Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
09/12/2021
|
query raised by dfo
|
|
2
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
09/12/2021
|
The correction have been made as per the instruction received
|
|
3
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
03/01/2022
|
Case Down
|
|
4
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
03/01/2022
|
Letter attached.
|
|
5
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
14/01/2022
|
query raised by dfo
|
|
6
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
15/03/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
24/03/2022
|
essentail sought out
|
|
8
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
24/03/2022
|
essential sought out
|
|
9
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
24/05/2022
|
forward to DFO for upload the inforamtion
|
|
10
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
27/05/2022
|
Letter attached.
|
|
11
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
30/06/2022
|
query raised by dfo
|
|
12
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
26/07/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
28/07/2022
|
plz attach copy of letter
|
|
14
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
04/08/2022
|
plz attach copy of letter by which correction has been made
|
|
16
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
16/08/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
23/08/2022
|
essentail sought out
|
|
18
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
24/08/2022
|
Essential sought out
|
|
19
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
30/09/2022
|
Case Down
|
|
20
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
30/09/2022
|
Letter attached.
|
|
21
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
03/10/2022
|
Query raised by dfo
|
|
22
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
26/10/2022
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
31/10/2022
|
Essential sought out
|
|
24
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
04/11/2022
|
Query replied.
|
|
25
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
21/03/2023
|
Case down
|
|
26
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
22/03/2023
|
Letter attached.
|
|
27
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
25/04/2023
|
Dfo letter court case judgement report
|
|
28
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
26/04/2023
|
Dfo letter court case judgement report
|
|
29
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
12/05/2023
|
Case down - EDS Nodal Office
|
|
30
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
15/05/2023
|
Case down
|
|
31
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
16/05/2023
|
Corrections have been made as per instructions received
|
|
32
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
16/05/2023
|
EDS Replied by DFO
|
|
33
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
19/05/2023
|
Case down - EDS pending
|
|
34
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
23/05/2023
|
Case Down
|
|
35
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
25/05/2023
|
Please make corrections, upload details with supporting documents in part -1 as required in point no. 1,2,7,8,10,12 of the query raised.
|
|
36
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
30/05/2023
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
06/06/2023
|
please submit/upload - Undertaking for No retail outlet present on either side within 1 Km from the proposed site.
|
|
38
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
13/06/2023
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
20/07/2023
|
Undertaking certificate regarding No Toll plaza within 1000 mtrs on both sides of the proposed site needs to be submitted/ uploaded. EDS for toll plaza was also raised on date 25/05/2023.
|
|
40
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
23/08/2023
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
08/09/2023
|
1.Total period for which forest land is proposed now corrected as 15 by UA.
2. Temporary employment is justified by UA
4. Separate NPV calculation sheet uploaded
5. NPV rates taken as per as per vegetation density
6.All undertakings submitted by UA uploaded
7.Undertaking High tension wire uploaded on portal
8.Undertaking certificate No Toll Plaza uploaded
10.Undertaking for No LPG godown uploaded
11. CA sheme uploaded along with plantation operation details
|
|
42
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
12/09/2023
|
EDS replied
|
|
43
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
15/09/2023
|
current recommendation of CCF and DFO needs to be uploaded in light of of Hon'ble Supreme Court judgement dated 21-07-2022
|
|
44
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
19/09/2023
|
current recommendation of CCF and DFO needs to be uploaded in light of of Hon'ble Supreme Court judgement dated 21-07-
|
|
45
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
10/10/2023
|
DFO Letter
|
|
46
|
CF (South Circle Gurgaon)
|
REPLY
|
Nodal Officer
|
26/10/2023
|
EDS Reply attached.
|
|
47
|
Nodal Officer
|
EDS
|
CF (South Circle Gurgaon)
|
15/12/2023
|
Case down
|
|
48
|
CF (South Circle Gurgaon)
|
EDS
|
DFO (Faridabad)
|
27/12/2023
|
case down
|
|
49
|
DFO (Faridabad)
|
EDS
|
User Agency (rosysabharwal19@gmail.com)
|
06/06/2024
|
Letter attached- order
|
|
50
|
User Agency (rosysabharwal19@gmail.com)
|
REPLY
|
DFO (Faridabad)
|
12/11/2024
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Faridabad)
|
REPLY
|
CF (South Circle Gurgaon)
|
04/07/2025
|
project is not site specific. So case not recommended. letter attached
|
|