TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/23941/2017              (ii). Name of Project for which Forest Land is required : Construction of Km-35 of Raipur-Kumalda-Kaddukhal Motor Road to Ghena              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Presently the villagers (01 number of villagers Ghena with a total population of 375 ) have to walk through a distance of 12-13 km to meet their daily needs ,as there is no road connecting the village.Due to the non-existing of any road connectivity ,the lives of the villagers are in constant              (iv). File no. : 8B/UCP/06/63/2019/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 2.0825
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/23941/201703/02/201706/09/2017  07/08/2017  04/06/2017  27/03/2017   07/09/2017  04/09/2017  29/07/2017  01/05/2017   04/10/2017   06/11/2017  

Mussoorie :11/11/2017


Narendranagar,Munikireti :11/11/2017

Yamuna:
  27/07/2018 (Mussoorie)

Bhagirathi:
  06/02/2019 (Narendranagar,Munikireti)

Uttarakhand:
22/03/2019
Uttarakhand:
01/05/2019
Dehradun:
15/05/2019
17/12/2019
By :Regional Office
Uttarakhand
28/02/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:10/06/2019  
Replied by State Government(Uttarakhand) on:11/09/2019  
Query raised by Regional Office (Dehradun) on:09/10/2019  
Replied by State Government(Uttarakhand) on:06/12/2019  
Query raised by State Government (Uttarakhand) on:18/06/2019  
Replied by Nodal Officer (Uttarakhand) on:03/09/2019  
Query raised by State Government (Uttarakhand) on:10/10/2019  
Replied by Nodal Officer (Uttarakhand) on:03/12/2019  
Query raised by State Government (Uttarakhand) on:05/12/2019  
Replied by Nodal Officer (Uttarakhand) on:06/12/2019  
Query raised by Nodal Officer (Uttarakhand) on:23/03/2019  
Replied by Circle(Yamuna) on:22/04/2019  
Query raised by Nodal Officer (Uttarakhand) on:01/07/2019  
Replied by Circle(Yamuna) on:05/08/2019  
Query raised by Nodal Officer (Uttarakhand) on:01/07/2019  
Replied by Circle(Bhagirathi) on:28/08/2019  
Query raised by Nodal Officer (Uttarakhand) on:10/10/2019  
Replied by Circle(Bhagirathi) on:22/11/2019  
Query raised by Nodal Officer (Uttarakhand) on:10/10/2019  
Replied by Circle(Yamuna) on:29/11/2019  
Query raised by Circle (Bhagirathi) on:11/02/2019  
Replied by DFO (Narendranagar,Munikireti) on:27/02/2019  
Query raised by Circle (Yamuna) on:02/03/2019  
Replied by DFO (Mussoorie) on:12/03/2019  
Query raised by Circle (Yamuna) on:26/03/2019  
Replied by DFO (Mussoorie) on:21/04/2019  
Query raised by Circle (Yamuna) on:02/07/2019  
Replied by DFO (Mussoorie) on:31/07/2019  
Query raised by Circle (Bhagirathi) on:01/08/2019  
Replied by DFO (Mussoorie) on:31/07/2019  
Query raised by Circle (Bhagirathi) on:14/08/2019  
Replied by DFO (Narendranagar,Munikireti) on:05/08/2019  
Query raised by Circle (Bhagirathi) on:10/10/2019  
Replied by DFO (Narendranagar,Munikireti) on:22/08/2019  
Query raised by Circle (Yamuna) on:21/11/2019  
Replied by DFO (Narendranagar,Munikireti) on:20/11/2019  
Query raised by DFO (Mussoorie) on:29/11/2017  
Replied by UA on :24/01/2018  
Query raised by DFO (Mussoorie) on:29/01/2018  
Replied by UA on :21/03/2018  
Query raised by DFO (Mussoorie) on:05/04/2018  
Replied by UA on :26/06/2018  
Query raised by DFO (Narendranagar,Munikireti) on:21/07/2018  
Replied by UA on :25/07/2018  
Query raised by DFO (Narendranagar,Munikireti) on:13/09/2018  
Replied by UA on :29/01/2019  
Query raised by DFO (Narendranagar,Munikireti) on:30/01/2019  
Replied by UA on :04/02/2019  
Query raised by DFO (Narendranagar,Munikireti) on:16/02/2019  
Replied by UA on :18/02/2019  
Query raised by DFO (Mussoorie) on:26/03/2019  
Replied by UA on :04/04/2019  
Query raised by DFO (Mussoorie) on:03/07/2019  
Replied by UA on :17/07/2019  
Query raised by DFO (Mussoorie) on:18/07/2019  
Replied by UA on :18/07/2019  
Query raised by DFO (Mussoorie) on:25/07/2019  
Replied by UA on :29/07/2019  
Query raised by DFO (Narendranagar,Munikireti) on:01/08/2019  
Replied by UA on :03/08/2019  
Query raised by DFO (Narendranagar,Munikireti) on:16/08/2019  
Replied by UA on :16/08/2019  
Query raised by DFO (Narendranagar,Munikireti) on:19/08/2019  
Replied by UA on :21/08/2019  
Query raised by DFO (Narendranagar,Munikireti) on:13/10/2019  
Replied by UA on :08/11/2019  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:28/03/2023  
Replied by State Government(Uttarakhand) on:02/08/2024  
Query raised by Regional Office (Dehradun) on:05/09/2024  
Query raised by State Government (Uttarakhand) on:29/03/2023  
Replied by Nodal Officer (Uttarakhand) on:15/06/2024  
Query raised by State Government (Uttarakhand) on:31/07/2024  
Replied by Nodal Officer (Uttarakhand) on:02/08/2024  
Query raised by State Government (Uttarakhand) on:09/09/2024  
Query raised by Nodal Officer on:29/03/2023  
Replied by UA on :06/05/2024  
Query raised by Nodal Officer on:18/09/2024  
Replied by UA on :23/09/2024  
Query raised by Nodal Officer on:19/10/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .