Sno.State NameProposal No.RO/Ministry File NumberProposal NameCategoryUser Agency NameArea (ha.)Proposal StatusImportant DatesAllocation of Fresh forest land (Form-A) Part-IView Report (Part-II to Part-V and Stage-I Clearances)Stage-II Approval on
1 Arunachal Pradesh FP/AR/TRANS/41550/2019 3-AN-C-039/2021-GHY Construction of 33 Kv line from Yachuli to Hapoli under Comprehensive scheme for strengthening of Transmission & distribution in Arunachal Pradesh. Transmission Line DEPARTMENT OF POWER ARUNACHAL PRADESH 29.14 APPROVED
Proposal received(at Nodal Officer)electronically on : 08 Aug 2019
Stage-I Approval on : 28 Feb 2022
Compliance Report Submitted by User Agency on : 17 Aug 2022
18 Aug 2022
2 Arunachal Pradesh FP/AR/TRANS/40560/2019 3-AN-A-022/2021-GHY Construction of 132 KV S/C on D/C Transmission line from Naharlagun to Gerukamukh under Comp.Scheme T & D in Arunachal Pradesh. Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 230.44 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 Jun 2019
Stage-I Approval on : 17 Mar 2022
Compliance Report Submitted by User Agency on : 19 Jul 2022
20 Jul 2022
3 Arunachal Pradesh FP/AR/TRANS/142551/2021 3-AN-C-088/2022/GHY Construction of 132kV D/C LILO of one circuit of Pare HEP – North Lakhimpur (AEGCL) line at Nirjuli (POWERGRID) substation in Arunachal Pradesh Transmission Line VAPI II-NORTH LAKHIMPUR TRANSMISSION LIMITED 30.95 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 May 2021
Stage-I Approval on : 30 Mar 2022
Compliance Report Submitted by User Agency on : 11 Jul 2022
15 Jul 2022
4 Arunachal Pradesh FP/AR/TRANS/43444/2019 3-AN-A-011/2021-GHY Construction of 132 kV S/C (on D/C tower) Khupi to Seppa transmission line under Comprehensive Scheme for Strengthening of Transmission and Distribution System in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 130.062 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Dec 2019
Stage-I Approval on : 08 Mar 2022
Compliance Report Submitted by User Agency on : 30 Jun 2022
11 Jul 2022
5 Arunachal Pradesh FP/AR/TRANS/144909/2021 FNO 3 AN C/092/2022/GHY Construction of 132kV D/C Roing-Chapakhowa Transmission Line under NERSS-X. Transmission Line POWERGRID 15.034 APPROVED
Proposal received(at Nodal Officer)electronically on : 17 Jul 2021
Stage-I Approval on : 09 May 2022
Compliance Report Submitted by User Agency on : 06 Jul 2022
11 Jul 2022
6 Arunachal Pradesh FP/AR/TRANS/140671/2021 3-ANC052/2021-GHY Construction of 132 kV D/C Pare HEP to Lakhimpur Transmission Line Transmission Line VAPI II-NORTH LAKHIMPUR TRANSMISSION LIMITED 24.602 APPROVED
Proposal received(at Nodal Officer)electronically on : 05 Apr 2021
Stage-I Approval on : 09 Dec 2021
Compliance Report Submitted by User Agency on : 16 May 2022
31 May 2022
7 Arunachal Pradesh FP/AR/ROAD/41095/2019 F. no. 3-AN A 015/2021-GHY DIVERSION OF FOREST LAND FOR THE CONSTRUCTION OF TATO TO MENCHUKA ROAD FROM 0+000 KM TO 41+275 KM BY BRO BRAMHANK UNDER WEST SIANG DISTRICT IN THE STATE OF ARUNACHAL PRADESH Road BRO 49.53 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jul 2019
Stage-I Approval on : 22 Jun 2021
Compliance Report Submitted by User Agency on : 09 Dec 2021
22 Feb 2022
8 Arunachal Pradesh FP/AR/TRANS/41716/2019 F. No 3 - AN A 071/2020 - SHI Construction of 132KV transmission line from Naharlagun to Sagalee under comprehensive scheme for strengthening of T&D system in Arunachal Pradesh. Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 89.54 APPROVED
Proposal received(at Nodal Officer)electronically on : 22 Aug 2019
Stage-I Approval on : 31 Aug 2021
Compliance Report Submitted by User Agency on : 28 Jan 2022
09 Feb 2022
9 Arunachal Pradesh FP/AR/TRANS/35036/2018 F. no. 3-AN A 093/2019-SHI Construction of 132 kV line from Rillo (Pakke Kessang) to Seijosa under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 119.7 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jul 2018
