TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/155241/2022              (ii). Name of Project for which Forest Land is required : Construction of Banwaldhar Jarmwar to Bainji Kandai Motor Road in district Rudraprayag              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : After construction of this road village Bainji Kandai will get transporation, educational, social and economical benefits              (iv). File no. : 8B/UCP/06/56/2023/FC              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.35
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/155241/202210/05/2022aa10/05/2022   19/07/2022 Rudraprayag :23/07/2022Garhwal:
  24/03/2023 (Rudraprayag)

Uttarakhand:
06/04/2023
Uttarakhand:
17/04/2023
Dehradun:
22/05/2023
04/12/2024
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:13/06/2023  
Replied by State Government(Uttarakhand) on:05/09/2023  
Query raised by Regional Office (Dehradun) on:30/10/2023  
Replied by State Government(Uttarakhand) on:21/02/2024  
Query raised by Regional Office (Dehradun) on:02/08/2024  
Replied by State Government(Uttarakhand) on:19/09/2024  
Query raised by State Government (Uttarakhand) on:14/06/2023  
Replied by Nodal Officer (Uttarakhand) on:05/09/2023  
Query raised by State Government (Uttarakhand) on:16/11/2023  
Replied by Nodal Officer (Uttarakhand) on:21/02/2024  
Query raised by State Government (Uttarakhand) on:05/08/2024  
Replied by Nodal Officer (Uttarakhand) on:13/09/2024  
Query raised by Nodal Officer (Uttarakhand) on:14/06/2023  
Replied by Circle(Garhwal) on:21/08/2023  
Query raised by Nodal Officer (Uttarakhand) on:16/11/2023  
Replied by Circle(Garhwal) on:14/02/2024  
Query raised by Nodal Officer (Uttarakhand) on:12/08/2024  
Replied by Circle(Garhwal) on:12/09/2024  
Query raised by Circle (Garhwal) on:20/06/2023  
Replied by DFO (Rudraprayag) on:01/07/2023  
Query raised by Circle (Garhwal) on:11/07/2023  
Replied by DFO (Rudraprayag) on:05/08/2023  
Query raised by Circle (Garhwal) on:17/11/2023  
Replied by DFO (Rudraprayag) on:05/02/2024  
Query raised by Circle (Garhwal) on:16/08/2024  
Replied by DFO (Rudraprayag) on:12/09/2024  
Query raised by DFO (Rudraprayag) on:02/08/2022  
Replied by UA on :05/08/2022  
Query raised by DFO (Rudraprayag) on:16/08/2022  
Replied by UA on :08/09/2022  
Query raised by DFO (Rudraprayag) on:14/10/2022  
Replied by UA on :11/01/2023  
Query raised by DFO (Rudraprayag) on:30/01/2023  
Replied by UA on :03/03/2023  
Query raised by DFO (Rudraprayag) on:20/03/2023  
Replied by UA on :21/03/2023  
Query raised by DFO (Rudraprayag) on:21/06/2023  
Replied by UA on :21/06/2023  
Query raised by DFO (Rudraprayag) on:11/07/2023  
Replied by UA on :01/08/2023  
Query raised by DFO (Rudraprayag) on:18/11/2023  
Replied by UA on :08/01/2024  
Query raised by DFO (Rudraprayag) on:22/01/2024  
Replied by UA on :26/01/2024  
Query raised by DFO (Rudraprayag) on:30/08/2024  
Replied by UA on :11/09/2024  
NOTE:- Stage-I Approval accorded by : Regional Office .