TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/SK/TRANS/157621/2022              (ii). Name of Project for which Forest Land is required : Diversion of forest land for laying of 220kV D/C Singhik to Chungthang TL in North Sikkim under CSSTDS by Energy & Power Department, Govt. of Sikkim              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Energy and Power Department Government of Sikkim is constructing 19 No's of Substation and 29 No's of Transmission Line in Sikkim for integrated power development and in the scheme the construction of 220kV D/C Singhik-chungthang Transmission Line is one of it.              (iv). File no. : IRO/KOL/SK/TRANS/157621/2022              (v). State : Sikkim              (vi). Category of the Project : Transmission Line              (vii). Shape of forest land proposed to be diverted : Linear              (viii). Area of forest land proposed for diversion(in ha.): 26.8
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentRegional OfficeStage-I Approval onStage-II Approval on
FP/SK/TRANS/157621/202228/06/202219/07/2022   02/09/2022   15/09/2022   15/09/2022 North Territorial :15/09/2022Territorial:
  06/02/2023 (North Territorial)

Sikkim:
16/03/2023
Sikkim:
16/03/2023
Kolkata:
16/03/2023
16/06/2023
By :Regional Office
  
C. Essential Details Sought History
Communication between Regional Office & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by Regional Office (Kolkata) on:20/03/2023  
Replied by State Government(Sikkim) on:31/03/2023  
Query raised by Regional Office (Kolkata) on:04/05/2023  
Replied by State Government(Sikkim) on:19/05/2023  
Query raised by State Government (Sikkim) on:31/03/2023  
Replied by Nodal Officer (Sikkim) on:31/03/2023  
Query raised by State Government (Sikkim) on:19/05/2023  
Replied by Nodal Officer (Sikkim) on:19/05/2023  
Query raised by Nodal Officer (Sikkim) on:16/03/2023  
Replied by Circle(Territorial) on:16/03/2023  
Query raised by Nodal Officer (Sikkim) on:19/05/2023  
Replied by Circle(Territorial) on:19/05/2023  
Query raised by Circle (Territorial) on:16/03/2023  
Replied by DFO (North Territorial) on:16/03/2023  
Query raised by Circle (Territorial) on:19/05/2023  
Replied by DFO (North Territorial) on:19/05/2023  
NOTE:- Stage-I Approval accorded by : Regional Office .
Close(X)
Close(X)
Please wait ...