Stage-I Approval on : 22 Feb 2021
Compliance Report Submitted by User Agency on : 21 Aug 2021
21 Jan 2022
10 Arunachal Pradesh FP/AR/TRANS/35487/2018 F. No 3 - AN C 083/2019 - SHI Construction of 132kV T/L from Deomali to Khonsa under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 79.73 APPROVED
Proposal received(at Nodal Officer)electronically on : 31 Aug 2018
Stage-I Approval on : 30 Jul 2021
Compliance Report Submitted by User Agency on : 12 Jan 2022
12 Jan 2022
11 Arunachal Pradesh FP/AR/VELEC/41943/2019 F. No 3 AN C 077/2020-SHI Construction of 33 kV line from Jairampur to Manmao under Comprehensive Transmission and Distribution scheme in Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 36.65 APPROVED
Proposal received(at Nodal Officer)electronically on : 09 Sep 2019
Stage-I Approval on : 25 Aug 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
28 Dec 2021
12 Arunachal Pradesh FP/AR/TRANS/42021/2019 F. No 3 - AN C 038/2021-GHY Construction of 33 kV T/L from Changlang(Yatdam) to Khimyang(Kantang) under Comprehensive Scheme for strengthening of Transmission and Distribution in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER ARUNACHAL PRADESH 36.483 APPROVED
Proposal received(at Nodal Officer)electronically on : 13 Sep 2019
Stage-I Approval on : 31 Aug 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
24 Dec 2021
13 Arunachal Pradesh FP/AR/VELEC/35705/2018 F. No 3 AN C 070/2020-SHI Construction of 33 kV line from Namsai (POWERGRID) to Chowkham (DoP) under Comprehensive Transmission and Distribution scheme of Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 41.46 APPROVED
Proposal received(at Nodal Officer)electronically on : 21 Nov 2018
Stage-I Approval on : 16 Aug 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
24 Dec 2021
14 Arunachal Pradesh FP/AR/TRANS/40516/2019 F. No 3 - AN C 078/2020 - SHI Construction of 132 Kv S/C on D/C transmission line from Naharlagun to Banderdewa under Comprehensive scheme for strengthening of T & D system in Arunachal Pradesh. Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 34.33 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Jun 2019
Stage-I Approval on : 31 Aug 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
24 Dec 2021
15 Arunachal Pradesh FP/AR/TRANS/41999/2019 F. No 3 - AN A 021/2021 - GHY Construction of 33kV T/L from Deomali to Kanubari under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER ARUNACHAL PRADESH 73.7 APPROVED
Proposal received(at Nodal Officer)electronically on : 12 Sep 2019
Stage-I Approval on : 31 Aug 2021
Compliance Report Submitted by User Agency on : 21 Dec 2021
24 Dec 2021
16 Arunachal Pradesh FP/AR/VELEC/36662/2018 F. No 3 AN A 100/2019-SHI Proposal for diversion of 63.85 Ha. forest land for construction of 33 kV Khupi Thrizino distribution line Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 63.85 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Oct 2018
Stage-I Approval on : 19 Feb 2020
Compliance Report Submitted by User Agency on : 12 Nov 2021
12 Nov 2021
17 Arunachal Pradesh FP/AR/TRANS/33413/2018 3-AN A 096/2019-SHI Construction of 132 kV line from Likabali to Niglok under Comprehensive Scheme for Strengthening of Transmission & Distribution system in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 135.47 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 May 2018
Stage-I Approval on : 06 Mar 2020
Compliance Report Submitted by User Agency on : 10 Sep 2021
12 Nov 2021
18 Arunachal Pradesh FP/AR/TRANS/44311/2020 3AN A 014/2021-GHY Construction of 132kV S/C (on D/C tower) Seppa to Bameng transmission line under Comprehensive Scheme for Strengthening of Transmission and Distribution System in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 78.548 APPROVED
Proposal received(at Nodal Officer)electronically on : 30 Jan 2020
Stage-I Approval on : 08 Jul 2021
Compliance Report Submitted by User Agency on : 16 Sep 2021
20 Sep 2021
19 Arunachal Pradesh FP/AR/SubStation/43214/2019 F. No. 3 AN B 010/2021/GHY Proposal for diversion of 0.4 Ha forest land for construction of 33/11kV Sub-station at Diyun. Sub Station DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 0.4 APPROVED
Proposal received(at Nodal Officer)electronically on : 06 Dec 2019
Stage-I Approval on : 06 May 2021
Compliance Report Submitted by User Agency on : 16 Sep 2021
20 Sep 2021
20 Arunachal Pradesh FP/AR/TRANS/34374/2018 3-ANA 086/2019-SHI Construction of 132 kV S/C Transmission Line on D/C Tower from Gerukamukh to Likabali Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 141.14 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Jun 2018
Stage-I Approval on : 27 Dec 2019
Compliance Report Submitted by User Agency on : 10 Sep 2021
16 Sep 2021
21 Arunachal Pradesh FP/AR/VELEC/32244/2018 F. No 3 - AN A 053/2020 - SHI Proposal for diversion of 65.87 Ha.forest land for construction of 33KV SEPPA PIPU distribution line Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 65.87 APPROVED
Proposal received(at Nodal Officer)electronically on : 27 Mar 2018
Stage-I Approval on : 06 May 2021
Compliance Report Submitted by User Agency on : 10 Sep 2021
15 Sep 2021
22 Arunachal Pradesh FP/AR/VELEC/34804/2018 F. No 3 AN C 068/2020-SHI Proposal for diversion of 30.76 Ha.forest land for construction of 33KV Bameng to Khenewa distribution line Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 30.76 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jul 2018
Stage-I Approval on : 29 Apr 2021
Compliance Report Submitted by User Agency on : 10 Sep 2021
15 Sep 2021
23 Arunachal Pradesh FP/AR/TRANS/34390/2018 F. No 3 - AN A 102/2019 - SHI Construction of 132 kV line from Seppa to Rillo under Comprehensive Scheme for Strengthening of Transmission and Distribution in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 94.18 APPROVED
Proposal received(at Nodal Officer)electronically on : 26 Jun 2018
Stage-I Approval on : 29 Apr 2021
Compliance Report Submitted by User Agency on : 10 Sep 2021
15 Sep 2021
24 Arunachal Pradesh FP/AR/VELEC/33398/2018 3-ANC 039/2019-SHI Construction of 33 kv Transmission Line from Jang to Thingbu Under Comprehensive Scheme for strengthening T & D System in Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 28.67 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 May 2018
Stage-I Approval on : 03 Dec 2019
Compliance Report Submitted by User Agency on : 23 Aug 2021
31 Aug 2021
25 Arunachal Pradesh FP/AR/TRANS/33964/2018 3-AN A 029/2020-SHI construction of 132KV transmission line from Riloh to Sagalee under comprehensive scheme for strengthening of T&D system in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 89.588 APPROVED
Proposal received(at Nodal Officer)electronically on : 02 Jun 2018
Stage-I Approval on : 21 Oct 2020
Compliance Report Submitted by User Agency on : 24 Aug 2021
31 Aug 2021
26 Arunachal Pradesh FP/AR/VELEC/33401/2018 3-ANC 042/2019-SHI Construction of 33 kv Transmission Line from Tawang to Y-Junction Under Comprehensive Scheme for strengthening T & D System in Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 17.04 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 May 2018
Stage-I Approval on : 29 Nov 2019
Compliance Report Submitted by User Agency on : 23 Aug 2021
31 Aug 2021
27 Arunachal Pradesh FP/AR/VELEC/30346/2017 3-ANC 041/2018-SHI Construction of 33KV Transmission Line from Jang to Mukto under Comprehensive Scheme for strenghtening of T&D System in Arunachal Pradesh. Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 20.4795 APPROVED
