TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/HYD/147118/2021              (ii). Name of Project for which Forest Land is required : Jiwa-II (1.75 MW) SHEP              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Jiwa-II (1.75 MW) Hydro Electric Project is run-of-the river project. This project is located opposite village Kathiari/Bhiyali near Sainj town in Sub-Tehsil Sainj, Sub Division Banjar, District Kullu, Himachal Pradesh.              (iv). File no. : FC/HPB/01/104/2022              (v). State : Himachal Pradesh              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.8223
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeROHQ, New DelhiStage-I Approval onStage-II Approval on
FP/HP/HYD/147118/202105/10/202115/11/2021  23/10/2021   17/11/2021  08/11/2021   17/11/2021   22/11/2021 GHNP :22/11/2021GHNP:
  27/12/2021 (GHNP)

Himachal Pradesh:
04/01/2022
Himachal Pradesh:
17/05/2022
Shimla:
04/08/2022
30/01/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Shimla) on:07/09/2022  
Replied by State Government(Himachal Pradesh) on:02/06/2023  
Query raised by Regional Office (Shimla) on:01/11/2023  
Replied by State Government(Himachal Pradesh) on:02/05/2024  
Query raised by Regional Office (Shimla) on:20/05/2024  
Replied by State Government(Himachal Pradesh) on:21/06/2024  
Query raised by Regional Office (Shimla) on:05/12/2024  
Replied by State Government(Himachal Pradesh) on:08/01/2025  
Query raised by State Government (Himachal Pradesh) on:08/09/2022  
Replied by Nodal Officer (Himachal Pradesh) on:02/06/2023  
Query raised by State Government (Himachal Pradesh) on:04/11/2023  
Replied by Nodal Officer (Himachal Pradesh) on:02/05/2024  
Query raised by State Government (Himachal Pradesh) on:25/05/2024  
Replied by Nodal Officer (Himachal Pradesh) on:21/06/2024  
Query raised by State Government (Himachal Pradesh) on:09/12/2024  
Replied by Nodal Officer (Himachal Pradesh) on:08/01/2025  
Query raised by Nodal Officer (Himachal Pradesh) on:21/01/2022  
Replied by Circle(GHNP) on:08/02/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:24/02/2022  
Replied by Circle(GHNP) on:03/03/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:02/04/2022  
Replied by Circle(GHNP) on:06/04/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:25/04/2022  
Replied by Circle(GHNP) on:29/04/2022  
Query raised by Nodal Officer (Himachal Pradesh) on:08/09/2022  
Replied by Circle(GHNP) on:24/03/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:24/04/2023  
Replied by Circle(GHNP) on:30/05/2023  
Query raised by Nodal Officer (Himachal Pradesh) on:04/11/2023  
Replied by Circle(GHNP) on:17/01/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:23/01/2024  
Replied by Circle(GHNP) on:05/03/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:15/03/2024  
Replied by Circle(GHNP) on:24/04/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:27/05/2024  
Replied by Circle(GHNP) on:13/06/2024  
Query raised by Nodal Officer (Himachal Pradesh) on:09/12/2024  
Replied by Circle(GHNP) on:24/12/2024  
Query raised by Circle (GHNP) on:01/01/2022  
Replied by DFO (GHNP) on:01/01/2022  
Query raised by Circle (GHNP) on:27/01/2022  
Replied by DFO (GHNP) on:08/02/2022  
Query raised by Circle (GHNP) on:25/02/2022  
Replied by DFO (GHNP) on:03/03/2022  
Query raised by Circle (GHNP) on:29/04/2022  
Replied by DFO (GHNP) on:29/04/2022  
Query raised by Circle (GHNP) on:29/04/2022  
Replied by DFO (GHNP) on:29/04/2022  
Query raised by Circle (GHNP) on:21/09/2022  
Replied by DFO (GHNP) on:23/03/2023  
Query raised by Circle (GHNP) on:27/04/2023  
Replied by DFO (GHNP) on:10/05/2023  
Query raised by Circle (GHNP) on:08/11/2023  
Replied by DFO (GHNP) on:23/12/2023  
Query raised by Circle (GHNP) on:28/12/2023  
Replied by DFO (GHNP) on:28/12/2023  
Query raised by Circle (GHNP) on:24/01/2024  
Replied by DFO (GHNP) on:05/03/2024  
Query raised by Circle (GHNP) on:18/03/2024  
Replied by DFO (GHNP) on:10/04/2024  
Query raised by Circle (GHNP) on:27/05/2024  
Replied by DFO (GHNP) on:10/06/2024  
Query raised by Circle (GHNP) on:12/12/2024  
Replied by DFO (GHNP) on:16/12/2024  
Query raised by Circle (GHNP) on:23/12/2024  
Replied by DFO (GHNP) on:23/12/2024  
Query raised by DFO (GHNP) on:04/02/2022  
Replied by UA on :05/02/2022  
Query raised by DFO (GHNP) on:21/09/2022  
Replied by UA on :28/12/2022  
Query raised by DFO (GHNP) on:23/01/2023  
Replied by UA on :02/02/2023  
Query raised by DFO (GHNP) on:06/02/2023  
Replied by UA on :23/02/2023  
Query raised by DFO (GHNP) on:21/03/2023  
Replied by UA on :21/03/2023  
Query raised by DFO (GHNP) on:28/04/2023  
Replied by UA on :05/05/2023  
Query raised by DFO (GHNP) on:16/11/2023  
Replied by UA on :25/11/2023  
Query raised by DFO (GHNP) on:24/01/2024  
Replied by UA on :16/02/2024  
Query raised by DFO (GHNP) on:22/03/2024  
Replied by UA on :03/04/2024  
Query raised by DFO (GHNP) on:29/05/2024  
Replied by UA on :08/06/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .