Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Udaipur (South) Territorial)
|
EDS
|
User Agency (dineshengineersltd@gmail.com)
|
03/09/2020
|
EDS raised
|
|
2
|
User Agency (dineshengineersltd@gmail.com)
|
REPLY
|
DFO (Udaipur (South) Territorial)
|
12/09/2020
|
The correction have been made as per the instruction received
|
|
3
|
State secretary
|
EDS
|
Nodal Officer
|
23/12/2020
|
please eds letter dated 23.12.20
|
|
4
|
Nodal Officer
|
EDS
|
CF (Udaipur)
|
23/12/2020
|
Please find attached EDS for compliance.
|
|
5
|
CF (Udaipur)
|
EDS
|
DFO (Udaipur (South) Territorial)
|
28/12/2020
|
Please find attached EDS for compliance.
|
|
6
|
DFO (Udaipur (South) Territorial)
|
REPLY
|
CF (Udaipur)
|
30/12/2020
|
reply filled
|
|
7
|
CF (Udaipur)
|
REPLY
|
Nodal Officer
|
01/01/2021
|
eds done
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
01/02/2021
|
The EDS compliance report is attached.
|
|