Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Dhenkanal)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
04/02/2015
|
1. Hard copy of the proposal with state sl no.
2. Authenticated land schedule of both forest and non forest land.
3. Index map of village sheet along with forest plots demarcated by proper colour.
4. To co-ordinate the Tahasildar/Range officer concerned for joint verification and tree enumeration etc.
|
|
2
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Dhenkanal)
|
27/04/2015
|
Dear Sir,
The point-wise ‘Essential Details Sought for’ has been duly complied for Birasal Chromite Mines in Kankadahad Block, District Dhenkanal of OMC.
S.K. Das
Dy. General Manager (Geo)
Authorised Signatory
|
|
3
|
DFO (Dhenkanal)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
14/05/2015
|
1. Index map of the village sheet along with the forest plots demarcated by proper color mentioned.
2. To co-ordinate the Tahasildar/Range Officer concerned regarding joint verification, tree enumeration etc.
3. GPS reading of the proposed bore area.
4. Proposed bore point should be mentioned in Topo sheet.
5. To contact the undersigned for compliance/Site inspection etc.
|
|
4
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Dhenkanal)
|
27/05/2015
|
Dear Sir,
The point-wise ‘Essential Details Sought for’ has been duly complied for Birasal Chromite Mines in Hatadihi Block, District Dhenkanal of OMC.
S.K. Das
Dy. General Manager (Geo)
Authorised Signatory
|
|
5
|
DFO (Dhenkanal)
|
EDS
|
User Agency (fdp.omc@gmail.com)
|
08/06/2015
|
you are requested to co-ordinate the Tahasildar/Range Officer concerned regarding joint verification, tree enumeration etc for the purpose. After completion of the above task, the undersigned will inspect the proposed drilling point.
|
|
6
|
User Agency (fdp.omc@gmail.com)
|
REPLY
|
DFO (Dhenkanal)
|
27/08/2015
|
Sir,The compliance to the observation made in the letter dt 8.6.2015 is submitted herewith in PDF format attached.
|
|
7
|
CF (Angul)
|
EDS
|
DFO (Dhenkanal)
|
16/09/2015
|
To rectify the figure in proposal of Birasal Chromite mine
|
|
8
|
DFO (Dhenkanal)
|
REPLY
|
CF (Angul)
|
28/10/2015
|
Sir ,
Please, in continuation of this Memo No.6892 dt.29.09.2015, the revised letter is enclosed herewith.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Angul)
|
09/11/2015
|
Three objection are found.
|
|
10
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
20/11/2015
|
.
|
|