Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Nellore)
|
EDS
|
User Agency (rayudubt@gmail.com)
|
20/10/2020
|
RoFR information
|
|
2
|
User Agency (rayudubt@gmail.com)
|
REPLY
|
DFO (Nellore)
|
15/06/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Nellore)
|
EDS
|
User Agency (rayudubt@gmail.com)
|
17/03/2022
|
DGPS authenticated maps to be got signed, Adl. NPV undertaking
|
|
4
|
User Agency (rayudubt@gmail.com)
|
REPLY
|
DFO (Nellore)
|
11/04/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Nellore)
|
EDS
|
User Agency (rayudubt@gmail.com)
|
09/06/2022
|
District name to be changed
|
|
6
|
User Agency (rayudubt@gmail.com)
|
REPLY
|
DFO (Nellore)
|
28/07/2022
|
The correction have been made as per the instruction received
|
|
7
|
Regional Office
|
EDS
|
State secretary
|
31/01/2023
|
as per the attached EDS
|
|
8
|
State secretary
|
EDS
|
Nodal Officer
|
02/02/2023
|
Additional information called for
|
|
9
|
Nodal Officer
|
EDS
|
CF (Guntur)
|
14/02/2023
|
Request to submit additional information
|
|
10
|
CF (Guntur)
|
EDS
|
DFO (Nellore)
|
03/03/2023
|
Request to submit additional information
|
|
11
|
DFO (Nellore)
|
REPLY
|
CF (Guntur)
|
20/07/2023
|
Additional information uploaded
|
|
12
|
CF (Guntur)
|
REPLY
|
Nodal Officer
|
21/07/2023
|
Additional information submitted
|
|
13
|
Nodal Officer
|
REPLY
|
State secretary
|
08/08/2023
|
Additional information submitted
|
|
14
|
State secretary
|
REPLY
|
Regional Office
|
21/08/2023
|
Additional information on violation of FC Act.
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
16/04/2024
|
Erring officials
who have been involved in the violation of Adhiniyam may kindly be furnished
|
|
16
|
State secretary
|
REPLY
|
Regional Office
|
25/10/2024
|
Action taken report for violation of FC Act, 1980
|
|
17
|
Regional Office
|
EDS
|
State secretary
|
17/12/2024
|
as in EDS
|
|
18
|
State secretary
|
EDS
|
Nodal Officer
|
27/01/2025
|
Action taken report
|
|