Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
03/06/2016
|
as per letter no 4448/12-1 dated 03-06-2016
|
|
2
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
04/06/2016
|
objection
|
|
3
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
29/06/2016
|
The correction have been made as per the instruction received
|
|
4
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
25/01/2018
|
objection reply
25-01-2018
|
|
5
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
27/01/2018
|
send back
|
|
6
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
27/01/2018
|
objection reply date
27-01-2018
|
|
7
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
17/02/2018
|
find the letter attached
|
|
8
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
21/02/2018
|
find the letter attached
|
|
9
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
23/02/2018
|
objection
23-02-2018
|
|
10
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
10/08/2018
|
The correction have been made as per the instruction received
|
|
11
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
28/08/2018
|
please reply the EDS with forwarding letter and current date .
|
|
12
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
07/09/2018
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
12/09/2018
|
objection reply
12-09-2018
|
|
14
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
12/09/2018
|
The On line objections raised by Reg. Office/Nodal officer on date 17-02-2018. has been clarified by DFO Almora letter no 1321/12-1 dated 11-09-2018.
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
06/08/2019
|
State Government may submit the hard copy of the proposal containing original documents.
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
08/08/2019
|
State Government may submit the hard copy of the proposal containing original documents.
|
|
17
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
09/08/2019
|
State Government may submit the hard copy of the proposal containing original documents.
|
|
18
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
13/08/2019
|
State Government may submit the hard copy of the proposal containing original documents.
|
|
19
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
31/08/2019
|
objection reply date 31-08-2019
|
|
20
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
01/11/2019
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
18/11/2019
|
objection reply dated 18-11-2019
|
|
22
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
23/11/2019
|
As per letter no 1796/12-1 dated 23-11-2019
|
|
23
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
02/12/2019
|
find the letter attached
|
|
24
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
06/12/2019
|
find the letter attached
|
|
25
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
11/12/2019
|
OBJECTION DATED 11-12-2019
|
|
26
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
27/05/2020
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
01/07/2020
|
objection reply dated 01-07-2020
|
|
28
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
02/07/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 02-12-2019 has been clarified by Dfo Almora letter no 15/12-1 dated 01-07-2020.
|
|
29
|
Nodal Officer
|
REPLY
|
State secretary
|
04/07/2020
|
The correction have been made as per the instruction received
|
|
30
|
State secretary
|
REPLY
|
Regional Office
|
04/07/2020
|
The correction have been made as per the instruction received
|
|
31
|
Regional Office
|
EDS
|
State secretary
|
21/07/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
32
|
State secretary
|
EDS
|
Nodal Officer
|
21/07/2020
|
State Government may attend to the shortcomings mentioned in the attached document.
|
|
33
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
23/07/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
34
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
27/07/2020
|
state govt. may attend the following shortcomings as per the attachment here
|
|
35
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
05/08/2020
|
objection date 05-08-2020
|
|
36
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
04/11/2020
|
The correction have been made as per the instruction received
|
|
37
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
23/11/2020
|
Correction has been made.
|
|
38
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
25/11/2020
|
The On line objections raised by Reg. Office /Nodal officer on date 23-07-2020 has been clarified by Dfo Almora letter no 2834/12-1 dated 23-11-2020.
|
|
39
|
Nodal Officer
|
EDS
|
CF (North Kumaun)
|
27/11/2020
|
find the letter attached
|
|
40
|
CF (North Kumaun)
|
EDS
|
DFO (Almora)
|
08/12/2020
|
find the letter attached
|
|
41
|
DFO (Almora)
|
EDS
|
User Agency (anandb070@gmail.com)
|
10/12/2020
|
please do needful as per eds
|
|
42
|
User Agency (anandb070@gmail.com)
|
REPLY
|
DFO (Almora)
|
01/01/2021
|
The correction have been made as per the instruction received
|
|
43
|
DFO (Almora)
|
REPLY
|
CF (North Kumaun)
|
07/01/2021
|
correction has been made online as per eds.
|
|
44
|
CF (North Kumaun)
|
REPLY
|
Nodal Officer
|
08/01/2021
|
The On line objections raised by Reg. Office /Nodal officer on date 27-11-2020 has been clarified by Dfo Almora letter no 3582/12-1 dated 07-01-2021
|
|
45
|
Nodal Officer
|
REPLY
|
State secretary
|
01/02/2021
|
Required documents uploaded for your further necessary action.
|
|
46
|
State secretary
|
REPLY
|
Regional Office
|
01/02/2021
|
Required documents uploaded for your further necessary action.
|
|