| Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
|
1
|
DFO (Jalandhar)
|
EDS
|
User Agency (balraj1234987@gmail.com)
|
07/03/2019
|
gpm fees
|
|
|
2
|
User Agency (balraj1234987@gmail.com)
|
REPLY
|
DFO (Jalandhar)
|
11/03/2019
|
The correction have been made as per the instruction received
|
|
|
3
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
03/05/2019
|
eds
|
|
|
4
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
03/05/2019
|
Regarding objection.
|
|
|
5
|
DFO (Jalandhar)
|
EDS
|
User Agency (balraj1234987@gmail.com)
|
07/05/2019
|
Regarding Objection
|
|
|
6
|
User Agency (balraj1234987@gmail.com)
|
REPLY
|
DFO (Jalandhar)
|
15/05/2019
|
The correction have been made as per the instruction received
|
|
|
7
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
29/05/2019
|
objections
|
|
|
8
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
31/05/2019
|
Report sent to your office vide DFO Jalandhar Letter No 1298 Dated 29.05.2019.
|
|
|
9
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
19/06/2019
|
Toposheet of CA Site not uploaded. New CA Scheme not uploaded.
|
|
|
10
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
20/06/2019
|
Toposheet of CA Site not uploaded. New CA Scheme not uploaded.
|
|
|
11
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
27/06/2019
|
new ca scheme uploaded
|
|
|
12
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
27/06/2019
|
objection.
|
|
|
13
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
01/07/2019
|
correction have been made
|
|
|
14
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
02/07/2019
|
correction has been made by DFO Jalandhar.
|
|
|
15
|
Nodal Officer
|
EDS
|
CF (Bist circle)
|
02/07/2019
|
As per telephonic conversation, case is sent back to CF.
|
|
|
16
|
CF (Bist circle)
|
EDS
|
DFO (Jalandhar)
|
03/07/2019
|
As per telephonic conversation, case is sent back to DFO.
|
|
|
17
|
DFO (Jalandhar)
|
REPLY
|
CF (Bist circle)
|
24/07/2019
|
objection removed
|
|
|
18
|
CF (Bist circle)
|
REPLY
|
Nodal Officer
|
24/07/2019
|
objection removed by DFO Jalandhar.
|
|