TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HP/HYD/12761/2015              (ii). Name of Project for which Forest Land is required : RAMPUR HYDRO ELECTRIC PROJECT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Additional land for road, bridge, river protection / training works.              (iv). File no. : 8-114/2005-FC (Vol.)              (v). State : Himachal Pradesh              (vi). Category of the Project : Hydel              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.8374
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiStage-I Approval onStage-II Approval on
FP/HP/HYD/12761/201526/05/201501/06/2015   04/06/2015   05/06/2015   11/06/2015 Rampur :11/06/2015Rampur:
  24/06/2015 (Rampur)

Himachal Pradesh:
30/06/2015
Himachal Pradesh:
20/07/2015
20/07/201525/03/2021
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 22/05/2020  
Replied by State Government (Himachal Pradesh) on:19/09/2020  
Query raised by MoEFCC,New Delhi on 19/10/2020  
Replied by State Government (Himachal Pradesh) on:30/01/2021  
Query raised by State Government (Himachal Pradesh) on:09/09/2015  
Replied by Nodal Officer (Himachal Pradesh) on:29/02/2016  
Query raised by State Government (Himachal Pradesh) on:18/03/2016  
Replied by Nodal Officer (Himachal Pradesh) on:06/11/2019  
Query raised by State Government (Himachal Pradesh) on:23/05/2020  
Replied by Nodal Officer (Himachal Pradesh) on:19/09/2020  
Query raised by State Government (Himachal Pradesh) on:19/10/2020  
Replied by Nodal Officer (Himachal Pradesh) on:30/01/2021  
Query raised by Nodal Officer (Himachal Pradesh) on:09/09/2015  
Replied by Circle(Rampur) on:11/12/2015  
Query raised by Nodal Officer (Himachal Pradesh) on:13/01/2016  
Replied by Circle(Rampur) on:17/02/2016  
Query raised by Nodal Officer (Himachal Pradesh) on:18/03/2016  
Replied by Circle(Rampur) on:31/05/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:12/06/2019  
Replied by Circle(Rampur) on:19/10/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:05/11/2019  
Replied by Circle(Rampur) on:05/11/2019  
Query raised by Nodal Officer (Himachal Pradesh) on:23/05/2020  
Replied by Circle(Rampur) on:08/09/2020  
Query raised by Nodal Officer (Himachal Pradesh) on:19/10/2020  
Replied by Circle(Rampur) on:14/01/2021  
Query raised by Circle (Rampur) on:17/09/2015  
Replied by DFO (Rampur) on:02/12/2015  
Query raised by Circle (Rampur) on:18/01/2016  
Replied by DFO (Rampur) on:09/02/2016  
Query raised by Circle (Rampur) on:22/03/2016  
Replied by DFO (Rampur) on:31/05/2019  
Query raised by Circle (Rampur) on:15/06/2019  
Replied by DFO (Rampur) on:11/10/2019  
Query raised by Circle (Rampur) on:29/05/2020  
Query raised by Circle (Rampur) on:03/09/2020  
Replied by DFO (Rampur) on:03/09/2020  
Query raised by Circle (Rampur) on:06/11/2020  
Replied by DFO (Rampur) on:31/12/2020  
Query raised by DFO (Rampur) on:22/09/2015  
Replied by UA on :31/10/2015  
Query raised by DFO (Rampur) on:12/04/2016  
Replied by UA on :01/11/2018  
Query raised by DFO (Rampur) on:18/06/2019  
Replied by UA on :09/09/2019  
Query raised by DFO (Rampur) on:11/06/2020  
Replied by UA on :23/07/2020  
Query raised by DFO (Rampur) on:21/11/2020  
Replied by UA on :12/12/2020  
NOTE:- Stage-I Approval accorded by : Head Office .