Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
28/09/2021
|
Non submission of Hardcopy of the proposal
|
|
2
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
09/01/2022
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
19/01/2022
|
Shortcoming in the DRP
|
|
4
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
29/01/2022
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
07/03/2022
|
Submission of Document as per check List
|
|
6
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
06/04/2022
|
The correction have been made as per the instruction received
|
|
7
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
27/04/2022
|
.
|
|
8
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
07/05/2022
|
DRP submitted vide memo No.3153 dtd.06.05.2022
|
|
9
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
11/05/2022
|
Submit compliance at an earliest.
|
|
10
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
12/05/2022
|
Submission of Document as per check List
|
|
11
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
25/05/2022
|
The correction have been made as per the instruction received
|
|
12
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
25/05/2022
|
Submission of DRP of By pass Road
|
|
13
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
05/07/2022
|
Please comply the observations point out vide this office letter No. 13051 dated 02.07.2022.
|
|
14
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
06/07/2022
|
Compliance to deficiencies raised by the CCF, FD & NO FC Act, Office of the TCCF, Odisha.
|
|
15
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
07/07/2022
|
Short coming in DRP
|
|
16
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
22/08/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
13/09/2022
|
Proposal for diversion of 6.56 ha. of forest land for construction of Bolangir By-pass Road(west) by the Executive Engineer,N.H Division,Bolangir.
|
|
18
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
13/09/2022
|
Kindly submit the necessary compliance as sought by the CCF, FD & NO, FC Act.
|
|
19
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
06/10/2022
|
The RCCF has scrutinized the DRP and raised some objection and returned vide memo no. 3193 dt.13.09.2022
|
|
20
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
24/11/2022
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
24/11/2022
|
Compliance report submited by the user Agency
|
|
22
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
25/11/2022
|
Kindly comply the Point No.6 of the observations made by the CCF, FD & NO, FC Act vide his Memo No. 13052 dt.02.07.2022 and submit the compliance report.
|
|
23
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
07/12/2022
|
Kindly submit the complete compliance to the point No.6 i.e Hal and Sabik Kisam of both forest and non-forest land of the project.
|
|
24
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
21/07/2023
|
The correction have been made as per the instruction received
|
|
25
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
25/07/2023
|
The Point No.6 of the observations made by the CCF, FD & NO, FC Act vide his Memo No. 13052 dt.02.07.2022 and submit the compliance report.
|
|
26
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
02/08/2023
|
Compliance under Sl. No. 1 to 10 as sought for vide Memo No. 13051 dated 02.07.2022 by the CCF, FD & NO, FC Act. has been submitted.
|
|
27
|
Regional Office
|
EDS
|
State secretary
|
30/09/2023
|
Addl. Information sought from the State Govt.
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
09/10/2023
|
For necessary compliance.
|
|
29
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
27/10/2023
|
Observations of GoI, MoEF & CC, may be complied.
|
|
30
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
04/11/2023
|
The DFO, Bolangir Forest Division is requested to submit the Point wise compliance as sought for by the Govt. of India, MOEF & CC, IRO, BBSR.
|
|
31
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
07/12/2023
|
Diversion of 6.56 ha. of forest land for construction of Bolangir By-pass Road (west) by the Executive Engineer, NH Division, Bolangir under Bolangir Forest Division- regarding submission of compliance.
|
|
32
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
12/12/2023
|
Compliance to GoI observations received from DFO, Bolangir has been submitted.
|
|
33
|
Nodal Officer
|
REPLY
|
State secretary
|
27/12/2023
|
Compliance submitted to GoI, MOEF & CC, IRO, BBSR vide this office Letter No. 25191 dated 26.12.2023
|
|
34
|
State secretary
|
REPLY
|
Regional Office
|
16/01/2024
|
Compliance furnished by PCCF (FD&NO, FCA), O/o the PCCF & HoFF, Odisha vide letter dtd.26.12.2023
|
|
35
|
Regional Office
|
EDS
|
State secretary
|
23/01/2024
|
Addl. information sought from the State Govt.
|
|
36
|
State secretary
|
EDS
|
Nodal Officer
|
29/01/2024
|
For necessary compliance.
|
|
37
|
Nodal Officer
|
EDS
|
CF (Bhawanipatna)
|
02/03/2024
|
Please comply the EDS vide this office Memo No. 523 5dated 02.03.2023
|
|
38
|
CF (Bhawanipatna)
|
EDS
|
DFO (Bolangir)
|
10/04/2024
|
Submit Compliance to GoI observations vide No.5-ORC603/2023-BHU dtd.23.01.2024.
|
|
39
|
DFO (Bolangir)
|
EDS
|
User Agency (sibu.taria@gmail.com)
|
26/04/2024
|
2602-Diversion of 6.56 Ha. of Forest land for construction of Bolangir By- Pass Road by N.H Division. Violation of Forest Conservation Act-1980-regarding.
|
|
40
|
User Agency (sibu.taria@gmail.com)
|
REPLY
|
DFO (Bolangir)
|
29/07/2024
|
The correction have been made as per the instruction received
|
|
41
|
DFO (Bolangir)
|
REPLY
|
CF (Bhawanipatna)
|
29/07/2024
|
Submission of compliance as objections raised by Dy. Inspector General of Forests, GoI,MoEF& CC, RO,BBSR,
|
|
42
|
CF (Bhawanipatna)
|
REPLY
|
Nodal Officer
|
30/07/2024
|
Compliance has been submitted to the observations of Govt. India
|
|
43
|
Nodal Officer
|
REPLY
|
State secretary
|
09/08/2024
|
Compliance to the observations of Govt. of India dated 23.01.2024 is enclosed.
|
|
44
|
State secretary
|
REPLY
|
Regional Office
|
20/08/2024
|
Compliance furnished by PCCF (FD&NO, FCA), O/o the PCCF & HoFF, Odisha vide letter dtd.09.08.2024.
|
|