Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Mussoorie)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
31/10/2019
|
Kindly, Remove the pointwise objection as per this office letter No. 1705/12-1, Dated 31-10-2019.
|
|
2
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Mussoorie)
|
12/12/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Mussoorie)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
24/12/2019
|
Kindly, Original hard copy of proposal is not revived in office for further action. Remove the pointwise objection as per this office letter No. 1705/12-1, Dated 31-10-2019 & sent two original hard copy of proposal in this office for further action.
|
|
4
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Mussoorie)
|
06/01/2020
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Mussoorie)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
14/01/2020
|
Kindly, Remove the pointwise objection as per this office letter No. 1705/12-1, Dated 31-10-2019 & letter no. 2947/12-1 dt. 14-01-2020.
|
|
6
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Mussoorie)
|
30/01/2020
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Mussoorie)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
02/02/2020
|
Kindly, Remove the pointwise objection as per this office letter No. 1705/12-1, Dated 31-10-2019 & letter no. 2947/12-1 dt. 14-01-2020. Your reply is not above. Pl. see & watch online proposal Part-I & hard copy of proposal.
|
|
8
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Mussoorie)
|
03/02/2020
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Mussoorie)
|
EDS
|
User Agency (tarit.mohan@ril.com)
|
12/02/2020
|
Kindly, Remove the pointwise objection as per this office letter No. 3333/12-1, Dated 10-02-2020, letter No. 1705/12-1, Dated 31-10-2019 & letter no. 2947/12-1 dt. 14-01-2020. Your reply is not above. Pl. see & watch online proposal Part-I & hard copy of proposal.
|
|
10
|
User Agency (tarit.mohan@ril.com)
|
REPLY
|
DFO (Mussoorie)
|
27/02/2020
|
The correction have been made as per the instruction received
|
|