Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
20/05/2021
|
Diversion of 3.003 Ha. of forest land for the project.
|
|
2
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
28/06/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
15/07/2021
|
Not submitted the connected documents.
|
|
4
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
03/08/2021
|
The correction have been made as per the instruction received
|
|
5
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
27/09/2021
|
Compliance to the objections wanting.
|
|
6
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
27/09/2021
|
Diversion of 3.003 Ha. Forest land for the project improvement to Narigaon - Gillaguntha - Betabadi Road
|
|
7
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
02/10/2021
|
The correction have been made as per the instruction received
|
|
8
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
12/10/2021
|
Compliance submitted
|
|
9
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
08/11/2021
|
Please comply EDS to the observations vide this office Memo No.18738 dated 06.11.2021
|
|
10
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
09/11/2021
|
Compliance to the observations need to be submitted
|
|
11
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
11/11/2021
|
Diversion of 3.003 Ha. of Forest land for the project impvorement of Narigaon-Gallaguntha-Betabadi Road.
|
|
12
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
02/08/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
06/10/2022
|
Compliance report of Diversion of 3.033 ha. of forest land for the Project "Improvement to Narigaon-Gillaguntha- Betabadi Road from 0/00 Km to 5/087 Km.
|
|
14
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
11/10/2022
|
Compliance to the shortcomings
|
|
15
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
12/10/2022
|
Diversion of 3.003 ha. of forest land for the project improvement to Narigaon to Gillaguntha Betabadi Road 5/087 km in the district of Koraput under RCPLWE Phase II scheme package no. OR 19 RCPL-13 for the year 2019-20
|
|
16
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
29/11/2022
|
The correction have been made as per the instruction received
|
|
17
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
16/12/2022
|
Point wise compliance report has been done.
|
|
18
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
20/12/2022
|
compliance to the shortcomings
|
|
19
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
22/12/2022
|
Diversion of 3.003 ha. of forest land for the project improvement to Narigaon, Gillagunaht, Betabadi road.
|
|
20
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
27/02/2023
|
The correction have been made as per the instruction received
|
|
21
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
04/03/2023
|
Diversion of 3.003 Ha. of Forest land for the project improvement to Narigaon - Gillaguntha - Betabadi Road from
|
|
22
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
15/03/2023
|
Compliance submitted.
|
|
23
|
Nodal Officer
|
EDS
|
CF (Koraput)
|
18/04/2023
|
Please comply the EDS vide this office Memo No. 7230 dated 17.04.2023.
|
|
24
|
CF (Koraput)
|
EDS
|
DFO (Koraput)
|
24/04/2023
|
compliance to objections raised by Nodal Officer
|
|
25
|
DFO (Koraput)
|
EDS
|
User Agency (eerandbkpt@gmail.com)
|
27/04/2023
|
Proposal for divrsionof 3.003 ha. of forest land for improvement to Narigaon-Gillaguntha Betabadi Road
|
|
26
|
User Agency (eerandbkpt@gmail.com)
|
REPLY
|
DFO (Koraput)
|
29/05/2023
|
The correction have been made as per the instruction received
|
|
27
|
DFO (Koraput)
|
REPLY
|
CF (Koraput)
|
29/05/2023
|
Diversion of 3.003 ha. of forest land for the project improvement to Narigaon to Gillaguntha & Betabadi Road from 0.00 Km to 5.087 km in the District of Koraput.
|
|
28
|
CF (Koraput)
|
REPLY
|
Nodal Officer
|
30/05/2023
|
Necessary compliance is furnished.
|
|