A. General Details
  (i). Proposal No. : FP/HP/IND/35171/2018              (ii). Name of Project for which Forest Land is required : Renewal of diversion of existing stone crusher of M/s Bushahr Laghu Udyog, Situated at village- Pashada, P.O.- Khenari, Tehsil-Rampur, Dist.- Shimla, HP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Renewal of diversion of 0.0934 ha (instead of .02898 ha) of forest land for already established Stone Crusher at pashada in favour of M/s Bushahr Laghu Udyog VPO Jhkari Rampur with in the Juridiction of Rampur Forest Division, Distt Shimla Himachal Pradesh.              (iv). File no. : FC/HPB/09/79/2022              (v). State : Himachal Pradesh              (vi). Category of the Project : Industry              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.0934
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/HP/IND/35171/201830/08/201818/09/2018  07/09/2018   26/09/2018  12/09/2018   27/09/2018   01/10/2018 Rampur :06/10/2018Rampur:
  20/11/2018 (Rampur)

Himachal Pradesh:
06/12/2018
Himachal Pradesh:
07/02/2019
21/02/2019
HO Linked Date:
06/10/2025
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 13/10/2025  
Replied by State Government (Himachal Pradesh) on:05/03/2026  
Query raised by MoEFCC,New Delhi on 13/04/2026  
Query raised by State Government (Himachal Pradesh) on:08/05/2020  
Replied by Nodal Officer (Himachal Pradesh) on:06/05/2022  
Query raised by State Government (Himachal Pradesh) on:22/07/2022  
Replied by Nodal Officer (Himachal Pradesh) on:05/12/2024  
Query raised by State Government (Himachal Pradesh) on:29/01/2025  
Replied by Nodal Officer (Himachal Pradesh) on:30/01/2025  
Query raised by State Government (Himachal Pradesh) on:19/03/2025  
Replied by Nodal Officer (Himachal Pradesh) on:04/08/2025  
Query raised by State Government (Himachal Pradesh) on:27/10/2025  
Replied by Nodal Officer (Himachal Pradesh) on:05/03/2026  
Query raised by Nodal Officer (Himachal Pradesh) on:22/12/2018  
Replied by Circle(Rampur) on:17/01/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:24/01/2019  
Replied by Circle(Rampur) on:28/01/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:08/05/2020  
Replied by Circle(Rampur) on:23/03/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:20/04/2022  
Replied by Circle(Rampur) on:06/05/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:22/07/2022  
Replied by Circle(Rampur) on:02/08/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:25/08/2023  
Replied by Circle(Rampur) on:24/06/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:10/07/2024  
Replied by Circle(Rampur) on:04/12/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:19/03/2025  
Replied by Circle(Rampur) on:12/06/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:19/06/2025  
Replied by Circle(Rampur) on:19/07/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:28/10/2025  
Replied by Circle(Rampur) on:19/02/2026  
Query raised by Circle (Rampur) on:26/11/2018  
Replied by DFO (Rampur) on:27/11/2018  
Query raised by Circle (Rampur) on:29/12/2018  
Replied by DFO (Rampur) on:11/01/2019  
Query raised by Circle (Rampur) on:14/05/2020  
Replied by DFO (Rampur) on:31/01/2022  
Query raised by Circle (Rampur) on:23/02/2022  
Replied by DFO (Rampur) on:22/03/2022  
Query raised by Circle (Rampur) on:25/04/2022  
Replied by DFO (Rampur) on:06/05/2022  
Query raised by Circle (Rampur) on:26/07/2022  
Replied by DFO (Rampur) on:25/03/2023  
Query raised by Circle (Rampur) on:12/04/2023  
Replied by DFO (Rampur) on:18/07/2023  
Query raised by Circle (Rampur) on:31/08/2023  
Replied by DFO (Rampur) on:28/04/2024  
Query raised by Circle (Rampur) on:30/04/2024  
Replied by DFO (Rampur) on:07/05/2024  
Query raised by Circle (Rampur) on:14/05/2024  
Replied by DFO (Rampur) on:14/05/2024  
Query raised by Circle (Rampur) on:14/05/2024  
Replied by DFO (Rampur) on:17/05/2024  
Query raised by Circle (Rampur) on:16/07/2024  
Replied by DFO (Rampur) on:24/10/2024  
Query raised by Circle (Rampur) on:28/10/2024  
Replied by DFO (Rampur) on:21/11/2024  
Query raised by Circle (Rampur) on:20/03/2025  
Replied by DFO (Rampur) on:07/05/2025  
Query raised by Circle (Rampur) on:19/06/2025  
Replied by DFO (Rampur) on:02/07/2025  
Query raised by Circle (Rampur) on:28/10/2025  
Replied by DFO (Rampur) on:18/02/2026  
Query raised by DFO (Rampur) on:03/01/2019  
Replied by UA on :11/01/2019  
Query raised by DFO (Rampur) on:09/06/2020  
Replied by UA on :25/07/2020  
Query raised by DFO (Rampur) on:04/12/2021  
Replied by UA on :31/01/2022  
Query raised by DFO (Rampur) on:20/09/2022  
Replied by UA on :17/03/2023  
Query raised by DFO (Rampur) on:26/06/2023  
Replied by UA on :10/07/2023  
Query raised by DFO (Rampur) on:13/12/2023  
Replied by UA on :08/04/2024  
Query raised by DFO (Rampur) on:06/05/2024  
Replied by UA on :07/05/2024  
Query raised by DFO (Rampur) on:12/08/2024  
Replied by UA on :28/08/2024  
Query raised by DFO (Rampur) on:28/08/2024  
Replied by UA on :28/08/2024  
Query raised by DFO (Rampur) on:26/03/2025  
Replied by UA on :02/04/2025  
Query raised by DFO (Rampur) on:05/04/2025  
Replied by UA on :08/04/2025  
Query raised by DFO (Rampur) on:19/06/2025  
Replied by UA on :19/06/2025  
Query raised by DFO (Rampur) on:12/01/2026  
Replied by UA on :17/02/2026  
NOTE:- Proposal is pending at State Government due to EDS raised by Head Office .