Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
16/10/2021
|
The hard copy of the proposal containing original documents is not yet received in this office.
|
|
2
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
09/12/2021
|
Sir, The proposal hard copy has been submit in your office.
|
|
3
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
14/12/2021
|
Sir Please remove the objection
|
|
4
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
15/12/2021
|
Please remove the objection.
|
|
5
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
17/05/2022
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
27/06/2022
|
Sir, Please remove the objection.
|
|
7
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
25/07/2022
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
02/08/2022
|
eds ojbection remove letter has not upload.
|
|
9
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
03/08/2022
|
The correction have been made as per the instruction received
|
|
10
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
14/08/2022
|
please submit the proposal hard copy in dfo office.
|
|
11
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
23/11/2022
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
12/12/2022
|
sir
eds objection has been removed.
|
|
13
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
04/01/2023
|
Sir Please remove the objection
|
|
14
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
16/01/2023
|
please eds objection has been remove.
|
|
15
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
10/11/2023
|
The correction have been made as per the instruction received
|
|
16
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
29/01/2024
|
sir eds objection has been removed.
|
|
17
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
15/02/2024
|
Sir Please remove the objection
|
|
18
|
DFO (Badrinath,Gopeshwar)
|
EDS
|
User Agency (eepdpwdkpg@gmail.com)
|
13/03/2024
|
Please remove the point no 7 or 9
|
|
19
|
User Agency (eepdpwdkpg@gmail.com)
|
REPLY
|
DFO (Badrinath,Gopeshwar)
|
20/04/2024
|
The correction have been made as per the instruction received
|
|
20
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
23/04/2024
|
Sir, Eds objection has been removed..
|
|
21
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
10/05/2024
|
find the letter attached
|
|
22
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
13/05/2024
|
find the letter attached
|
|
23
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
04/07/2024
|
sir, eds objection has been removed by user agency and dfo office.
|
|
24
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
19/07/2024
|
Attach the correct copy related to the proposal
|
|
25
|
DFO (Badrinath,Gopeshwar)
|
REPLY
|
CF (Garhwal)
|
19/07/2024
|
sir, eds objection has been removed by dfo office.
|
|
26
|
CF (Garhwal)
|
REPLY
|
Nodal Officer
|
24/07/2024
|
Sir Please received the information this proposal
|
|
27
|
Nodal Officer
|
EDS
|
CF (Garhwal)
|
23/09/2024
|
CF/DFO is asked to attend the shortcomings according to the send EDS letter by nodal office.
|
|
28
|
CF (Garhwal)
|
EDS
|
DFO (Badrinath,Gopeshwar)
|
24/09/2024
|
Please find tha attachment
|
|