TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/UK/ROAD/11258/2015              (ii). Name of Project for which Forest Land is required : Dheghat - Nagchula To Chanterkhali -Kaliyalingudh Jhipa Bend Motor Road.              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : By the Construction of Dheghat - Nagchula To Chanterkhali -Kaliyalingudh Jhipa Bend Motor Road (2.50 km.). Villagers related these portion will got benefit therefore construction of above mentioned road is important for effected villagers              (iv). File no. : 8B/UCP/06/174/2016              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 1.485
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/ROAD/11258/201529/03/201517/10/2015  07/04/2015   20/10/2015  01/09/2015   08/02/2016   08/03/2016 Almora :04/06/2016North Kumaun:
  13/07/2016 (Almora)

Uttarakhand:
18/07/2016
Uttarakhand:
23/07/2016
Dehradun:
01/08/2016
17/11/2016
By :Regional Office
Uttarakhand
02/09/2024
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:09/08/2016  
Replied by State Government(Uttarakhand) on:04/11/2016  
Query raised by State Government (Uttarakhand) on:29/08/2016  
Replied by Nodal Officer (Uttarakhand) on:28/10/2016  
Query raised by Nodal Officer (Uttarakhand) on:04/09/2016  
Replied by Circle(North Kumaun) on:27/10/2016  
Query raised by Circle (North Kumaun) on:12/09/2016  
Query raised by DFO (Almora) on:10/06/2016  
Replied by UA on :28/06/2016  
Query raised by DFO (Almora) on:15/09/2016  
Replied by UA on :25/10/2016  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:21/02/2025  
Query raised by State Government (Uttarakhand) on:24/02/2025  
Query raised by Nodal Officer on:04/03/2025  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .