| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
17/12/2020
|
Request to re examine the proposal
|
|
|
2
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
18/12/2020
|
DFO narsipatnam is requested to examine the proposal with reference to already sanctioned the roads. Instructions issued.
|
|
|
3
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
03/02/2021
|
Report submission on Gompam to Bobbampadu road proposal
|
|
|
4
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
09/02/2021
|
As per the instructions of the Prl. CCF and report submitted to the DFO, detailed report submitted to Prl. CCF
|
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
16/04/2021
|
As per EDS attached
|
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
21/06/2021
|
Request to identify suitable non forest area for compensatory afforestation purpose.
|
|
|
7
|
Nodal Officer
|
EDS
|
CF (Visakhapatnam)
|
29/06/2021
|
Request to furnish CA land details, KML fles,
Soil suitability certifcate etc., for further consideration.
|
|
|
8
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
30/06/2021
|
DFO is requested to submit CA land details as called for by the Prl. CCF.
|
|
|
9
|
CF (Visakhapatnam)
|
EDS
|
DFO (Visakhapatnam)
|
30/06/2021
|
DFO is requested to submit CA land details as called for by the Prl. CCF.
|
|
|
10
|
DFO (Visakhapatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
01/07/2021
|
Proposals for diversion of forest land for formation
of roads under LWE Category – Request to furnish CA land details, KML fles,
Soil suitability certifcate etc
|
|
|
11
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
14/07/2021
|
The Executive Engineer, PR Division, Paderu is requested to submit CA land details as called for by the Prl.CCF&HoFF, A.P., Guntur for further process.
|
|
|
12
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
22/01/2022
|
The correction have been made as per the instruction received
|
|
|
13
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
01/02/2022
|
The correction have been made as per the instruction received
|
|
|
14
|
DFO (Narasipatnam)
|
EDS
|
User Agency (eeprpdr2010@gmail.com)
|
15/02/2022
|
The Executive Engineer, PR PIU Division, Paderu is requested to submit the reports on each road proposal to concerned Divisional Forest Officers along with all necessary documents i.e. CA area soil/ site suitability certificate, authenticated DGPS map, kml file and Proceedings of the District Collector, Visakhapatnam in 6 sets in hard and soft copies to process the road proposals for further process.
|
|
|
15
|
User Agency (eeprpdr2010@gmail.com)
|
REPLY
|
DFO (Narasipatnam)
|
21/02/2022
|
The correction have been made as per the instruction received
|
|
|
16
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
22/02/2022
|
The Part-II proposals along with CA area details are submitted herewith for further process.
|
|
|
17
|
DFO (Visakhapatnam)
|
REPLY
|
CF (Visakhapatnam)
|
26/02/2022
|
Revised CA scheme along with other documents pertaining to the road Gompam to Boppampadu.
|
|
|
18
|
CF (Visakhapatnam)
|
EDS
|
DFO (Narasipatnam)
|
03/03/2022
|
The DFO, Visakhapatnam and Narsipatnam are requested to submit rectified proposals as per the shortcomings communicated by the Nodal Officer
|
|
|
19
|
CF (Visakhapatnam)
|
EDS
|
DFO (Visakhapatnam)
|
03/03/2022
|
The DFO, Visakhapatnam and Narsipatnam are requested to submit rectified proposals as per the shortcomings communicated by the Nodal Officer
|
|
|
20
|
DFO (Narasipatnam)
|
REPLY
|
CF (Visakhapatnam)
|
03/03/2022
|
The shortcomings and proportionate CA scheme details are uploaded and requested for taking further process.
|
|
|
21
|
DFO (Visakhapatnam)
|
REPLY
|
CF (Visakhapatnam)
|
04/03/2022
|
Revised CA scheme along with other details
|
|
|
22
|
CF (Visakhapatnam)
|
REPLY
|
Nodal Officer
|
04/03/2022
|
As per the instructions issued by the Nodal Officer rectified proposals along with CA details are uploaded.
|
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
07/03/2022
|
Ca land details submitted
|
|
|
24
|
State secretary
|
REPLY
|
Regional Office
|
17/03/2022
|
Submitted
|
|