  (i). Proposal No. : FP/UK/Others/10660/2015              (ii). Name of Project for which Forest Land is required : 33/11 KV SUBSTATION AT GULAR IN DOGI PATTI OF NARENDRANAGAR BLOCK IN TEHRI DISTRICT              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : this substation is required to be constructed to give good quality of electric supply to this remote area of narendra nagar block              (iv). File no. : 8B/UCP/09/63/2016              (v). State : Uttarakhand              (vi). Category of the Project : Others              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.12
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/UK/Others/10660/201503/03/201505/04/2015  07/03/2015   28/07/2015  28/03/2015   17/10/2015   03/11/2015 Narendranagar,Munikireti :17/11/2015Bhagirathi:
  02/12/2015 (Narendranagar,Munikireti)

Uttarakhand:
24/02/2016
Uttarakhand:
19/03/2016
Dehradun:
11/04/2016
30/03/2017
By :Regional Office
Uttarakhand
01/08/2018
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Dehradun) on:28/04/2016  
Replied by State Government(Uttarakhand) on:25/07/2016  
Query raised by Regional Office (Dehradun) on:10/08/2016  
Replied by State Government(Uttarakhand) on:25/07/2016  
Query raised by State Government (Uttarakhand) on:11/05/2016  
Replied by Nodal Officer (Uttarakhand) on:23/07/2016  
Query raised by State Government (Uttarakhand) on:23/08/2016  
Replied by Nodal Officer (Uttarakhand) on:04/03/2017  
Query raised by Nodal Officer (Uttarakhand) on:26/02/2016  
Replied by Circle(Bhagirathi) on:16/03/2016  
Query raised by Nodal Officer (Uttarakhand) on:17/05/2016  
Replied by Circle(Bhagirathi) on:15/06/2016  
Query raised by Nodal Officer (Uttarakhand) on:04/09/2016  
Replied by Circle(Bhagirathi) on:17/01/2017  
Query raised by Nodal Officer (Uttarakhand) on:02/02/2017  
Replied by Circle(Bhagirathi) on:28/02/2017  
Query raised by Circle (Bhagirathi) on:04/12/2015  
Replied by DFO (Narendranagar,Munikireti) on:30/01/2016  
Query raised by Circle (Bhagirathi) on:29/02/2016  
Replied by DFO (Narendranagar,Munikireti) on:08/03/2016  
Query raised by Circle (Bhagirathi) on:17/05/2016  
Replied by DFO (Narendranagar,Munikireti) on:15/06/2016  
Query raised by Circle (Bhagirathi) on:05/09/2016  
Replied by DFO (Narendranagar,Munikireti) on:12/01/2017  
Query raised by Circle (Bhagirathi) on:06/02/2017  
Replied by DFO (Narendranagar,Munikireti) on:25/02/2017  
Query raised by DFO (Narendranagar,Munikireti) on:05/12/2015  
Replied by UA on :29/01/2016  
Query raised by DFO (Narendranagar,Munikireti) on:29/02/2016  
Replied by UA on :05/03/2016  
Query raised by DFO (Narendranagar,Munikireti) on:18/05/2016  
Replied by UA on :06/06/2016  
Query raised by DFO (Narendranagar,Munikireti) on:09/06/2016  
Replied by UA on :09/06/2016  
Query raised by DFO (Narendranagar,Munikireti) on:07/09/2016  
Replied by UA on :12/01/2017  
Query raised by DFO (Narendranagar,Munikireti) on:12/01/2017  
Replied by UA on :12/01/2017  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Dehradun) on:04/11/2020  
Replied by State Government(Uttarakhand) on:04/11/2020  
Query raised by Regional Office (Dehradun) on:06/11/2020  
Query raised by State Government (Uttarakhand) on:08/11/2020  
Query raised by Nodal Officer on:08/11/2020  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .