights under the Forest Rights Act,2006 on the forest land proposed to be diverted as issued by DC Shimla is not uploaded in Part-I against Column No.-K
|
|
18
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
31/01/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
31/01/2022
|
FRA certificate has been uploaded by UA at relevant column
|
|
20
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
23/02/2022
|
EDS
|
|
21
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
22/03/2022
|
The attested copy of FRA certificate in duplicate has been submitted vide letter No. 6084 dated 4/3/2022 for further transmission to the quarter concerned
|
|
22
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
23/03/2022
|
Reply of EDS is enclosed
|
|
23
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
20/04/2022
|
EDS
|
|
24
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
25/04/2022
|
EDS raised by the GoI
|
|
25
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
06/05/2022
|
Needful has been done
|
|
26
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
06/05/2022
|
Needful has been done
|
|
27
|
Nodal Officer
|
REPLY
|
State secretary
|
06/05/2022
|
The proposal is forwarded in view of point No. 4 raised during the REC meeting held on 29.11.2021.
|
|
28
|
State secretary
|
REPLY
|
Regional Office
|
06/05/2022
|
The proposal is forwarded in view of point No. 4 raised during the REC meeting held on 29.11.2021.
|
|
29
|
Regional Office
|
EDS
|
State secretary
|
22/07/2022
|
The State Govt. may attend the shortcomings attached herewith
|
|
30
|
State secretary
|
EDS
|
Nodal Officer
|
22/07/2022
|
EDS
|
|
31
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
22/07/2022
|
EDS
|
|
32
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
26/07/2022
|
EDS raised by the GoI
|
|
33
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
20/09/2022
|
EDS is enclosed
|
|
34
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
17/03/2023
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
25/03/2023
|
Reply of the EDS is enclosed
|
|
36
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
12/04/2023
|
The cases is returned with the remarks that the NPV bill not uploaded in online web portal part-II
|
|
37
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
26/06/2023
|
EDS is enclosed
|
|
38
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
10/07/2023
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
18/07/2023
|
Reply of EDS is attached
|
|
40
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
02/08/2023
|
Reply of EDS is enclosed
|
|
41
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
25/08/2023
|
Shortcomings have been noticed in the proposals, which may be completed.
|
|
42
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
31/08/2023
|
EDS
|
|
43
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
13/12/2023
|
EDS is enclosed
|
|
44
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
08/04/2024
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
28/04/2024
|
The case is not shown in Part-II of online portal. please re submit the case
|
|
46
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
30/04/2024
|
Please submit the reply of observations raised by the GoI i
|
|
47
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
06/05/2024
|
EDS is enclosed
|
|
48
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
07/05/2024
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
07/05/2024
|
Reply of the observations is enclosed. Unable to upload the documents in online portal Part-II due to technical issue in Parivesh Portal.
|
|
50
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
14/05/2024
|
EDS
|
|
51
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
14/05/2024
|
Please upload EDS
|
|
52
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
14/05/2024
|
EDS
|
|
53
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
17/05/2024
|
Reply of EDS is enclosed
|
|
54
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
24/06/2024
|
Reply of EDS attached
|
|
55
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
10/07/2024
|
EDS
|
|
56
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
16/07/2024
|
EDS
|
|
57
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
12/08/2024
|
EDS is enclosed
|
|
58
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
28/08/2024
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
28/08/2024
|
Upload revised kml file
|
|
60
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
28/08/2024
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
24/10/2024
|
Reply of EDS is attached for information and necessary action at your end please.
|
|
62
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
28/10/2024
|
EDS
|
|
63
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
21/11/2024
|
Reply of EDS is enclosed and data of CD has been sent to your good office through e-mail:- rampurcricle@gmail.com
|
|
64
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
04/12/2024
|
Reply of EDS is attached
|
|
65
|
Nodal Officer
|
REPLY
|
State secretary
|
05/12/2024
|
Complete reply is submitted please.
|
|
66
|
State secretary
|
REPLY
|
Regional Office
|
05/12/2024
|
Complete reply is submitted please.
|
|
67
|
Regional Office
|
EDS
|
State secretary
|
29/01/2025
|
The State Govt may attend the shortcomings attached herewith.
|
|
68
|
State secretary
|
EDS
|
Nodal Officer
|
29/01/2025
|
EDS
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
30/01/2025
|
Complete reply is submitted
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
30/01/2025
|
Complete reply is submitted
|
|
71
|
Regional Office
|
EDS
|
State secretary
|
19/03/2025
|
The State govt may attend the shortcomings attached herewith.
|
|
72
|
State secretary
|
EDS
|
Nodal Officer
|
19/03/2025
|
eds
|
|
73
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
19/03/2025
|
eds
|
|
74
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
20/03/2025
|
EDS raised by GoI
|
|
75
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
26/03/2025
|
EDS regarding raised observations
|
|
76
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
02/04/2025
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
05/04/2025
|
KML file is not correct
|
|
78
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
08/04/2025
|
The correction have been made as per the instruction received
|
|
79
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
07/05/2025
|
EDS attached.
|
|
80
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
12/06/2025
|
Reply to EDS
|
|
81
|
Nodal Officer
|
EDS
|
CF (Rampur)
|
19/06/2025
|
EDS
|
|
82
|
CF (Rampur)
|
EDS
|
DFO (Rampur)
|
19/06/2025
|
EDS raised by Nodal Officer
|
|
83
|
DFO (Rampur)
|
EDS
|
User Agency (cheshwer1979@gmail.com)
|
19/06/2025
|
Kindly attend the observation raised by Nodal Officer.
|
|
84
|
User Agency (cheshwer1979@gmail.com)
|
REPLY
|
DFO (Rampur)
|
19/06/2025
|
The correction have been made as per the instruction received
|
|
85
|
DFO (Rampur)
|
REPLY
|
CF (Rampur)
|
02/07/2025
|
Reply of EDS attached.
|
|
86
|
CF (Rampur)
|
REPLY
|
Nodal Officer
|
19/07/2025
|
Reply of EDS is attached
|
|
87
|
Nodal Officer
|
REPLY
|
State secretary
|
04/08/2025
|
Complete reply is submitted
|
|
88
|
State secretary
|
REPLY
|
Regional Office
|
04/08/2025
|
Compete reply is submitted
|
|