TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/149153/2021              (ii). Name of Project for which Forest Land is required : Const Ram mandir to thatholi saspora moter road              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Ram mandir to thatholi saspora moter road by the Proposed Road Joins Very interior Area and Tourist Places of Berinag Biock Will be Benefited and Connect the Villages to tehsil and Distt .Head quarter by this Road .              (iv). State : Uttarakhand              (v). Category of the Project : Road              (vi). Shape of forest land proposed to be diverted : Linear              (vii). Area of forest land proposed for diversion(in ha.): 1.71
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/149153/202129/11/2021aa29/11/2021   18/01/2022 Pithoragarh :24/01/2022North Kumaun:
  01/04/2022 (Pithoragarh)

Uttarakhand:
07/06/2022
Uttarakhand:
06/03/2023
Dehradun:
29/03/2023
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:28/04/2023  
Query raised by State Government (Uttarakhand) on:28/04/2023  
Query raised by Nodal Officer (Uttarakhand) on:15/06/2022  
Replied by Circle(North Kumaun) on:16/02/2023  
Query raised by Nodal Officer (Uttarakhand) on:28/04/2023  
Replied by Circle() on:  
Query raised by Circle (North Kumaun) on:05/04/2022  
Replied by DFO (Pithoragarh) on:18/04/2022  
Query raised by Circle (North Kumaun) on:22/04/2022  
Replied by DFO (Pithoragarh) on:29/04/2022  
Query raised by Circle (North Kumaun) on:30/06/2022  
Replied by DFO (Pithoragarh) on:04/02/2023  
Query raised by Circle (North Kumaun) on:29/04/2023  
Replied by DFO () on:  
Query raised by DFO (Pithoragarh) on:03/02/2022  
Replied by UA on :25/02/2022  
Query raised by DFO (Pithoragarh) on:06/04/2022  
Replied by UA on :12/04/2022  
Query raised by DFO (Pithoragarh) on:02/07/2022  
Replied by UA on :10/01/2023  
Query raised by DFO (Pithoragarh) on:17/01/2023  
Replied by UA on :31/01/2023  
Query raised by DFO (Pithoragarh) on:02/05/2023  
Replied by UA on :19/12/2023  
Query raised by DFO (Pithoragarh) on:31/01/2024  
Replied by UA on :07/11/2024  
Query raised by DFO (Pithoragarh) on:11/11/2024  
Replied by UA on :04/12/2024  
Query raised by DFO (Pithoragarh) on:21/12/2024  
Replied by UA on :21/12/2024  
Query raised by DFO (Pithoragarh) on:26/12/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by Regional Office .
Close(X)
Close(X)
Please wait ...