A. General Details
  (i). Proposal No. : FP/UK/ROAD/11142/2015              (ii). Name of Project for which Forest Land is required : Naudkhal Malakota Road to Sirasu M R              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : This Project is Comes under Pradhan mantari Gram Sadak Yogna Norms. There is no other alternates except Forest Land to Connect this (Sirasu) Village.              (iv). File no. : 8B/UCP/06/201/2019/FC/06              (v). State : Uttarakhand              (vi). Category of the Project : Road              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 9.541
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/UK/ROAD/11142/201521/03/201521/03/2015   26/05/2015   05/06/2015   11/06/2015 Rajaji National Park Division :12/06/2015Rajaji National Park:
  04/11/2019 (Rajaji National Park Division)

Uttarakhand:
04/11/2019
Uttarakhand:
29/11/2019
Dehradun:
15/12/2019
29/04/2020
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:02/01/2020  
Replied by State Government(Uttarakhand) on:25/02/2020  
Query raised by Regional Office (Dehradun) on:03/03/2020  
Replied by State Government(Uttarakhand) on:19/03/2020  
Query raised by State Government (Uttarakhand) on:05/01/2020  
Replied by Nodal Officer (Uttarakhand) on:25/02/2020  
Query raised by State Government (Uttarakhand) on:04/03/2020  
Replied by Nodal Officer (Uttarakhand) on:19/03/2020  
Query raised by Nodal Officer (Uttarakhand) on:13/11/2019  
Replied by Circle(Rajaji National Park) on:19/11/2019  
Query raised by Nodal Officer (Uttarakhand) on:06/01/2020  
Replied by Circle(Rajaji National Park) on:21/01/2020  
Query raised by Nodal Officer (Uttarakhand) on:22/01/2020  
Replied by Circle(Rajaji National Park) on:11/02/2020  
Query raised by Nodal Officer (Uttarakhand) on:04/03/2020  
Replied by Circle(Rajaji National Park) on:16/03/2020  
Query raised by Circle (Rajaji National Park) on:04/11/2019  
Replied by DFO (Rajaji National Park Division) on:04/11/2019  
Query raised by Circle (Rajaji National Park) on:14/11/2019  
Replied by DFO (Rajaji National Park Division) on:19/11/2019  
Query raised by Circle (Rajaji National Park) on:07/01/2020  
Replied by DFO (Rajaji National Park Division) on:21/01/2020  
Query raised by Circle (Rajaji National Park) on:21/01/2020  
Replied by DFO (Rajaji National Park Division) on:21/01/2020  
Query raised by Circle (Rajaji National Park) on:22/01/2020  
Replied by DFO (Rajaji National Park Division) on:11/02/2020  
Query raised by Circle (Rajaji National Park) on:06/03/2020  
Replied by DFO (Rajaji National Park Division) on:16/03/2020  
Query raised by DFO (Rajaji National Park Division) on:28/02/2019  
Replied by UA on :08/06/2019  
Query raised by DFO (Rajaji National Park Division) on:04/10/2019  
Replied by UA on :14/10/2019  
Query raised by DFO (Rajaji National Park Division) on:01/11/2019  
Replied by UA on :01/11/2019  
Query raised by DFO (Rajaji National Park Division) on:14/11/2019  
Replied by UA on :18/11/2019  
Query raised by DFO (Rajaji National Park Division) on:07/01/2020  
Replied by UA on :17/01/2020  
Query raised by DFO (Rajaji National Park Division) on:18/01/2020  
Replied by UA on :20/01/2020  
Query raised by DFO (Rajaji National Park Division) on:27/01/2020  
Replied by UA on :27/01/2020  
Query raised by DFO (Rajaji National Park Division) on:28/01/2020  
Replied by UA on :28/01/2020  
Query raised by DFO (Rajaji National Park Division) on:07/02/2020  
Replied by UA on :11/02/2020  
Query raised by DFO (Rajaji National Park Division) on:06/03/2020  
Replied by UA on :12/03/2020  
NOTE:- Stage-I Approval accorded by : Regional Office .