Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
08/09/2021
|
Sir DFO unsigned copy of the Diverted land Toposheet map and Digital map are uploaded in online form-A part-i. Please DFO Singed copy the Diverted land map are uploaded.
|
|
2
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
09/09/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
24/09/2021
|
origina document not available.
|
|
4
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
13/10/2021
|
Sir Hard Copy thoruh by Dakiya Dated-13-10-2021
|
|
5
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
13/10/2021
|
original documents not available.
|
|
6
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
23/10/2021
|
Sir Hard Copy thoruh by Dakiya Dated-23-10-2021
|
|
7
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
25/10/2021
|
original documents not available.
|
|
8
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
28/10/2021
|
Sir Hard Copy thoruh by Dakiya Dated-23-10-2021
|
|
9
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
29/10/2021
|
original documents not available.
|
|
10
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
16/11/2021
|
Sir Hard Copy thoruh by Dakiya Dated-23-10-2021
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
30/12/2021
|
find the letter attched
|
|
12
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
01/01/2022
|
find the letter attached.
|
|
13
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
03/01/2022
|
sir please reply the EDS.
|
|
14
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
04/06/2022
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
06/06/2022
|
Hard copy not received.
|
|
16
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
08/08/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
16/08/2022
|
Please make correction as per EDS.
|
|
18
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
07/09/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
08/09/2022
|
Correction has been made and proposal's copies sent through dakiya.
|
|
20
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
22/10/2022
|
Sir,the correction have been made as per the instruction received.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
11/11/2022
|
• The hard copy of the proposal containing original documents is not yet received in this office. The CF may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
22
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
22/11/2022
|
Sir,the hard copy is submitted.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
09/12/2022
|
• The hard copy of the proposal containing original documents is not yet received in this office.
|
|
24
|
CF (Bhagirathi)
|
REPLY
|
Nodal Officer
|
08/02/2023
|
Sir,the Hard copy of the proposal containing original documents Submitted to office.
|
|
25
|
Regional Office
|
EDS
|
State secretary
|
24/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
25/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
27
|
Nodal Officer
|
EDS
|
CF (Bhagirathi)
|
25/04/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
28
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
26/04/2023
|
find the letter attached.
|
|
29
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
02/05/2023
|
EDS
|
|
30
|
CF (Bhagirathi)
|
EDS
|
DFO (Tehri,New Tehri)
|
10/05/2023
|
find the letter attached.
|
|
31
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
11/05/2023
|
Find the attached letter and provide details as per letter.
|
|
32
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
27/08/2024
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
20/09/2024
|
Please Upload the hard Copy of This Letter
|
|
34
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
25/09/2024
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
26/09/2024
|
Please shortout these Queries
|
|
36
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
16/10/2024
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Tehri,New Tehri)
|
EDS
|
User Agency (eepwdchamba@rediffmail.com)
|
19/10/2024
|
Sir, Please Rectify these Queries
|
|
38
|
User Agency (eepwdchamba@rediffmail.com)
|
REPLY
|
DFO (Tehri,New Tehri)
|
24/12/2024
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Tehri,New Tehri)
|
REPLY
|
CF (Bhagirathi)
|
01/01/2025
|
Sir, the correction have been made as per the instruction received.
|
|