Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
21/09/2017
|
As per letter no 911/12-1 dated 21-09-2017
|
|
2
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
25/09/2017
|
please find enclosed
|
|
3
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
06/11/2017
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
09/01/2018
|
please find enclosed
|
|
5
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
16/01/2018
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
05/02/2018
|
please find enclosed
|
|
7
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/02/2018
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
12/04/2018
|
please find enclosed
|
|
9
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
16/04/2018
|
Plz Hard copy Send CF Office this Proposal
|
|
10
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
16/04/2018
|
Plz Hard copy Send CF Office this Proposal
|
|
11
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/05/2018
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
09/05/2018
|
plz hard copy send cf office this proposal
|
|
13
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
16/05/2018
|
The correction have been made as per the instruction received
|
|
14
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
18/05/2018
|
Plz Hard copy Send CF Office this Proposal
|
|
15
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
20/05/2018
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
30/05/2018
|
Plz Hard copy Send CF Office this Proposal
|
|
17
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
06/06/2018
|
The correction have been made as per the instruction received
|
|
18
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
21/06/2018
|
plz find enclosed
|
|
19
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/06/2018
|
As per letter no 3958/12-1 dated 21-06-2018
|
|
20
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
22/06/2018
|
plz fid enclosed
|
|
21
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/08/2018
|
The correction have been made as per the instruction received
|
|
22
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
09/08/2018
|
PLZ CHIKED BY EMAIL ID
|
|
23
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
25/08/2018
|
The correction have been made as per the instruction received
|
|
24
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
29/08/2018
|
plz fin enclosed
|
|
25
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
30/08/2018
|
The correction have been made as per the instruction received
|
|
26
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
05/09/2018
|
plz find enclosed
|
|
27
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
09/09/2018
|
The correction have been made as per the instruction received
|
|
28
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
25/09/2018
|
plz find enclosed
|
|
29
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
27/09/2018
|
As per letter no 1186/12-1 dated 27-09-2018
|
|
30
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
28/09/2018
|
plz find enclosed
|
|
31
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
12/12/2018
|
The correction have been made as per the instruction received
|
|
32
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
14/12/2018
|
As per letter no 1186/12-1 dated 27-09-2018
|
|
33
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
08/01/2019
|
The correction have been made as per the instruction received
|
|
34
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/01/2019
|
plz find enclosed
|
|
35
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
05/02/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
36
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
06/02/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal.
|
|
37
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
06/02/2019
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part iii as in online web portal
|
|
38
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/02/2019
|
The correction have been made as per the instruction received
|
|
39
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
07/02/2019
|
Please attach the acknowledgment letter of the hard copy of the proposal in the Nodal Office.
|
|
40
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
08/02/2019
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
13/02/2019
|
plz find enclosed
|
|
42
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
14/02/2019
|
The On line objections raised by Reg. Office /Nodal officer on date 05-02.2019 has been clarified by dfo Bageshwar letter no 2120/12-1 dated 12-02-2019
|
|
43
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
28/02/2019
|
find the letter attached
|
|
44
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
28/02/2019
|
find the letter attached
|
|
45
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
02/03/2019
|
find the letter attached
|
|
46
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
25/04/2019
|
The correction have been made as per the instruction received
|
|
47
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
15/05/2019
|
please check email id
|
|
48
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
29/06/2019
|
The correction have been made as per the instruction received
|
|
49
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
11/07/2019
|
plz find enclosed
|
|
50
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
16/07/2019
|
Send Back
|
|
51
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
16/07/2019
|
Send Back
|
|
52
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
22/07/2019
|
The correction have been made as per the instruction received
|
|
53
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
22/07/2019
|
plz find enclosed
|
|
54
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
22/07/2019
|
Send back
|
|
55
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/07/2019
|
plz find enclosed
|
|
56
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
23/07/2019
|
Plz attachment Dfo letter and enclose
|
|
57
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
23/07/2019
|
plz find enclosed
|
|
58
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
23/07/2019
|
The On line objections raised by Reg. Office /Nodal officer on date 28-02-2019 has been clarified by Dfo Bageshwar letter no 200/12-1 dated 10-07-2019.
