Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
State secretary
|
EDS
|
Nodal Officer
|
23/08/2018
|
date of construction of the infrastuctures
|
|
2
|
Nodal Officer
|
EDS
|
CF (Bhubaneswar)
|
23/08/2018
|
Please furnish the compliance to the observations made by F&E Department communicated to you vide this office memo No.17882 dated 23.08.2018.
|
|
3
|
CF (Bhubaneswar)
|
EDS
|
DFO (Rajnagar WL)
|
24/09/2018
|
|
|
4
|
DFO (Rajnagar WL)
|
EDS
|
User Agency (ce@paradipport.gov.in)
|
01/11/2018
|
alleged destruction of Mangrove Forest from the mouth of River Mahanadi by Paradip port trust
|
|
5
|
User Agency (ce@paradipport.gov.in)
|
REPLY
|
DFO (Rajnagar WL)
|
01/11/2018
|
The correction have been made as per the instruction received
|
|
6
|
DFO (Rajnagar WL)
|
REPLY
|
CF (Bhubaneswar)
|
01/11/2018
|
alleged destruction of Mangrove Forest from the mouth of River Mahanaddi by Paradip port trust
|
|
7
|
CF (Bhubaneswar)
|
REPLY
|
Nodal Officer
|
01/11/2018
|
Compliance in response to M.No. 17881 dt. 23.8.18 of Addl. PCCF (Nodal) & Letter No. 17888/F&E dt. 14.8.18 of F&E Deptt, Govt. of Odisha has been received from DFO, MFD(WL) Rajnagar vide his m.no. 6772 dt. 19.9.18 & forwarded to Nodal Office vide this office m. no. 4142 dt. 24.9.18 with encl & EDS replied by DFO. So the EDS sought for is replied to Nodal Office.
|
|
8
|
Nodal Officer
|
REPLY
|
State secretary
|
01/11/2018
|
Eds has been complied vide this office letter No. 20127 dated 29.09.2018.
|
|