Proposal received(at Nodal Officer)electronically on : 20 Nov 2017
Stage-I Approval on : 31 Dec 2019
Compliance Report Submitted by User Agency on : 21 Aug 2021
31 Aug 2021
28 Arunachal Pradesh FP/AR/VELEC/29965/2017 3-MN C 072/2019-SHI CONSTRUCTION OF 33 KV LINE FROM TENZINGAON TO BALEMU UNDER COMPREHENSIVCE SCHEME FOR STRENGETHENING OF TRANSMISSION AND DISTRIBUTION IN ARUNACHAL PRADESH Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 49.486 APPROVED
Proposal received(at Nodal Officer)electronically on : 31 Oct 2017
Stage-I Approval on : 02 Jan 2020
Compliance Report Submitted by User Agency on : 23 Aug 2021
31 Aug 2021
29 Arunachal Pradesh FP/AR/VELEC/35672/2018 3-ANC 091/2019-SHI Construction of 33 kV line from Namsai (Deobeel) s/s to Namsai (Manmow) S/s under comprehensive scheme in Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 9.11 APPROVED
Proposal received(at Nodal Officer)electronically on : 04 Sep 2018
Stage-I Approval on : 29 Jan 2020
Compliance Report Submitted by User Agency on : 23 Aug 2021
31 Aug 2021
30 Arunachal Pradesh FP/AR/VELEC/33404/2018 3-ANC 040/2019-SHI Construction of 33 kv Transmission Line from Y-Junction to Klemta Under Comprehensive Scheme for strengthening T & D System in Arunachal Pradesh Village Electricity DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 4.92 APPROVED
Proposal received(at Nodal Officer)electronically on : 01 May 2018
Stage-I Approval on : 29 Aug 2019
Compliance Report Submitted by User Agency on : 23 Aug 2021
31 Aug 2021
31 Arunachal Pradesh FP/AR/TRANS/35450/2018 3-ANC 103/2019-SHI Construction of 132 kV Transmission Line from Pasighat (old) to Pasighat (new) under Comprehensive Scheme in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 35.591 APPROVED
Proposal received(at Nodal Officer)electronically on : 28 Aug 2018
Stage-I Approval on : 31 Dec 2019
Compliance Report Submitted by User Agency on : 21 Aug 2021
20 Apr 2021
32 Arunachal Pradesh FP/AR/TRANS/38414/2019 3-ANC 106/2019-SHI Construction of 132kV LILO of Along to Daporjio at Basar Substation under Comprehensive Scheme for Strengthening of Transmission & Distribution system in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 6.2289 APPROVED
Proposal received(at Nodal Officer)electronically on : 18 Jan 2019
Stage-I Approval on : 29 Jan 2020
Compliance Report Submitted by User Agency on : 21 Aug 2021
31 Mar 2021
33 Arunachal Pradesh FP/AR/TRANS/45252/2020 3-AN C 038/2019-SHI Construction of 132kV SC Transmission line from Jairampur to miao under Comprehensive scheme of Transmission and Distribution system in Arunachal Pradesh. Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 93.366 APPROVED
Proposal received(at Nodal Officer)electronically on : 07 Apr 2020
Stage-I Approval on : 12 Sep 2019
Compliance Report Submitted by User Agency on : 27 Apr 2021
31 Mar 2021
34 Arunachal Pradesh FP/AR/SubStation/34957/2018 3-AN B 077/2019-SHI Proposal for Diversion of 2 Ha. Forest Land for Construction of 132/33kV Sub-Station at Seijosa Sub Station DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 2 APPROVED
Proposal received(at Nodal Officer)electronically on : 25 Jul 2018
Stage-I Approval on : 23 Jan 2020
Compliance Report Submitted by User Agency on : 27 Apr 2021
30 Sep 2020
35 Arunachal Pradesh FP/AR/TRANS/34226/2018 3-ANC 062/2019-SHI Construction of 132KV transmission line from Chimpu to Holongi under comprehensive scheme for strengthening of T&D system in Arunachal Pradesh Transmission Line DEPARTMENT OF POWER GOVT OF ARUNACHAL PRADESH 39.468 APPROVED
Proposal received(at Nodal Officer)electronically on : 15 Jun 2018
Stage-I Approval on : 04 Nov 2019
Compliance Report Submitted by User Agency on : 24 Aug 2021
24 Jun 2020
Please wait ...