Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
08/10/2018
|
hard copy of Proposal not received yet.
|
|
2
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
09/10/2018
|
the hard copy had been sent
|
|
3
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
09/10/2018
|
hard copy of Proposal not received yet..
|
|
4
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
09/10/2018
|
the hard copy had been sent
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
27/11/2018
|
eds
|
|
6
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
27/11/2018
|
Regarding objection.
|
|
7
|
DFO (Gurdaspur)
|
EDS
|
User Agency (pannuinternational001@gmail.com)
|
10/12/2018
|
submit documents as asked by higher officials
|
|
8
|
User Agency (pannuinternational001@gmail.com)
|
REPLY
|
DFO (Gurdaspur)
|
23/05/2019
|
The correction have been made as per the instruction received
|
|
9
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
27/05/2019
|
Objection has been removed
|
|
10
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
27/05/2019
|
Report sent to your office vide DFO Gurdaspur letter No. 405 Dated 24.05.2019.
|
|
11
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
01/07/2019
|
eds
|
|
12
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
02/07/2019
|
regarding objection.
|
|
13
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
06/08/2019
|
Objection has been removed
|
|
14
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
06/08/2019
|
Report sent to your office vide DFO Gurdaspur letter no . 929 Dated 05.08.2019.
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
14/10/2019
|
eds
|
|
16
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
16/10/2019
|
regarding objection.
|
|
17
|
DFO (Gurdaspur)
|
EDS
|
User Agency (pannuinternational001@gmail.com)
|
09/12/2019
|
regarding Objection
|
|
18
|
User Agency (pannuinternational001@gmail.com)
|
REPLY
|
DFO (Gurdaspur)
|
31/01/2020
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
31/01/2020
|
objection has been removed
|
|
20
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
31/01/2020
|
Report sent to your office vide DFO Gurdaspur Letter No. 1966 Dated 09.12.2019.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
03/02/2020
|
eds
|
|
22
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
04/02/2020
|
eds
|
|
23
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
11/02/2020
|
Objection has been Removed.
|
|
24
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
12/02/2020
|
Report sent to your office vide DFO Gurdaapur letter no. 2355 Dated 04.02.2020.
|
|
25
|
State secretary
|
EDS
|
Nodal Officer
|
13/07/2020
|
eds
|
|
26
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
13/07/2020
|
eds
|
|
27
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
13/07/2020
|
Regarding objection.
|
|
28
|
DFO (Gurdaspur)
|
EDS
|
User Agency (pannuinternational001@gmail.com)
|
27/08/2020
|
Submit the Undertaking of Penal NPV as Per Instruction received.
|
|
29
|
User Agency (pannuinternational001@gmail.com)
|
REPLY
|
DFO (Gurdaspur)
|
04/02/2021
|
The correction have been made as per the instruction received
|
|
30
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
24/02/2021
|
Objection has been removed
|
|
31
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
25/02/2021
|
plz upload revised Part-III in online Part-II.
|
|
32
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
25/02/2021
|
Objection has been removed
|
|
33
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
26/02/2021
|
Report sent to your office vide DFO Gurdaspur letter no. 2511 dated 22.02.2021.
|
|
34
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
09/03/2021
|
Please upload correct undertaking to provide Cost or NFL
|
|
35
|
CF (Bist circle)
|
EDS
|
DFO (Gurdaspur)
|
09/03/2021
|
Please upload correct undertaking to provide Cost or NFL
|
|
36
|
DFO (Gurdaspur)
|
REPLY
|
CF (Bist circle)
|
09/03/2021
|
Objection has been removed
|
|
37
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
09/03/2021
|
Objection has been removed by dfo gurdaspur.
|
|
38
|
Nodal Officer
|
REPLY
|
State secretary
|
09/03/2021
|
Recommended
|
|