Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
18/01/2019
|
Plz attached C.A. suitability certificate, trees correct list.
|
|
2
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
25/01/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
31/01/2019
|
Plz attached C.A. suitability certificate, trees correct list. 18/01/2019 DFO
|
|
4
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
18/02/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
27/02/2019
|
Send the correction letter to the office.
|
|
6
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
18/04/2019
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
20/04/2019
|
remove obj
|
|
8
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
19/06/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
26/06/2019
|
nic
|
|
10
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
09/07/2019
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
18/07/2019
|
find letter
|
|
12
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
19/07/2019
|
The correction have been made as per the instruction received
|
|
13
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
31/07/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
14
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
05/08/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
15
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
05/08/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
16
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
29/08/2019
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
04/09/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal. Send receiving letter.
|
|
18
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
17/11/2019
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
20/11/2019
|
The hard copy of the proposal containing original documents is not yet received in CF office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
20
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
22/11/2019
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
23/11/2019
|
Correction has been removed as per letter.
|
|
22
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
10/12/2019
|
The On line objections raised by Reg. Office /Nodal officer on date 31-07-2019 has been clarified by DFO Pithoragarh letter no 1949/12-1 dated 22-11-2019
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
12/12/2019
|
find the letter attached
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/12/2019
|
find the letter attached
|
|
25
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
13/12/2019
|
Make correction as per letter.
|
|
26
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
10/07/2020
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
13/07/2020
|
Objection has been removed as per letter.
|
|
28
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
28/07/2020
|
As per letter no 342/12-1 dated 27-07-2020
|
|
29
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
28/07/2020
|
Remove objection as per letter.
|
|
30
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
09/09/2020
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
14/09/2020
|
The correction have been made as per the instruction received
|
|
32
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
19/09/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 12-12-2019 has been clarified by Dfo Pithoragarh letter no 1019/12-1 dated 10-09-2020.
|
|
33
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
22/09/2020
|
find the letter attached
|
|
34
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
17/10/2020
|
find the letter attached
|
|
35
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
17/10/2020
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
36
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
13/11/2020
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
04/12/2020
|
obj removed as per instruction
|
|
38
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/12/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 22-09-2020 has been clarified by Dfo Pithoragarh letter no 2018/12-1 dated 04-12-2020.
|
|
39
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
14/12/2020
|
find the letter attached
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
23/12/2020
|
find the letter attached
|
|
41
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
23/12/2020
|
find the letter attached
|
|
42
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
05/01/2021
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
11/01/2021
|
objections have been removed
|
|
44
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
12/01/2021
|
The On line objections raised by Reg. Office /Nodal officer on date 14-12-2020 has been clarified by Dfo Pithoragarh letter no 2526/12-1 dated 11-01-2021.
|
|
45
|
Regional Office
|
EDS
|
State secretary
|
16/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
46
|
State secretary
|
EDS
|
Nodal Officer
|
16/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
47
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
16/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
48
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
17/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
49
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
18/03/2021
|
The state govt. may attend the following shortcomings as per the attachment here
|
|
50
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
07/07/2021
|
The correction have been made as per the instruction received
|
|
51
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
20/07/2021
|
plz remove objections
|
|
52
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
20/07/2021
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
20/07/2021
|
plz find enclosed corrections have been done
|
|
54
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
23/07/2021
|
As per letter no 261/12-1 dated 23-07-2021
|
|
55
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
26/07/2021
|
• please submit hard copy of the compliance for EDS raised by reginal office on dated 15-3-21 to nodal office for perusing proposal to RO office.
|
|
56
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
31/07/2021
|
• please submit hard copy of the compliance for EDS raised by reginal office on dated 15-3-21 to nodal office for perusing proposal to RO office.
The proposal is being reverted back through our official letter no. 415/12-1(2) Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the lette
|
|
57
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
02/08/2021
|
• please submit hard copy of the compliance for EDS raised by reginal office on dated 15-3-21 to nodal office for perusing proposal to RO office. The proposal is being reverted back through our official letter no. 415/12-1(2) Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the let
|
|
58
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
03/08/2021
|
The correction have been made as per the instruction received
|
|
59
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
06/08/2021
|
Please read enclosed letter. And follow the direction as mentioned in letter.
|
|
60
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
07/08/2021
|
The correction have been made as per the instruction received
|
|
61
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
25/08/2021
|
Pl. send five hard copies including signed online Part I with proper Name, designation and date of concerned authorities on the hard copies as per directions received by Nodal office via letter127/1G-5055 dated 12-07-2021.
|
|
62
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
02/09/2021
|
The correction have been made as per the instruction received
|
|
63
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
03/09/2021
|
Objecti has been removed as per letter attached.
|
|
64
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
13/09/2021
|
The proposal is being reverted back through our official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
65
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
22/09/2021
|
The proposal is being reverted back by CF office through their official letter no. 415/12-1 Dated 28-07-2021 with the intent that it must be submitted back online to the office after complying with all the instructions given in the letter.
|
|
66
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
06/10/2021
|
The correction have been made as per the instruction received
|
|
67
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
06/10/2021
|
objections been removed.
|
|
68
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/10/2021
|
As per letter no 1438/12-1 dated 05-10-2021
|
|
69
|
Nodal Officer
|
REPLY
|
State secretary
|
12/10/2021
|
The correction have been made as per the instruction received
|
|
70
|
State secretary
|
REPLY
|
Regional Office
|
12/10/2021
|
The correction have been made as per the instruction received
|
|
71
|
Regional Office
|
EDS
|
State secretary
|
29/10/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
72
|
State secretary
|
EDS
|
Nodal Officer
|
02/11/2021
|
State Govt. may attend the following shortcomings as per the attachment here
|
|
73
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
02/11/2021
|
State govt. may attend the following shortcomings as per the attachment here
|
|
74
|
CF (North Kumaun)
|
EDS
|
DFO (Pithoragarh)
|
09/11/2021
|
State govt. may attend the following shortcomings as per the attachment here
|
|
75
|
DFO (Pithoragarh)
|
EDS
|
User Agency (eepwdaskote@gmail.com)
|
12/11/2021
|
Please provide point wise answer
|
|
76
|
User Agency (eepwdaskote@gmail.com)
|
REPLY
|
DFO (Pithoragarh)
|
05/03/2025
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Pithoragarh)
|
REPLY
|
CF (North Kumaun)
|
05/07/2025
|
objection has been removed.
|
|
78
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
22/07/2025
|
As per letter no 68/12-1 dated 07-07-2025
|
|
79
|
Nodal Officer
|
REPLY
|
State secretary
|
02/08/2025
|
As per attached eds reply
|
|
80
|
State secretary
|
REPLY
|
Regional Office
|
26/08/2025
|
As per attachment
|
|