Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Balliguda)
|
EDS
|
User Agency (ehtc.div.bam@optcl.co.in)
|
01/04/2023
|
Sir please submit the compliance as per discrepancies indicated vide letter No1964 dated 31.03.2023.
|
|
2
|
User Agency (ehtc.div.bam@optcl.co.in)
|
REPLY
|
DFO (Balliguda)
|
03/07/2023
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Kalahandi North)
|
EDS
|
User Agency (ehtc.div.bam@optcl.co.in)
|
11/07/2023
|
it is noticed that you have not enumerated tree in girth under 30 cm poles,the tower have been erected in the different village forest and enumerated tree numbering is not visible. hence done properly
|
|
4
|
User Agency (ehtc.div.bam@optcl.co.in)
|
REPLY
|
DFO (Kalahandi North)
|
04/08/2023
|
The correction have been made as per the instruction received
|
|
5
|
Regional Office
|
EDS
|
State secretary
|
25/04/2024
|
Addl. information sought from the State Govt.
|
|
6
|
State secretary
|
EDS
|
Nodal Officer
|
01/05/2024
|
For necessary compliance
|
|
7
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
08/05/2024
|
Please comply the EDS vide this office Memo No. 9652 dated 08.05.2024.
|
|
8
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
08/05/2024
|
Please comply the EDS vide this office Memo No. 9652 dated 08.05.2024.
|
|
9
|
CF (Berhampur)
|
EDS
|
DFO (Balliguda)
|
09/05/2024
|
furnish the compliance
|
|
10
|
DFO (Balliguda)
|
REPLY
|
CF (Berhampur)
|
28/05/2024
|
The compliance report along with its enclosures are hereby submitted vide this office memo No.2909 dated 16.05.2024.
|
|
11
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
30/05/2024
|
Compliance report
|
|
12
|
CF (Bhawanipatna)
|
EDS
|
DFO (Kalahandi North)
|
31/05/2024
|
Please comply the observations raised by the Govt. of India under point No.a to c.
|
|
13
|
DFO (Kalahandi North)
|
EDS
|
User Agency (ehtc.div.bam@optcl.co.in)
|
20/06/2024
|
Compliance report of memo No.9651 dt-08.05.2024 by CCF,Nodal
|
|
14
|
User Agency (ehtc.div.bam@optcl.co.in)
|
REPLY
|
DFO (Kalahandi North)
|
20/06/2024
|
The correction have been made as per the instruction received
|
|
15
|
DFO (Kalahandi North)
|
EDS
|
User Agency (ehtc.div.bam@optcl.co.in)
|
20/06/2024
|
SUBMIT DGPS SURVEY MAP WITH ORSAC AUTHENTICATION LETTER OF CA SITE PODMUNDI -BRAHMANI RF
|
|
16
|
User Agency (ehtc.div.bam@optcl.co.in)
|
REPLY
|
DFO (Kalahandi North)
|
29/11/2024
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Kalahandi North)
|
EDS
|
User Agency (ehtc.div.bam@optcl.co.in)
|
03/12/2024
|
Jointverification report and non encroachment and non-encumbrance of the proposed plantation site in Pattola and in the JV site has been found to be suitable for plantation
|
|
18
|
User Agency (ehtc.div.bam@optcl.co.in)
|
REPLY
|
DFO (Kalahandi North)
|
04/12/2024
|
The correction have been made as per the instruction received
|
|
19
|
DFO (Kalahandi North)
|
REPLY
|
CF (Bhawanipatna)
|
04/12/2024
|
After Joint verification by Range Officer,Bhawanipatna and concerned Tahasildar submitted the report verifying non encroachment and non-encumbrance of the proposed plantation site in Pattola (Sinang RF) and in the joint verification the site has been found to be suitable for plantation.
|
|
20
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
06/12/2024
|
The compliance to memo No.9652 dtd.08.05.2024 of the CCF(Nodal) has been submitted.
|
|
21
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
06/12/2024
|
Please comply to the EDS vied this office Memo No.24664 dated 06.12.2024.
|
|
22
|
CF (Bhawanipatna)
|
EDS
|
DFO (Kalahandi North)
|
10/12/2024
|
The DFO, Kalahandi North Division to comply the observations pointed out by the Addl.PCCF FDNO,FC Act to this office.
|
|