  (i). Proposal No. : FP/AS/ROAD/125122/2021              (ii). Name of Project for which Forest Land is required : WIDENING / UP-GRADATION OF NH-29 FROM 2-LANE TO 4-LANE DIVIDED NATIONAL HIGHWAY FROM DABOKA TO LAHORIJAN (KARBI ANGLONG EAST FOREST DIVISION PART) UNDER BHARATMALA PARIYOJANA (LOT-1-PACKAGE-II)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The National Highways & Infrastructure Development Corporation Limited (hereinafter referred to as “NHICDL”) has been constituted through an Act of Parliament for faster, economical and quality Road Construction work throughout India. NHIDCL has been entrusted with the assignment of preparation of D              (iv). File no. : 3-AS-C-136/2022-GHY              (v). State : Assam              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 14.56
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/AS/ROAD/125122/202103/03/202106/05/2022  07/04/2022  12/11/2021  04/10/2021  25/03/2021   08/05/2022  26/04/2022  30/03/2022  22/10/2021  21/09/2021   10/05/2022   24/05/2022 Karbi Anglong East Division, Diphu :27/05/2022Karbi Anglong Circle(council) Diphu:
  30/07/2022 (Karbi Anglong East Division, Diphu)

Assam:
18/08/2022
Assam:
18/08/2022
Guwahati:
17/09/2022
05/07/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Guwahati) on:30/09/2022  
Replied by State Government(Assam) on:08/11/2022  
Query raised by Regional Office (Guwahati) on:16/11/2022  
Replied by State Government(Assam) on:19/11/2022  
Query raised by Regional Office (Guwahati) on:07/12/2022  
Replied by State Government(Assam) on:19/12/2022  
Query raised by Regional Office (Guwahati) on:27/12/2022  
Replied by State Government(Assam) on:31/12/2022  
Query raised by Regional Office (Guwahati) on:06/01/2023  
Replied by State Government(Assam) on:25/01/2023  
Query raised by Regional Office (Guwahati) on:21/02/2023  
Replied by State Government(Assam) on:11/09/2023  
Query raised by State Government (Assam) on:17/12/2022  
Replied by Nodal Officer (Assam) on:17/12/2022  
Query raised by Nodal Officer (Assam) on:17/12/2022  
Replied by Circle(Karbi Anglong Circle(council) Diphu) on:17/12/2022  
Query raised by Circle (Karbi Anglong Circle(council) Diphu) on:17/12/2022  
Replied by DFO (Karbi Anglong East Division, Diphu ) on:17/12/2022  