TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/ROAD/144793/2021              (ii). Name of Project for which Forest Land is required : Construction of 6 Lane 'Ganga Expressway' (Expandable upto 8 Lane), an access controlled Green field Expressway in district Meerut, Hapur, Bulandsahar, Amroha, Sambhal, Badaun, Shahjahanpur, Hardoi, Unnao, Raibareli, Partapgarh & Paryagraj, (CH 7+900-CH 601+847 Km) total length 593.947 Kms.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : An access controlled Greenfield Project with general ROW of 120 mt. Total 121.4716 Ha of Forest Land falls in 9 Districts i.e.Hapur(2.0342Ha),Amroha(1.6800Ha),Sambhal (4.0520Ha),Badaun(4.9257Ha),Shahjahanpur (3.9070 Ha),Hardoi(6.2873Ha),Unnao (67.7839Ha),Raibareli(29.7266Ha), Partapgarh(1.0749Ha)              (iv). File no. : 8B/UP/06/295/2021/FC              (v). State : Uttar Pradesh              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 121.4716
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UP/ROAD/144793/202113/10/202118/10/2021   26/10/2021   27/10/2021   18/11/2021 Social Forestry Division Meerut :21/11/2021
Forest Division Hapur :21/11/2021
Social Forestry Division Bulandshahar :21/11/2021
Social Forestry Division J.P. Nagar (Amroha) :21/11/2021
Social Forestry Division Sambhal :21/11/2021
Social Forestry Division Budaun :21/11/2021
Social Forestry Division Shahjahanpur :21/11/2021
Social Forestry Division Hardoi :21/11/2021
Social Forestry Division Unnao :21/11/2021
Social Forestry Division Rae Bareli :21/11/2021
Social Forestry Division Pratapgarh :21/11/2021
Social Forestry Division Allahabad :21/11/2021
Meerut Circle Meerut:
  24/11/2021 (Social Forestry Division Bulandshahar)

Meerut Circle Meerut:
  24/11/2021 (Forest Division Hapur)

Allhabad Circle Allhabad:
  25/11/2021 (Social Forestry Division Pratapgarh)

Moradabad Circle Moradabad:
  26/11/2021 (Social Forestry Division Sambhal)

Moradabad Circle Moradabad:
  26/11/2021 (Social Forestry Division J.P. Nagar (Amroha))

Allhabad Circle Allhabad:
  27/11/2021 (Social Forestry Division Allahabad)

Lucknow Circle Lucknow:
  27/11/2021 (Social Forestry Division Rae Bareli)

Lucknow Circle Lucknow:
  27/11/2021 (Social Forestry Division Unnao)

Lucknow Circle Lucknow:
  27/11/2021 (Social Forestry Division Hardoi)

Meerut Circle Meerut:
  29/11/2021 (Social Forestry Division Meerut)

Bareilly Circle Bareilly:
  30/11/2021 (Social Forestry Division Shahjahanpur)

Bareilly Circle Bareilly:
  30/11/2021 (Social Forestry Division Budaun)

Uttar Pradesh:
08/12/2021
Uttar Pradesh:
13/12/2021
Lucknow:
22/12/2021
16/06/2022
By :Regional Office
Uttar Pradesh
01/03/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:17/01/2022  
Replied by State Government(Uttar Pradesh) on:06/04/2022  
Query raised by Regional Office (Lucknow) on:29/04/2022  
Replied by State Government(Uttar Pradesh) on:26/05/2022  
Query raised by State Government (Uttar Pradesh) on:19/01/2022  
Replied by Nodal Officer (Uttar Pradesh) on:31/03/2022  
Query raised by State Government (Uttar Pradesh) on:02/05/2022  
Replied by Nodal Officer (Uttar Pradesh) on:24/05/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:08/12/2021  
Replied by Circle(Lucknow Circle Lucknow) on:10/12/2021  
Query raised by Nodal Officer (Uttar Pradesh) on:20/01/2022  
Replied by Circle(Bareilly Circle Bareilly) on:04/02/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:20/01/2022  
Replied by Circle(Allhabad Circle Allhabad) on:07/02/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:20/01/2022  
Replied by Circle(Moradabad Circle Moradabad) on:07/02/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:20/01/2022  
Replied by Circle(Meerut Circle Meerut) on:08/02/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:20/01/2022  
Replied by Circle(Lucknow Circle Lucknow) on:09/02/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2022  
Replied by Circle(Lucknow Circle Lucknow) on:31/03/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2022  
Replied by Circle(Allhabad Circle Allhabad) on:31/03/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2022  
Replied by Circle(Moradabad Circle Moradabad) on:31/03/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2022  
Replied by Circle(Meerut Circle Meerut) on:31/03/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:11/02/2022  
Replied by Circle(Bareilly Circle Bareilly) on:31/03/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2022  
Replied by Circle(Moradabad Circle Moradabad) on:10/05/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2022  
Replied by Circle(Meerut Circle Meerut) on:14/05/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2022  
Replied by Circle(Bareilly Circle Bareilly) on:17/05/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2022  
Replied by Circle(Allhabad Circle Allhabad) on:17/05/2022  
Query raised by Nodal Officer (Uttar Pradesh) on:02/05/2022  
Replied by Circle(Lucknow Circle Lucknow) on:20/05/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:30/11/2021  
Replied by DFO (Social Forestry Division J.P. Nagar (Amroha)) on:02/12/2021  
Query raised by Circle (Moradabad Circle Moradabad) on:30/11/2021  
Replied by DFO (Social Forestry Division Sambhal) on:02/12/2021  
Query raised by Circle (Lucknow Circle Lucknow) on:03/12/2021  
Replied by DFO (Social Forestry Division Rae Bareli) on:03/12/2021  
Query raised by Circle (Lucknow Circle Lucknow) on:03/12/2021  
Replied by DFO (Social Forestry Division Unnao) on:03/12/2021  
Query raised by Circle (Lucknow Circle Lucknow) on:03/12/2021  
Replied by DFO (Social Forestry Division Unnao) on:06/12/2021  
Query raised by Circle (Lucknow Circle Lucknow) on:09/12/2021  
Replied by DFO (Social Forestry Division Unnao) on:10/12/2021  
Query raised by Circle (Moradabad Circle Moradabad) on:20/01/2022  
Replied by DFO (Social Forestry Division J.P. Nagar (Amroha)) on:21/01/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:20/01/2022  
Replied by DFO (Social Forestry Division Sambhal) on:01/02/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:24/01/2022  
Replied by DFO (Social Forestry Division Shahjahanpur) on:03/02/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:24/01/2022  
Replied by DFO (Social Forestry Division Hardoi) on:04/02/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:24/01/2022  
Replied by DFO (Social Forestry Division Budaun) on:04/02/2022  
Query raised by Circle (Meerut Circle Meerut) on:24/01/2022  
Replied by DFO (Social Forestry Division Pratapgarh) on:04/02/2022  
Query raised by Circle (Meerut Circle Meerut) on:24/01/2022  
Replied by DFO (Forest Division Hapur) on:04/02/2022  
Query raised by Circle (Meerut Circle Meerut) on:24/01/2022  
Replied by DFO (Social Forestry Division Meerut) on:04/02/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:03/02/2022  
Replied by DFO (Social Forestry Division Bulandshahar) on:04/02/2022  
Query raised by Circle (Bareilly Circle Bareilly) on:04/02/2022  
Replied by DFO (Social Forestry Division Rae Bareli) on:05/02/2022  
Query raised by Circle (Allhabad Circle Allhabad) on:04/02/2022  
Replied by DFO (Social Forestry Division Unnao) on:07/02/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:14/02/2022  
Replied by DFO (Social Forestry Division Unnao) on:24/03/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:14/02/2022  
Replied by DFO (Social Forestry Division Rae Bareli) on:30/03/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:14/02/2022  
Replied by DFO (Social Forestry Division J.P. Nagar (Amroha)) on:30/03/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:16/02/2022  
Replied by DFO (Social Forestry Division Sambhal) on:30/03/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:16/02/2022  
Replied by DFO (Social Forestry Division Hardoi) on:30/03/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:04/05/2022  
Replied by DFO (Social Forestry Division Sambhal) on:09/05/2022  
Query raised by Circle (Moradabad Circle Moradabad) on:04/05/2022  
Replied by DFO (Social Forestry Division J.P. Nagar (Amroha)) on:09/05/2022  
Query raised by Circle (Meerut Circle Meerut) on:11/05/2022  
Replied by DFO (Forest Division Hapur) on:14/05/2022  
Query raised by Circle (Lucknow Circle Lucknow) on:17/05/2022  
Replied by DFO (Social Forestry Division Unnao) on:17/05/2022  
Query raised by DFO (Social Forestry Division Allahabad) on:23/11/2021  
Replied by UA on :23/11/2021  
Query raised by DFO (Social Forestry Division Rae Bareli) on:24/01/2022  
Replied by UA on :01/02/2022  
Query raised by DFO (Social Forestry Division Unnao) on:17/02/2022  
Replied by UA on :22/02/2022  
Query raised by DFO (Social Forestry Division Rae Bareli) on:03/03/2022  
Replied by UA on :04/03/2022  
Query raised by DFO (Social Forestry Division Unnao) on:15/03/2022  
Replied by UA on :23/03/2022  
Query raised by DFO (Social Forestry Division Rae Bareli) on:26/03/2022  
Replied by UA on :29/03/2022  
Query raised by DFO (Forest Division Hapur) on:13/05/2022  
Replied by UA on :13/05/2022  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Lucknow) on:29/03/2023  
Query raised by State Government (Uttar Pradesh) on:31/03/2023  
Query raised by Nodal Officer on:31/03/2023  
Replied by UA on :12/06/2024  
Query raised by Nodal Officer on:13/06/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .
Close(X)
Close(X)
Please wait ...