TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/26451/2017              (ii). Name of Project for which Forest Land is required : Diversion of Protected Forest Land for Rehabilitation and Up-gradation to 4-lane with paved shoulders configuration from Naviganj to Mitrason section (Km 289.000 to Km 356.000 )Package-IV section of National Highway-91 in Kannuj District in the State of Uttar Pradesh              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The Project involves capacity augmentation to 4 lane with paved Shoulders configuration from Naviganj to Mitrason section of NH-91.Road side Plantation Naviganj(Km 289.000) to Mitrason(km 356.000)& Kannuj Bypass except other Bypasses &Realignment in Kannuj District is notified as Protected forest              (iv). File no. : 8B/UP/06/25/2017/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 99.328
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/26451/201731/05/201707/09/2017  01/09/2017  22/08/2017  01/08/2017  05/07/2017  04/07/2017  30/06/2017  29/06/2017  20/06/2017  31/05/2017   07/09/2017  07/09/2017  31/08/2017  17/08/2017  27/07/2017  05/07/2017  03/07/2017  30/06/2017  28/06/2017  10/06/2017   08/09/2017   16/01/2018 Kannauj :16/01/2018Kanpur Circle Kanpur:
  16/02/2018 (Kannauj)

Uttar Pradesh:
17/02/2018
Uttar Pradesh:
20/02/2018
Lucknow:
05/03/2018
12/06/2018
By :Regional Office
Uttar Pradesh
18/04/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:16/04/2018  
Replied by State Government(Uttar Pradesh) on:16/05/2018  
Query raised by State Government (Uttar Pradesh) on:17/04/2018  
Replied by Nodal Officer (Uttar Pradesh) on:15/05/2018  
Query raised by Nodal Officer (Uttar Pradesh) on:17/04/2018  
Replied by Circle(Kanpur Circle Kanpur) on:15/05/2018  
Query raised by Circle (Kanpur Circle Kanpur) on:08/05/2018  
Query raised by DFO (Kannauj) on:27/01/2018  
Replied by UA on :12/02/2018  
Query raised by DFO (Kannauj) on:09/05/2018  
Replied by UA on :14/05/2018  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:10/05/2022  
Replied by State Government(Uttar Pradesh) on:20/06/2023  
Query raised by Regional Office (Lucknow) on:31/07/2023  
Replied by State Government(Uttar Pradesh) on:04/04/2024  
Query raised by Regional Office (Lucknow) on:24/06/2024  
Query raised by State Government (Uttar Pradesh) on:11/05/2022  
Replied by Nodal Officer (Uttar Pradesh) on:20/06/2023  
Query raised by State Government (Uttar Pradesh) on:11/08/2023  
Replied by Nodal Officer (Uttar Pradesh) on:04/04/2024  
Query raised by State Government (Uttar Pradesh) on:08/07/2024  
Query raised by Nodal Officer on:19/05/2022  
Replied by UA on :01/06/2023  
Query raised by Nodal Officer on:14/08/2023  
Replied by UA on :26/12/2023  
Query raised by Nodal Officer on:28/12/2023  
Replied by UA on :08/03/2024  
Query raised by Nodal Officer on:12/03/2024  
Replied by UA on :13/03/2024  
Query raised by Nodal Officer on:02/04/2024  
Replied by UA on :03/04/2024  
Query raised by Nodal Officer on:08/07/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .