Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
20/02/2023
|
Additional details called for.
|
|
2
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
20/04/2023
|
Madam reply submitted
|
|
3
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
25/04/2023
|
Undertaking from the User Agency for the construction of new compound wall after demolition of existing compound wall may be obtained and submitted.
|
|
4
|
DFO (Chengalpattu,Kancheepuram)
|
EDS
|
User Agency (divisiontwocmdpchennai15@gmail.com)
|
28/04/2023
|
Undertaking from the User Agency for the construction of new compound wall after demolition of existing compound wall may be obtained and submitted.
|
|
5
|
User Agency (divisiontwocmdpchennai15@gmail.com)
|
REPLY
|
DFO (Chengalpattu,Kancheepuram)
|
05/05/2023
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
16/05/2023
|
Madam, Reply submitted
|
|
7
|
Nodal Officer
|
EDS
|
CF (Chennai)
|
30/06/2023
|
The CF is requested to upload the details vide PCCF ref. No. TS3-15962-2022, dt. 28.06.2023 for further action.
|
|
8
|
CF (Chennai)
|
EDS
|
DFO (Chengalpattu,Kancheepuram)
|
03/07/2023
|
Reply for query raised by the PCCF may be furnished.
|
|
9
|
DFO (Chengalpattu,Kancheepuram)
|
EDS
|
User Agency (divisiontwocmdpchennai15@gmail.com)
|
05/07/2023
|
User agency request to provide equivalent area of non forest land to the Forest Department as CA land as instructed by the PCCF
|
|
10
|
User Agency (divisiontwocmdpchennai15@gmail.com)
|
REPLY
|
DFO (Chengalpattu,Kancheepuram)
|
13/07/2023
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Chengalpattu,Kancheepuram)
|
REPLY
|
CF (Chennai)
|
21/07/2023
|
Submitted
|
|
12
|
CF (Chennai)
|
REPLY
|
Nodal Officer
|
22/07/2023
|
Reply for the queries raised by the PCCF vide letter No.TS3-15962-2022, Dated: 28.06.2023
|
|