TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/TN/ROAD/155502/2022              (ii). Name of Project for which Forest Land is required : Construction of Grade Seperator connecting Medavakkam – Sholinganallur road junction, Medavakkam - Mambakkam road junction, Mount – Medavakkam Road junction in Marmalong Bridge – Irumbuliyur Road at M              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This is an important project connecting Velachery to Irumbuliyur road, Since the Grade Separator project will eliminate traffic conflict on keelkattalai junction, Mambakkam junction, and shollinganallur junction. This Arterial link will be a critical link for bypassing traffic to reach Chennai C              (iv). File no. : 4-TNB117/2024-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.536
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TN/ROAD/155502/202220/05/202215/06/2022   29/06/2022   18/07/2022   29/08/2022 Chengalpattu,Kancheepuram :13/09/2022Chennai:
  03/02/2023 (Chengalpattu,Kancheepuram)

Tamil Nadu:
22/06/2023
Tamil Nadu:
27/07/2023
Chennai:
08/01/2024
04/04/2024
By :Regional Office
Tamil Nadu
07/02/2025
21/02/2025
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
   Query raised by Nodal Officer (Tamil Nadu) on:30/06/2023  
Replied by Circle(Chennai) on:22/07/2023  
Query raised by Circle (Chennai) on:20/02/2023  
Replied by DFO (Chengalpattu,Kancheepuram) on:20/04/2023  
Query raised by Circle (Chennai) on:25/04/2023  
Replied by DFO (Chengalpattu,Kancheepuram) on:16/05/2023  
Query raised by Circle (Chennai) on:03/07/2023  
Replied by DFO (Chengalpattu,Kancheepuram) on:21/07/2023  
Query raised by DFO (Chengalpattu,Kancheepuram) on:28/04/2023  
Replied by UA on :05/05/2023  
Query raised by DFO (Chengalpattu,Kancheepuram) on:05/07/2023  
Replied by UA on :13/07/2023  
NOTE:- Stage-II Approval accorded by : Regional Office .