  (i). Proposal No. : FP/UK/ROAD/43594/2019              (ii). Name of Project for which Forest Land is required : Construction of Katna to Wari Motor Road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : For Benefit of Villagers of Katna and Wari like Medical facility, Education facility, and Transportation facility of Crops and other materials. Presently village Wari and tok of Katna are not connect of by any road. GIC Katna is not connected by motor road and proposed to be connected by this align              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.53
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/43594/201927/12/201917/02/2020  24/01/2020  28/12/2019   30/07/2020  07/02/2020  23/01/2020   10/08/2020   29/08/2020 Champawat :31/08/2020North Kumaun:
  23/06/2021 (Champawat)

Uttarakhand:
05/07/2022
Uttarakhand:
21/08/2023
Dehradun:
20/09/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:16/10/2023  
Replied by State Government(Uttarakhand) on:16/04/2025  
Query raised by Regional Office (Dehradun) on:03/05/2025  
Query raised by State Government (Uttarakhand) on:20/09/2023  
Replied by Nodal Officer (Uttarakhand) on:20/09/2023  
Query raised by State Government (Uttarakhand) on:18/10/2023  
Replied by Nodal Officer (Uttarakhand) on:17/02/2025  
Query raised by State Government (Uttarakhand) on:27/02/2025  
Replied by Nodal Officer (Uttarakhand) on:05/04/2025  
Query raised by State Government (Uttarakhand) on:05/05/2025  
Query raised by Nodal Officer (Uttarakhand) on:14/07/2022  
Replied by Circle(North Kumaun) on:01/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:11/08/2023  
Replied by Circle(North Kumaun) on:18/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:20/09/2023  
Replied by Circle(North Kumaun) on:20/09/2023  
Query raised by Nodal Officer (Uttarakhand) on:19/10/2023  
Replied by Circle(North Kumaun) on:04/07/2024  
Query raised by Nodal Officer (Uttarakhand) on:30/07/2024  
Replied by Circle(North Kumaun) on:13/02/2025  
Query raised by Nodal Officer (Uttarakhand) on:24/05/2025  
Replied by Circle(North Kumaun) on:04/07/2025  
Query raised by Circle (North Kumaun) on:02/07/2021  
Replied by DFO (Champawat) on:10/05/2022  
Query raised by Circle (North Kumaun) on:26/05/2022  
Replied by DFO (Champawat) on:02/07/2022  
Query raised by Circle (North Kumaun) on:14/07/2022  
Replied by DFO (Champawat) on:22/07/2023  
Query raised by Circle (North Kumaun) on:20/09/2023  
Replied by DFO (Champawat) on:20/09/2023  
Query raised by Circle (North Kumaun) on:19/10/2023  
Replied by DFO (Champawat) on:25/06/2024  
Query raised by Circle (North Kumaun) on:30/07/2024  
Replied by DFO (Champawat) on:20/01/2025  
Query raised by Circle (North Kumaun) on:27/05/2025  
Replied by DFO (Champawat) on:20/06/2025  
Query raised by DFO (Champawat) on:01/09/2020  
Replied by UA on :23/09/2020  
Query raised by DFO (Champawat) on:08/02/2021  
Replied by UA on :19/02/2021  
Query raised by DFO (Champawat) on:05/07/2021  
Replied by UA on :29/07/2021  
Query raised by DFO (Champawat) on:21/09/2021  
Replied by UA on :26/10/2021  
Query raised by DFO (Champawat) on:22/11/2021  
Replied by UA on :14/01/2022  
Query raised by DFO (Champawat) on:18/01/2022  
Replied by UA on :19/01/2022  
Query raised by DFO (Champawat) on:19/01/2022  
Replied by UA on :21/04/2022  
Query raised by DFO (Champawat) on:28/05/2022  
Replied by UA on :25/06/2022  
Query raised by DFO (Champawat) on:28/06/2022  
Replied by UA on :02/07/2022  
Query raised by DFO (Champawat) on:14/07/2022  
Replied by UA on :28/09/2022  
Query raised by DFO (Champawat) on:29/09/2022  
Replied by UA on :20/12/2022  
Query raised by DFO (Champawat) on:07/01/2023  
Replied by UA on :03/07/2023  
Query raised by DFO (Champawat) on:05/07/2023  
Replied by UA on :21/07/2023  
Query raised by DFO (Champawat) on:19/10/2023  
Replied by UA on :27/10/2023  
Query raised by DFO (Champawat) on:27/10/2023  
Replied by UA on :22/05/2024  
Query raised by DFO (Champawat) on:27/05/2024  
Replied by UA on :12/06/2024  
Query raised by DFO (Champawat) on:13/06/2024  
Replied by UA on :25/06/2024  
Query raised by DFO (Champawat) on:31/07/2024  
Replied by UA on :18/01/2025  
Query raised by DFO (Champawat) on:31/05/2025  
Replied by UA on :04/06/2025  
NOTE:- Proposal is pending at Nodal Officer due to EDS raised by Regional Office .