Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Tripura North)
|
EDS
|
DFO (North District Forest)
|
17/10/2020
|
The Proposal has been examined. The shortcomings have been noticed. The same is attached as pdf file for compliance and submission.
|
|
2
|
DFO (North District Forest)
|
REPLY
|
CF (Tripura North)
|
19/10/2020
|
The shortcomings in the initial application has been rectified, the CA scheme estimate file has been uploaded, further the justification for choosing the degraded forest land has also been provided.
|
|
3
|
Regional Office
|
EDS
|
State secretary
|
23/11/2020
|
State Government is requested to kindly furnish the additional information.
|
|
4
|
State secretary
|
REPLY
|
Regional Office
|
29/12/2020
|
Reply furnish against observation made by the MoEF & CC, Regional Office, Shillong.
|
|