Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Phulbani)
|
EDS
|
User Agency (rwphulbani@yahoo.com)
|
19/03/2021
|
Submission of Diversion proposal
|
|
2
|
User Agency (rwphulbani@yahoo.com)
|
REPLY
|
DFO (Phulbani)
|
28/09/2021
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Phulbani)
|
EDS
|
User Agency (rwphulbani@yahoo.com)
|
29/09/2021
|
Forwarding
|
|
4
|
User Agency (rwphulbani@yahoo.com)
|
REPLY
|
DFO (Phulbani)
|
27/10/2021
|
The correction have been made as per the instruction received
|
|
5
|
State secretary
|
EDS
|
Nodal Officer
|
16/03/2022
|
District profile required to be filled in by the DFO, Phulbani Forest Division.
|
|
6
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
16/04/2022
|
The DFO Phulbani Forest Division has not fill up the District Profile details in Part-II in the Parivesh portal.
|
|
7
|
CF (Berhampur)
|
EDS
|
DFO (Phulbani)
|
18/04/2022
|
Fill up the District Profile details in Part-II in the Parivesh Portal
|
|
8
|
DFO (Phulbani)
|
REPLY
|
CF (Berhampur)
|
06/05/2022
|
Part-II details updated
|
|
9
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
20/05/2022
|
The DFO Phulbani Division has fill up the District Profile details in Part-II in the Parivesh Portal. copy of the same is enclosed
|
|
10
|
Nodal Officer
|
REPLY
|
State secretary
|
02/06/2022
|
DFO, Phulbani Forest Division has updated the District profile details in Part-II of the above project.
|
|
11
|
Regional Office
|
EDS
|
State secretary
|
10/06/2022
|
EDS sought from the State Govt.
|
|
12
|
State secretary
|
EDS
|
Nodal Officer
|
17/06/2022
|
Compliance may be furnished to the Ministry.
|
|
13
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
04/08/2022
|
Compliance to GoI, MoEF & CC observations to be furnished
|
|
14
|
CF (Berhampur)
|
EDS
|
DFO (Phulbani)
|
08/08/2022
|
Request to comply the point wise observations
|
|
15
|
DFO (Phulbani)
|
REPLY
|
CF (Berhampur)
|
24/08/2022
|
Diversion of 1.518 ha. of forest land for improvement of existing road 6.0 KM under PMGSY
|
|
16
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
30/08/2022
|
uploaded the KML file CA Scheme, Sol Topo sheet and Geo reference MAP of CA area of Phulbani Division
|
|
17
|
Nodal Officer
|
EDS
|
CF (Berhampur)
|
13/09/2022
|
You are once requested to comply Point No. ii & iii of GoI, MoEF & CC, IRO, BBSR letter dated 29.04.2022 immediately.
|
|
18
|
CF (Berhampur)
|
EDS
|
DFO (Phulbani)
|
15/09/2022
|
Requested to Compile Point-II & III
|
|
19
|
DFO (Phulbani)
|
REPLY
|
CF (Berhampur)
|
12/11/2022
|
POINT I, II & III
|
|
20
|
CF (Berhampur)
|
REPLY
|
Nodal Officer
|
22/11/2022
|
the DFO phulbani Division has compiled the point no.I,II & III
|
|
21
|
Nodal Officer
|
REPLY
|
State secretary
|
07/12/2022
|
EDS has been complied vide this office letter No. 24731 dated 06.12.2022 to MoEF & CC & GoI, IRO, BBSR
|
|
22
|
State secretary
|
REPLY
|
Regional Office
|
05/01/2023
|
Compliance furnished by PCCF (FD&NO) FC Act, O/o PCCF & HoFF, Odisha vide letter dtd.28.12.2022.
|
|