TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/7245/2014              (ii). Name of Project for which Forest Land is required : CHOBATI M/R TO BARAM BACHKURI MOTOR ROAD              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This Road will connect Brambachkuri habitation which starts from Chaubati and it ends at Barambachkuri.The length of road is 9.070 Km,and passes through civil soyam forest and nap land in which 5.409 hectares of Civil soyam land is required in this project.              (iv). File no. : 8B/UCP/06/26/2015-FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 5.409
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/7245/201424/12/2014aa01/01/2015   03/01/2015   Pithoragarh :07/01/2015North Kumaun:
  28/01/2015 (Pithoragarh)

Uttarakhand:
09/02/2015
Uttarakhand:
16/03/2015
Dehradun:
23/03/2015
08/03/2016
By :Regional Office
Uttarakhand
15/03/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:04/06/2015  
Replied by State Government(Uttarakhand) on:16/11/2015  
Query raised by State Government (Uttarakhand) on:04/06/2015  
Replied by Nodal Officer (Uttarakhand) on:15/11/2015  
Query raised by Nodal Officer (Uttarakhand) on:11/02/2015  
Replied by Circle(North Kumaun) on:12/03/2015  
Query raised by Nodal Officer (Uttarakhand) on:04/06/2015  
Replied by Circle(North Kumaun) on:11/08/2015  
Query raised by Nodal Officer (Uttarakhand) on:15/08/2015  
Replied by Circle(North Kumaun) on:21/10/2015  
Query raised by Circle (North Kumaun) on:13/02/2015  
Replied by DFO (Pithoragarh) on:22/02/2015  
Query raised by Circle (North Kumaun) on:26/02/2015  
Replied by DFO (Pithoragarh) on:27/02/2015  
Query raised by Circle (North Kumaun) on:02/03/2015  
Replied by DFO (Pithoragarh) on:12/03/2015  
Query raised by Circle (North Kumaun) on:05/06/2015  
Replied by DFO (Pithoragarh) on:08/08/2015  
Query raised by Circle (North Kumaun) on:18/08/2015  
Replied by DFO (Pithoragarh) on:19/08/2015  
Query raised by Circle (North Kumaun) on:25/08/2015  
Replied by DFO (Pithoragarh) on:19/09/2015  
Query raised by Circle (North Kumaun) on:22/09/2015  
Replied by DFO (Pithoragarh) on:16/10/2015  
Query raised by DFO (Pithoragarh) on:08/06/2015  
Replied by UA on :31/07/2015  
Query raised by DFO (Pithoragarh) on:28/08/2015  
Replied by UA on :16/09/2015  
Query raised by DFO (Pithoragarh) on:26/09/2015  
Replied by UA on :01/10/2015  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:31/03/2022  
Replied by State Government(Uttarakhand) on:15/12/2022  
Query raised by Regional Office (Dehradun) on:26/12/2022  
Replied by State Government(Uttarakhand) on:27/10/2023  
Query raised by Regional Office (Dehradun) on:28/02/2024  
Query raised by State Government (Uttarakhand) on:04/04/2022  
Replied by Nodal Officer (Uttarakhand) on:15/12/2022  
Query raised by State Government (Uttarakhand) on:28/12/2022  
Replied by Nodal Officer (Uttarakhand) on:27/10/2023  
Query raised by State Government (Uttarakhand) on:16/03/2024  
Query raised by Nodal Officer on:04/04/2022  
Replied by UA on :30/04/2022  
Query raised by Nodal Officer on:09/05/2022  
Replied by UA on :29/09/2022  
Query raised by Nodal Officer on:03/10/2022  
Replied by UA on :02/11/2022  
Query raised by Nodal Officer on:10/11/2022  
Replied by UA on :21/11/2022  
Query raised by Nodal Officer on:28/12/2022  
Replied by UA on :04/10/2023  
Query raised by Nodal Officer on:16/03/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .
Close(X)