|
|
59
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
01/08/2019
|
find the letter attached
|
|
60
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
02/08/2019
|
find the letter attached
|
|
61
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
02/08/2019
|
find the letter attached
|
|
62
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
07/08/2019
|
The correction have been made as per the instruction received
|
|
63
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
08/08/2019
|
send back
|
|
64
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
09/08/2019
|
The correction have been made as per the instruction received
|
|
65
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
19/08/2019
|
Objections have been reved and uploaded online.
|
|
66
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
21/08/2019
|
Objections have been reved and uploaded online.
|
|
67
|
Regional Office
|
EDS
|
State secretary
|
11/10/2019
|
State Govt may attend the shortcomings as per the attachment
|
|
68
|
State secretary
|
EDS
|
Nodal Officer
|
22/10/2019
|
State Govt may attend the shortcomings as per the attachment
|
|
69
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
22/10/2019
|
State Govt may attend the shortcomings as per the attachment
|
|
70
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
24/10/2019
|
State Govt may attend the shortcomings as per the attachment
|
|
71
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
25/10/2019
|
State Govt may attend the shortcomings as per the attachment
|
|
72
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
23/12/2019
|
The correction have been made as per the instruction received
|
|
73
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
09/01/2020
|
plz hard coThe hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part ii as in online web portal
|
|
74
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
13/01/2020
|
The correction have been made as per the instruction received
|
|
75
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
14/01/2020
|
The hard copy of the proposal containing original documents is not yet received in this office. The user agency may provide original hard copy of the proposal to this office including authenticated copy of Part I to Part ii as in online web portal
|
|
76
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
14/01/2020
|
The correction have been made as per the instruction received
|
|
77
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
20/01/2020
|
plz find enclosed
|
|
78
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
21/01/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 22-10-2019 has been clarified by Dfo Bageshwar letter no 2129/12-1 dated 18-01-2020
|
|
79
|
Nodal Officer
|
REPLY
|
State secretary
|
22/01/2020
|
The correction have been made as per the instruction received
|
|
80
|
State secretary
|
REPLY
|
Regional Office
|
22/01/2020
|
The correction have been made as per the instruction received
|
|
81
|
Regional Office
|
EDS
|
State secretary
|
04/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
82
|
State secretary
|
EDS
|
Nodal Officer
|
04/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
83
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
04/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
84
|
CF (North Kumaun)
|
EDS
|
DFO (Bageshwar)
|
05/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
85
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
06/02/2020
|
The proposal was discussed in the REC meeting held on 29.01.2020. State Government may attend the shortcomings as per the minutes of REC meeting attached herewith.
|
|
86
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
22/02/2020
|
The correction have been made as per the instruction received
|
|
87
|
DFO (Bageshwar)
|
EDS
|
User Agency (eepmgsykapkot@rediffmail.com)
|
03/03/2020
|
The hard copy of the proposal containing original documents is not yet received in this office.
|
|
88
|
User Agency (eepmgsykapkot@rediffmail.com)
|
REPLY
|
DFO (Bageshwar)
|
05/03/2020
|
The correction have been made as per the instruction received
|
|
89
|
DFO (Bageshwar)
|
REPLY
|
CF (North Kumaun)
|
06/03/2020
|
plz find enclosed.
|
|
90
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
19/03/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 04-02-2020 has been clarified by Dfo Bageshwar letter no 2266/12-1 dated 06-03-2020.
|
|
91
|
Nodal Officer
|
REPLY
|
State secretary
|
21/03/2020
|
The correction have been made as per the instruction received
|
|
92
|
State secretary
|
REPLY
|
Regional Office
|
21/03/2020
|
The correction have been made as per the instruction received
|
|