Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
04/12/2019
|
EDS
|
|
2
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
04/12/2019
|
EDS
|
|
3
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
16/12/2019
|
Regarding Objections
|
|
4
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
17/12/2019
|
Report sent to your office vide DFO Jalandhar letter no. 8012 dated 13.12.2019.
|
|
5
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
17/12/2019
|
Please provide correct violation report.
|
|
6
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
17/12/2019
|
Please provide correct violation report.
|
|
7
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
17/12/2019
|
VIOLATION UPDATED, PLEASE FORWARD TO NODAL OFFICER
|
|
8
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
17/12/2019
|
VIOLATION UPDATED, PLEASE FORWARD TO NODAL OFFICER
|
|
9
|
State secretary
|
EDS
|
Nodal Officer
|
09/01/2020
|
eds
|
|
10
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
09/01/2020
|
EDS
|
|
11
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
09/01/2020
|
regarding objection.
|
|
12
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
20/01/2020
|
Regarding FRA
|
|
13
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
20/01/2020
|
Regarding FRA
|
|
14
|
Nodal Officer
|
REPLY
|
State secretary
|
11/02/2020
|
Reply
|
|
15
|
Regional Office
|
EDS
|
State secretary
|
16/03/2020
|
eds
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
18/03/2020
|
eds
|
|
17
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
18/03/2020
|
eds
|
|
18
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
18/03/2020
|
Objection.
|
|
19
|
DFO (Jalandhar)
|
EDS
|
User Agency (agiinfra2019@gmail.com)
|
20/03/2020
|
Regarding Objection
|
|
20
|
User Agency (agiinfra2019@gmail.com)
|
REPLY
|
DFO (Jalandhar)
|
22/05/2020
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
27/05/2020
|
Regarding Objections
|
|
22
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
27/05/2020
|
plz remove objection.
|
|
23
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
27/05/2020
|
Objection removed...
|
|
24
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
27/05/2020
|
Report sent to your office vide DFO Jalandhar letter no. 357 Dated 22.05.2020.
|
|
25
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
17/06/2020
|
Please upload all the necessary documents informed through phone, at additional information details of Part-II after countersigned by DFO
|
|
26
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
17/06/2020
|
Please upload all the necessary documents informed through phone, at additional information details of Part-II after countersigned by DFO
|
|
27
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
24/06/2020
|
All the documents are uploaded in Part II
|
|
28
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
25/06/2020
|
All the documents are uploaded in Part II by DFO Jalandhar.
|
|
29
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
14/07/2020
|
eds
|
|
30
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
14/07/2020
|
Regarding objection.
|
|
31
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
03/08/2020
|
Objections removed
|
|
32
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
04/08/2020
|
Report sent to your office vide DFO Jalandhar Letter no. 2229 Dated 24.07.2020.
|
|
33
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
07/08/2020
|
Please upload NOC from PWD and Damage report.
|
|
34
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
10/08/2020
|
Please upload NOC from PWD and Damage report.
|
|
35
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
11/08/2020
|
NOC from PWD and Damage report has been uploaded
|
|
36
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
14/08/2020
|
NOC from PWD and Damage report has been uploaded by DFO Jalandhar.
|
|
37
|
Nodal Officer
|
REPLY
|
State secretary
|
21/09/2020
|
reply
|
|
38
|
State secretary
|
EDS
|
Nodal Officer
|
05/10/2020
|
Please upload revised CA land suitability certificate in Part-II
|
|
39
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
05/10/2020
|
Please upload revised CA land suitability certificate in Part-II
|
|
40
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
05/10/2020
|
Please upload revised CA land suitability certificate in Part-II
|
|
41
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
05/10/2020
|
Revised CA Land Suitability Certificate uploaded in Part II
|
|
42
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
05/10/2020
|
Revised CA Land Suitability Certificate uploaded in Part II by dfo jalandhar.
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
09/10/2020
|
Reply
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
09/10/2020
|
Reply
|
|