TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/RAIL/155820/2022              (ii). Name of Project for which Forest Land is required : Single-line broad-gauge railway connectivity from Amarda Road station to the Subarnarekha Port.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The rail infrastructure will be used for transportation of cargoes such as coal/ iron ore/ limestone/ Mn ore/ dolomite/ project cargo once the port is operational. The alignment of the rail corridor has been finalized keeping in view minimum acquisition/ alienation of land and minimal disturbance              (iv). State : Orissa              (v). Category of the Project : Railway              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 12.202
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/OR/RAIL/155820/202226/05/202201/06/2022   03/06/2022   31/05/2022   31/05/2022 Balasore Wildlife :03/06/2022Baripada:
  29/10/2022 (Balasore Wildlife)

Orissa:
29/12/2022
Orissa:
24/07/2023
Bhubaneswar:
09/08/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Bhubaneswar) on:24/08/2023  
Replied by State Government(Orissa) on:02/04/2024  
Query raised by Regional Office (Bhubaneswar) on:25/04/2024  
Query raised by State Government (Orissa) on:02/09/2023  
Replied by Nodal Officer (Orissa) on:06/03/2024  
Query raised by State Government (Orissa) on:01/05/2024  
Query raised by Nodal Officer (Orissa) on:24/01/2023  
Replied by Circle(Baripada) on:01/07/2023  
Query raised by Nodal Officer (Orissa) on:07/09/2023  
Replied by Circle(Baripada) on:28/12/2023  
Query raised by Nodal Officer (Orissa) on:31/01/2024  
Replied by Circle(Baripada) on:17/02/2024  
Query raised by Nodal Officer (Orissa) on:09/05/2024  
Replied by Circle() on:  
Query raised by Circle (Baripada) on:10/11/2022  
Replied by DFO (Balasore Wildlife) on:29/12/2022  
Query raised by Circle (Baripada) on:30/01/2023  
Replied by DFO (Balasore Wildlife) on:23/06/2023  
Query raised by Circle (Baripada) on:12/09/2023  
Replied by DFO (Balasore Wildlife) on:04/12/2023  
Query raised by Circle (Baripada) on:15/12/2023  
Replied by DFO (Balasore Wildlife) on:16/12/2023  
Query raised by Circle (Baripada) on:12/02/2024  
Replied by DFO (Balasore Wildlife) on:16/02/2024  
Query raised by Circle (Baripada) on:17/05/2024  
Replied by DFO () on:  
Query raised by DFO (Balasore Wildlife) on:13/06/2022  
Replied by UA on :05/08/2022  
Query raised by DFO (Balasore Wildlife) on:12/09/2022  
Replied by UA on :28/10/2022  
Query raised by DFO (Balasore Wildlife) on:28/10/2022  
Replied by UA on :29/10/2022  
Query raised by DFO (Balasore Wildlife) on:15/12/2022  
Replied by UA on :17/12/2022  
Query raised by DFO (Balasore Wildlife) on:06/03/2023  
Replied by UA on :23/06/2023  
Query raised by DFO (Balasore Wildlife) on:19/10/2023  
Replied by UA on :28/11/2023  
Query raised by DFO (Balasore Wildlife) on:12/02/2024  
Replied by UA on :15/02/2024  
Query raised by DFO (Balasore Wildlife) on:29/05/2024  
Replied by UA on :30/01/2025  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .