| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
Regional Office
|
EDS
|
State secretary
|
12/04/2022
|
EDS
|
|
|
2
|
State secretary
|
EDS
|
Nodal Officer
|
28/10/2022
|
furnish the required information
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Adilabad)
|
28/10/2022
|
furnish the required information as called for by IRO
|
|
|
4
|
CF (Adilabad)
|
EDS
|
DFO (Asifabad)
|
17/01/2023
|
Please Furnish the EDS replies
|
|
|
5
|
DFO (Asifabad)
|
EDS
|
User Agency (eerbasifabad@gmail.com)
|
18/01/2023
|
Design cross section of the proposed road clearly indicating the width of carriage way BT portion shoulders Berm drainage etc may be furnished
Revised map kml file and map etc for an area of 3.412 ha of nonforest area proposed for CA purpose shall be uploaded in the online application
MAP and DGPS data for the entire area of 81.4313 ha NFL may be submitted
|
|
|
6
|
User Agency (eerbasifabad@gmail.com)
|
REPLY
|
DFO (Asifabad)
|
18/02/2023
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Asifabad)
|
REPLY
|
CF (Adilabad)
|
17/03/2023
|
Replies to Addl. information submitted
|
|
|
8
|
CF (Adilabad)
|
EDS
|
DFO (Asifabad)
|
27/04/2023
|
DFO is requested to Address UA to Upload Map In parivesh portal
|
|
|
9
|
DFO (Asifabad)
|
EDS
|
User Agency (eerbasifabad@gmail.com)
|
27/04/2023
|
UA is requested to Upload Revised map and KML details
|
|
|
10
|
User Agency (eerbasifabad@gmail.com)
|
REPLY
|
DFO (Asifabad)
|
28/04/2023
|
The correction have been made as per the instruction received
|
|
|
11
|
DFO (Asifabad)
|
REPLY
|
CF (Adilabad)
|
28/04/2023
|
Replies to Addl. information submitted
|
|
|
12
|
CF (Adilabad)
|
EDS
|
DFO (Asifabad)
|
13/10/2023
|
please upload correct and revised CA detail
|
|
|
13
|
DFO (Asifabad)
|
EDS
|
User Agency (eerbasifabad@gmail.com)
|
13/10/2023
|
UA is requested to upload coeect CA NFL details
|
|
|
14
|
User Agency (eerbasifabad@gmail.com)
|
REPLY
|
DFO (Asifabad)
|
13/10/2023
|
The correction have been made as per the instruction received
|
|
|
15
|
DFO (Asifabad)
|
REPLY
|
CF (Adilabad)
|
13/10/2023
|
Sir, EDS reply of Govena to jambuldhara is uploaded online with revised CA details and eds replies for NA.
|
|
|
16
|
CF (Adilabad)
|
REPLY
|
Nodal Officer
|
13/10/2023
|
Sir, EDS reply of Govena to jambuldhara is submitted by DFO is forwarded and uploaded online with revised CA details and eds replies for NA.
|
|
|
17
|
Nodal Officer
|
REPLY
|
State secretary
|
16/10/2023
|
EDS submitted
|
|
|
18
|
State secretary
|
REPLY
|
Regional Office
|
16/10/2023
|
replies furnished herewith.
|
|