  (i). Proposal No. : FP/UK/ROAD/46681/2020              (ii). Name of Project for which Forest Land is required : New Construction of Tilari to Sera Motor Road.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : The proposed motorway passes through villages like Tiladi, Dugatad Serasunali etc., which has a population of 718. This motorway starts from km 11 of the Sandev Chaubati motor route to the last point km 2 of the Tiladi motorway. The construction of the proposed motorway will facilitate the traffic o              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 3.02
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/46681/202024/06/202026/06/2020   07/08/2020   17/08/2020   20/08/2020 Pithoragarh :20/08/2020North Kumaun:
  26/08/2020 (Pithoragarh)

Uttarakhand:
17/11/2020
Uttarakhand:
18/03/2021
Dehradun:
20/07/2021
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:30/07/2021  
Replied by State Government(Uttarakhand) on:04/07/2022  
Query raised by Regional Office (Dehradun) on:14/07/2022  
Replied by State Government(Uttarakhand) on:15/03/2023  
Query raised by Regional Office (Dehradun) on:31/03/2023  
Query raised by State Government (Uttarakhand) on:09/08/2021  
Replied by Nodal Officer (Uttarakhand) on:04/07/2022  
Query raised by State Government (Uttarakhand) on:20/07/2022  
Replied by Nodal Officer (Uttarakhand) on:15/03/2023  
Query raised by State Government (Uttarakhand) on:01/04/2023  
Query raised by Nodal Officer (Uttarakhand) on:18/11/2020  
Replied by Circle(North Kumaun) on:04/01/2021  
Query raised by Nodal Officer (Uttarakhand) on:01/02/2021  
Replied by Circle(North Kumaun) on:15/02/2021  
Query raised by Nodal Officer (Uttarakhand) on:09/08/2021  
Replied by Circle(North Kumaun) on:26/11/2021  
Query raised by Nodal Officer (Uttarakhand) on:29/12/2021  
Replied by Circle(North Kumaun) on:25/05/2022  
Query raised by Nodal Officer (Uttarakhand) on:20/07/2022  
Replied by Circle(North Kumaun) on:16/02/2023  
Query raised by Nodal Officer (Uttarakhand) on:01/04/2023  
Replied by Circle(North Kumaun) on:30/11/2024  
Query raised by Circle (North Kumaun) on:24/10/2020  
Replied by DFO (Pithoragarh) on:11/11/2020  
Query raised by Circle (North Kumaun) on:23/11/2020  
Replied by DFO (Pithoragarh) on:31/12/2020  
Query raised by Circle (North Kumaun) on:08/02/2021  
Replied by DFO (Pithoragarh) on:12/02/2021  
Query raised by Circle (North Kumaun) on:11/08/2021  
Replied by DFO (Pithoragarh) on:07/10/2021  
Query raised by Circle (North Kumaun) on:09/11/2021  
Replied by DFO (Pithoragarh) on:12/11/2021  
Query raised by Circle (North Kumaun) on:12/01/2022  
Replied by DFO (Pithoragarh) on:10/03/2022  
Query raised by Circle (North Kumaun) on:22/03/2022  
Replied by DFO (Pithoragarh) on:25/03/2022  
Query raised by Circle (North Kumaun) on:05/04/2022  
Replied by DFO (Pithoragarh) on:18/04/2022  
Query raised by Circle (North Kumaun) on:22/04/2022  
Replied by DFO (Pithoragarh) on:02/05/2022  
Query raised by Circle (North Kumaun) on:27/07/2022  
Replied by DFO (Pithoragarh) on:04/02/2023  
Query raised by Circle (North Kumaun) on:03/04/2023  
Replied by DFO (Pithoragarh) on:19/11/2024  
Query raised by DFO (Pithoragarh) on:27/10/2020  
Replied by UA on :05/11/2020  
Query raised by DFO (Pithoragarh) on:08/12/2020  
Replied by UA on :16/12/2020  
Query raised by DFO (Pithoragarh) on:19/12/2020  
Replied by UA on :23/12/2020  
Query raised by DFO (Pithoragarh) on:31/12/2020  
Replied by UA on :31/12/2020  
Query raised by DFO (Pithoragarh) on:11/02/2021  
Replied by UA on :11/02/2021  
Query raised by DFO (Pithoragarh) on:12/08/2021  
Replied by UA on :14/09/2021  
Query raised by DFO (Pithoragarh) on:17/01/2022  
Replied by UA on :25/02/2022  
Query raised by DFO (Pithoragarh) on:28/07/2022  
Replied by UA on :10/01/2023  
Query raised by DFO (Pithoragarh) on:18/04/2023  
Replied by UA on :02/05/2023  
Query raised by DFO (Pithoragarh) on:06/05/2023  
Replied by UA on :13/06/2023  
Query raised by DFO (Pithoragarh) on:14/06/2023  
Replied by UA on :19/07/2023  
Query raised by DFO (Pithoragarh) on:24/07/2023  
Replied by UA on :02/05/2024  
Query raised by DFO (Pithoragarh) on:06/06/2024  
Replied by UA on :20/06/2024  
Query raised by DFO (Pithoragarh) on:30/07/2024  
Replied by UA on :16/11/2024  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .