TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/HR/ROAD/156170/2022              (ii). Name of Project for which Forest Land is required : Diversion of 0.98 ha. of Forest land for Construction of Link Road from Thapli-Barisher Road to Village -Koti in Tehsil-Morni, Distt. – Panchkula (HR).              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Diversion of 0.98 ha. of Forest land for Construction of Link Road from Thapli-Barisher Road to Village -Koti in Tehsil-Morni, Distt. – Panchkula (HR).              (iv). File no. : 9-HRB163-2023-CHA              (v). State : Haryana              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.98
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/HR/ROAD/156170/202203/06/202228/06/2022   01/07/2022   08/07/2022   13/07/2022 Morrni-Pinjore :18/07/2022North Circle Panchkula:
  19/08/2022 (Morrni-Pinjore)

Haryana:
07/09/2022
Haryana:
06/09/2023
Chandigarh:
29/09/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chandigarh) on:10/11/2023  
Replied by State Government(Haryana) on:11/07/2024  
Query raised by Regional Office (Chandigarh) on:07/08/2024  
Query raised by State Government (Haryana) on:14/11/2023  
Replied by Nodal Officer (Haryana) on:08/07/2024  
Query raised by State Government (Haryana) on:12/08/2024  
Query raised by Nodal Officer (Haryana) on:03/10/2022  
Replied by Circle(North Circle Panchkula) on:20/10/2022  
Query raised by Nodal Officer (Haryana) on:09/12/2022  
Replied by Circle(North Circle Panchkula) on:09/01/2023  
Query raised by Nodal Officer (Haryana) on:24/03/2023  
Replied by Circle(North Circle Panchkula) on:17/04/2023  
Query raised by Nodal Officer (Haryana) on:17/05/2023  
Replied by Circle(North Circle Panchkula) on:10/08/2023  
Query raised by Nodal Officer (Haryana) on:17/11/2023  
Replied by Circle(North Circle Panchkula) on:23/04/2024  
Query raised by Nodal Officer (Haryana) on:03/05/2024  
Replied by Circle(North Circle Panchkula) on:21/06/2024  
Query raised by Nodal Officer (Haryana) on:12/08/2024  
Replied by Circle(North Circle Panchkula) on:13/08/2024  
Query raised by Nodal Officer (Haryana) on:06/09/2024  
Replied by Circle() on:  
Query raised by Circle (North Circle Panchkula) on:04/10/2022  
Replied by DFO (Morrni-Pinjore) on:20/10/2022  
Query raised by Circle (North Circle Panchkula) on:13/12/2022  
Replied by DFO (Morrni-Pinjore) on:07/01/2023  
Query raised by Circle (North Circle Panchkula) on:24/03/2023  
Replied by DFO (Morrni-Pinjore) on:13/04/2023  
Query raised by Circle (North Circle Panchkula) on:18/05/2023  
Replied by DFO (Morrni-Pinjore) on:02/08/2023  
Query raised by Circle (North Circle Panchkula) on:20/11/2023  
Replied by DFO (Morrni-Pinjore) on:16/04/2024  
Query raised by Circle (North Circle Panchkula) on:06/05/2024  
Replied by DFO (Morrni-Pinjore) on:20/06/2024  
Query raised by Circle (North Circle Panchkula) on:10/09/2024  
Replied by DFO () on:  
NOTE:- Proposal is pending at DFO due to EDS raised by Regional Office .
Close(X)
Close(X)