Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
29/07/2021
|
find the letter attached
|
|
2
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
13/09/2021
|
The correction have been made as per the instruction received
|
|
3
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
01/10/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
4
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
04/10/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
5
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
12/10/2021
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
18/10/2021
|
plz find enclosed.
|
|
7
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/10/2021
|
As per letter no 1669/12-1 dated 23-10-2021
|
|
8
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
26/10/2021
|
As per letter no 1776/12-1 dated 26-10-2021
|
|
9
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
16/12/2021
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
22/12/2021
|
plz find enclosed
|
|
11
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
12/01/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
12
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
18/01/2022
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
13
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
29/03/2022
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
30/03/2022
|
plz find enclosed.
|
|
15
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
05/04/2022
|
find the letter attached
|
|
16
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/04/2022
|
find the letter attached
|
|
17
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
02/05/2022
|
find the letter attached..
|
|
18
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
10/11/2022
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
07/12/2022
|
plz find enclosed.
|
|
20
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
27/12/2022
|
As per letter no 1740/12-1 dared 22-12-2022
|
|
21
|
Regional Office
|
EDS
|
State secretary
|
08/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
22
|
State secretary
|
EDS
|
Nodal Officer
|
10/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
10/02/2023
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
15/02/2023
|
Do needful action as per EDS
|
|
25
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
15/02/2023
|
Do needful action as per EDS
|
|
26
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
08/06/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
22/06/2023
|
As per letter no 5095/12-1 dated 21-06-2023
|
|
28
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
26/06/2023
|
The correction have been made as per the instruction received
|
|
29
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
05/07/2023
|
plz find enclosed
|
|
30
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
21/07/2023
|
As per letter no 136/12-1 dated 19-07-2021
|
|
31
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
25/08/2023
|
find the letter attached
|
|
32
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/09/2023
|
find the letter attached
|
|
33
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
23/09/2023
|
find the letter attached
|
|
34
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
20/11/2023
|
The correction have been made as per the instruction received
|
|
35
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
01/12/2023
|
plz find enclosed.
|
|
36
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/01/2024
|
As per letter no 1463/12-1 dated 06-12-2023
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
38
|
State secretary
|
REPLY
|
Regional Office
|
12/02/2024
|
The correction have been made as per the instruction received
|
|
39
|
Regional Office
|
EDS
|
State secretary
|
06/05/2024
|
State Govt. may attend the following shortcomings as per the attachment here.
|
|
40
|
State secretary
|
EDS
|
Nodal Officer
|
07/05/2024
|
State Govt. may attend the following shortcomings as per the attachment here.
|
|
41
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
07/05/2024
|
State Govt. may attend the following shortcomings as per the attachment here.
|
|
42
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
08/05/2024
|
May attend the following shortcomings as per the attachment here.
|
|
43
|
DFO (Bageshwar)
|
EDS
|
User Agency (pdpwdbgr@gmail.com)
|
30/05/2024
|
May attend the following shortcomings as per the attachment here.
|
|
44
|
User Agency (pdpwdbgr@gmail.com)
|
REPLY
|
DFO (Bageshwar)
|
18/12/2024
|
The correction have been made as per the instruction received
|
|
45
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
26/12/2024
|
plz find enclosed
|
|
46
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
07/01/2025
|
As per Letter No-1628/12-1-2
Dated-03.01.2024
|
|