TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/9112/2015              (ii). Name of Project for which Forest Land is required : Daitari Iron Ore Mining Lease              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Daitari ML area finds place within the Latitude: 21° 05’ 31.092” to 21° 07’ 10.34508” N and Longitude: 85° 45’ 59.97672” to 85° 49’ 17.01804” E in the Survey of India Topo Sheet bearing No. 73 G/16 on 1:50000 scale. The area exhibits an undulated topography with varying elevations from 865 meters (M              (iv). File no. : 8-28/2015-FC              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 746.3325
B. Time Line
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/OR/MIN/9112/201510/02/2015aa10/02/2015   10/02/2015

Keonjhar WL :12/02/2015


Cuttack :12/02/2015

Baripada:
  03/04/2015 (Keonjhar WL)

Angul:
  08/04/2015 (Cuttack)

Orissa:
17/05/2015
Orissa:
03/08/2015
19/09/201513/01/2016
14/03/2016
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 25/08/2017  
Replied by State Government (Orissa) on:18/06/2018  
Query raised by MoEFCC,New Delhi on 03/10/2018  
Replied by State Government (Orissa) on:20/07/2021  
Query raised by MoEFCC,New Delhi on 09/08/2021  
Replied by State Government (Orissa) on:13/04/2023  
Query raised by MoEFCC,New Delhi on 11/05/2023  
Replied by State Government (Orissa) on:16/03/2024  
Query raised by MoEFCC,New Delhi on 20/05/2024  
Query raised by State Government (Orissa) on:26/09/2017  
Replied by Nodal Officer (Orissa) on:13/06/2018  
Query raised by State Government (Orissa) on:17/08/2021  
Replied by Nodal Officer (Orissa) on:12/04/2023  
Query raised by State Government (Orissa) on:20/07/2023  
Replied by Nodal Officer (Orissa) on:14/03/2024  
Query raised by State Government (Orissa) on:30/05/2024  
Query raised by Nodal Officer (Orissa) on:18/10/2017  
Replied by Circle(Rourkela) on:13/12/2017  
Query raised by Nodal Officer (Orissa) on:18/10/2017  
Replied by Circle(Angul) on:30/05/2018  
Query raised by Nodal Officer (Orissa) on:30/09/2021  
Replied by Circle(Angul) on:28/03/2023  
Query raised by Nodal Officer (Orissa) on:30/09/2021  
Replied by Circle(Baripada) on:11/04/2023  
Query raised by Nodal Officer (Orissa) on:01/08/2023  
Replied by Circle(Angul) on:23/02/2024  
Query raised by Nodal Officer (Orissa) on:01/08/2023  
Replied by Circle(Baripada) on:11/03/2024  
Query raised by Nodal Officer (Orissa) on:05/06/2024  
Replied by Circle() on:  
Query raised by Nodal Officer (Orissa) on:05/06/2024  
Replied by Circle() on:  
Query raised by Circle (Angul) on:16/11/2021  
Replied by DFO (Cuttack) on:21/03/2023  
Query raised by Circle (Angul) on:05/08/2023  
Replied by DFO (Cuttack) on:19/02/2024  
Query raised by Circle (Angul) on:10/06/2024  
Replied by DFO () on:  
Query raised by DFO (Cuttack) on:18/11/2021  
Replied by UA on :29/08/2022  
Query raised by DFO (Cuttack) on:18/08/2023  
Replied by UA on :16/12/2023  
Query raised by DFO (Cuttack) on:18/06/2024  
Replied by UA on :  
NOTE:- Proposal is pending at User Agency due to EDS raised by Head Office .