  (i). Proposal No. : FP/TN/IND/34099/2018              (ii). Name of Project for which Forest Land is required : TWAD 20 MGD CLOSED CONDUIT SCHEME              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : 20 MGD water supply scheme closed conduit system water supply scheme to Thermal power project SIPCOT complex. Heavy water plant and other industries in Thoothukudi District for Drinking and industrial purposes in SF No 600 of Srivaikuntam Forest Block Reserved Land              (iv). File no. : 4-TNB033/2019-CHN              (v). State : Tamil Nadu              (vi). Category of the Project : Industry              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 0.08
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onCompliance Report Submitted by State onStage-II Approval on
FP/TN/IND/34099/201811/06/201812/07/2018  09/07/2018   17/07/2018  12/07/2018   19/07/2018   31/07/2018 Thoothukudi :02/08/2018Tirunelveli:
  03/09/2018 (Thoothukudi)

Tamil Nadu:
20/09/2018
Tamil Nadu:
26/10/2018
Chennai:
26/03/2019
18/08/2020
By :Regional Office
Tamil Nadu
18/05/2022
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Chennai) on:10/04/2019  
Replied by State Government(Tamil Nadu) on:24/12/2019  
Query raised by Regional Office (Chennai) on:20/01/2020  
Replied by State Government(Tamil Nadu) on:04/08/2020  
Query raised by State Government (Tamil Nadu) on:21/12/2018  
Replied by Nodal Officer (Tamil Nadu) on:23/01/2019  
Query raised by State Government (Tamil Nadu) on:19/02/2019  
Replied by Nodal Officer (Tamil Nadu) on:26/02/2019  
Query raised by State Government (Tamil Nadu) on:28/02/2019  
Replied by Nodal Officer (Tamil Nadu) on:28/02/2019  
Query raised by State Government (Tamil Nadu) on:28/11/2019  
Replied by Nodal Officer (Tamil Nadu) on:28/11/2019  
Query raised by Nodal Officer (Tamil Nadu) on:26/09/2018  
Replied by Circle(Tirunelveli) on:08/10/2018  
Query raised by Nodal Officer (Tamil Nadu) on:07/01/2019  
Replied by Circle(Tirunelveli) on:18/01/2019  
Query raised by Nodal Officer (Tamil Nadu) on:19/02/2019  
Replied by Circle(Tirunelveli) on:21/02/2019  
Query raised by Circle (Tirunelveli) on:08/10/2018  
Replied by DFO (Thoothukudi) on:08/10/2018  
Query raised by Circle (Tirunelveli) on:08/01/2019  
Replied by DFO (Thoothukudi) on:08/01/2019  
Query raised by Circle (Tirunelveli) on:19/02/2019  
Replied by DFO (Thoothukudi) on:20/02/2019  
Query raised by Circle (Tirunelveli) on:20/02/2019  
Replied by DFO (Thoothukudi) on:21/02/2019  
D. Essential Details Sought History (Stage-II)
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & User Agency
Query raised by Regional Office (Chennai) on:30/06/2022  
Query raised by State Government (Tamil Nadu) on:17/10/2022  
Replied by Nodal Officer (Tamil Nadu) on:07/06/2023  
Query raised by State Government (Tamil Nadu) on:25/08/2023  
Query raised by Nodal Officer on:24/10/2024  
NOTE:- Proposal is pending at User Agency due to EDS raised by RO for Stage-II .