Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Head Office
|
EDS
|
State secretary
|
13/05/2022
|
EDS
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
23/05/2022
|
EDS
|
|
3
|
Nodal Officer
|
EDS
|
CF (Western)
|
23/05/2022
|
Necessary corrections has been made as per letter attached. Please do the needful.
|
|
4
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
25/05/2022
|
As per letter attached do the needful.
|
|
5
|
DFO (Haldwani)
|
EDS
|
User Agency (dfdmkhanansharda@gmail.com)
|
26/05/2022
|
As per the letter attached do the needful
|
|
6
|
User Agency (dfdmkhanansharda@gmail.com)
|
REPLY
|
DFO (Haldwani)
|
02/07/2022
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
01/08/2022
|
the correction has been reslove
|
|
8
|
CF (Western)
|
REPLY
|
Nodal Officer
|
05/08/2022
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
9
|
Nodal Officer
|
EDS
|
CF (Western)
|
18/08/2022
|
find the letter attached
|
|
10
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
20/08/2022
|
As per letter attached, kindly do the needful.
|
|
11
|
DFO (Haldwani)
|
EDS
|
User Agency (dfdmkhanansharda@gmail.com)
|
25/08/2022
|
As per letter attached, kindly do the needful.
|
|
12
|
User Agency (dfdmkhanansharda@gmail.com)
|
REPLY
|
DFO (Haldwani)
|
27/08/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
07/09/2022
|
Sir,
correction has been done and enclosed
|
|
14
|
CF (Western)
|
REPLY
|
Nodal Officer
|
12/09/2022
|
Necessary shortcomings has been rectified as per letter attached. Please do the needful.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Western)
|
22/09/2022
|
find the letter attached
|
|
16
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
22/09/2022
|
As per letter attached, kindly do the needful.
|
|
17
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
26/09/2022
|
certificate clwl
|
|
18
|
CF (Western)
|
REPLY
|
Nodal Officer
|
29/09/2022
|
As per EDS necessary shortcomings has been rectified by the Concerned Authority as letter attached. Please do the needful.
|
|
19
|
Nodal Officer
|
EDS
|
CF (Western)
|
11/10/2022
|
find the letter attached
|
|
20
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
12/10/2022
|
As per objection raised do the needful.
|
|
21
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
15/10/2022
|
Sir,
correction has been done
|
|
22
|
CF (Western)
|
REPLY
|
Nodal Officer
|
15/10/2022
|
As per objection raised necessary shortcomings has been rectified as per letter attached. Please do the needful.
|
|
23
|
Nodal Officer
|
REPLY
|
State secretary
|
19/10/2022
|
As per objection raised necessary shortcomings has been rectified as per letter attached. Please do the needful.
|
|
24
|
State secretary
|
REPLY
|
Head Office
|
19/10/2022
|
As per objection raised necessary shortcomings has been rectified as per letter attached. Please do the needful.
|
|
25
|
Head Office
|
EDS
|
State secretary
|
06/12/2022
|
EDS
|
|
26
|
State secretary
|
EDS
|
Nodal Officer
|
06/12/2022
|
EDS
|
|
27
|
Nodal Officer
|
EDS
|
CF (Western)
|
06/12/2022
|
EDS
|
|
28
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
07/12/2022
|
Do the needful as letter attached.
|
|
29
|
DFO (Haldwani)
|
EDS
|
User Agency (dfdmkhanansharda@gmail.com)
|
16/12/2022
|
Do the needful as letter attached.
|
|
30
|
User Agency (dfdmkhanansharda@gmail.com)
|
REPLY
|
DFO (Haldwani)
|
26/12/2022
|
The correction have been made as per the instruction received
|
|
31
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
28/12/2022
|
reply to EDS pointwise ans
|
|
32
|
CF (Western)
|
REPLY
|
Nodal Officer
|
31/12/2022
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
03/01/2023
|
The correction have been made as per the instruction received
|
|
34
|
State secretary
|
REPLY
|
Head Office
|
03/01/2023
|
The correction have been made as per the instruction received
|
|
35
|
Head Office
|
EDS
|
State secretary
|
31/01/2023
|
EDS cum TWP
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
31/01/2023
|
EDS cum TWP
|
|
37
|
Nodal Officer
|
EDS
|
CF (Western)
|
31/01/2023
|
State Government may attend to the shortcomings as per the minutes of FRCM attached.
|
|
38
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
01/02/2023
|
As per letter attached, Kindly do the needful.
|
|
39
|
DFO (Haldwani)
|
EDS
|
User Agency (dfdmkhanansharda@gmail.com)
|
02/02/2023
|
As per letter attached, Kindly do the needful.
|
|
40
|
User Agency (dfdmkhanansharda@gmail.com)
|
REPLY
|
DFO (Haldwani)
|
02/02/2023
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
04/02/2023
|
?????? ?? ??????? ?? ??????? ???
|
|
42
|
CF (Western)
|
REPLY
|
Nodal Officer
|
04/02/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
43
|
Nodal Officer
|
EDS
|
CF (Western)
|
06/02/2023
|
please upload correct file of KML file of CA area
|
|
44
|
CF (Western)
|
EDS
|
DFO (Haldwani)
|
06/02/2023
|
As per Nodal officer please upload correct file of KML file of CA area
|
|
45
|
DFO (Haldwani)
|
REPLY
|
CF (Western)
|
06/02/2023
|
As per letter attached, kindly do needful
|
|
46
|
CF (Western)
|
REPLY
|
Nodal Officer
|
06/02/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Kindly do the needful.
|
|
47
|
Nodal Officer
|
REPLY
|
State secretary
|
07/02/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|
48
|
State secretary
|
REPLY
|
Head Office
|
07/02/2023
|
As per EDS necessary shortcomings has been rectified as letter attached. Please do the needful.
|
|