TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UP/RAIL/7218/2014              (ii). Name of Project for which Forest Land is required : Luknow Pilibhit Gauge Conversion via Sitapur and Lakhimpur              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : To serve the project, a new bridge is to be constructed 12 Metre away from the old bridge. It will necessitate the laying of tracks on new alignment on Railway land measuring 0.85 Ha having 121 trees planted by the Railway. The diversion of this land is required for Non-Forestry purpose.              (iv). File no. : 8B/UP/07/34/2015              (v). State : Uttar Pradesh              (vi). Category of the Project : Railway              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.85
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UP/RAIL/7218/201426/11/201404/12/2014   06/12/2014   07/12/2014   12/12/2014 Social Forestry Division Sitapur :16/12/2014Lucknow Circle Lucknow:
  19/02/2015 (Social Forestry Division Sitapur)

Uttar Pradesh:
09/03/2015
Uttar Pradesh:
09/07/2015
Lucknow:
09/07/2015
23/09/2015
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Lucknow) on:29/07/2015  
Replied by State Government(Uttar Pradesh) on:25/08/2015  
Query raised by Regional Office (Lucknow) on:11/09/2015  
Replied by State Government(Uttar Pradesh) on:14/09/2015  
Query raised by State Government (Uttar Pradesh) on:25/08/2015  
Replied by Nodal Officer (Uttar Pradesh) on:25/08/2015  
Query raised by State Government (Uttar Pradesh) on:14/09/2015  
Replied by Nodal Officer (Uttar Pradesh) on:14/09/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:16/03/2015  
Replied by Circle(Lucknow Circle Lucknow) on:23/04/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:27/04/2015  
Replied by Circle(Lucknow Circle Lucknow) on:27/04/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:28/04/2015  
Replied by Circle(Lucknow Circle Lucknow) on:18/06/2015  
Query raised by Nodal Officer (Uttar Pradesh) on:19/06/2015  
Replied by Circle(Lucknow Circle Lucknow) on:09/07/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:21/04/2015  
Replied by DFO (Social Forestry Division Sitapur) on:23/04/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:15/05/2015  
Replied by DFO (Social Forestry Division Sitapur) on:17/06/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:22/06/2015  
Replied by DFO (Social Forestry Division Sitapur) on:30/06/2015  
Query raised by Circle (Lucknow Circle Lucknow) on:30/06/2015  
Replied by DFO (Social Forestry Division Sitapur) on:08/07/2015  
Query raised by DFO (Social Forestry Division Sitapur) on:23/04/2015  
Replied by UA on :23/04/2015  
Query raised by DFO (Social Forestry Division Sitapur) on:20/05/2015  
Replied by UA on :17/06/2015  
NOTE:- Stage-I Approval accorded by : Regional Office .