TimeLine Details
Proposal received date at each stage of flow.
A. General Details
  (i). Proposal No. : FP/OR/MIN/37631/2018              (ii). Name of Project for which Forest Land is required : Dipside Manoharpur Coal Mine Project (Expansion of Manoharpur Coal Mine Project)              (iii). Short narrative of the proposal and Project/scheme for which the forest land is required : Odisha Coal and Power Limited (OCPL) has been allotted with two coal blocks, viz Manoharpur and Dip-side Manoharpur Coal Blocks by MoC. Manoharpur and Dip side of Manoharpur coal blocks are contiguous blocks having common boundary and Dip-side Manoharpur is expansion of the Manoharpur coal block.              (iv). File no. : 8-63/2011-Fc Vol.I              (v). State : Orissa              (vi). Category of the Project : Mining              (vii). Shape of forest land proposed to be diverted : Non Linear              (viii). Area of forest land proposed for diversion(in ha.): 342.87
B. Time Line
  
Proposal No.Submitted by User AgencyQuery for Shortcoming(if any) by Nodal OfficerResubmission of Proposal by User AgencyQuery by Nodal Officer for submitting Hard CopiesUploading(by U.A.) of copies of receipt received from DFO & DCDivisionCircleNodal OfficeState GovernmentMoEFCC,New DelhiRegional Office(SIR) uploaded onStage-I Approval onStage-II Approval on
FP/OR/MIN/37631/201814/12/201807/01/2020  15/12/2018   27/10/2020  31/12/2019   28/10/2020   29/10/2020 Sundargarh :03/11/2020Rourkela:
  28/01/2021 (Sundargarh)

Orissa:
22/12/2021
Orissa:
16/02/2023
27/02/202318/09/2023
01/11/2023
29/12/2023
By :Head Office
  
C. Essential Details Sought History
Communication between MoEFCC,New Delhi & State GovernmentCommunication between State Government & Nodal OfficerCommunication between Nodal Officer & CircleCommunication between Circle & DivisionCommunication between Division & User Agency
Query raised by MoEFCC,New Delhi on 24/03/2023  
Replied by State Government (Orissa) on:02/09/2023  
Query raised by MoEFCC,New Delhi on 27/11/2023  
Replied by State Government (Orissa) on:28/11/2023  
Query raised by State Government (Orissa) on:15/04/2023  
Replied by Nodal Officer (Orissa) on:31/08/2023  
Query raised by State Government (Orissa) on:28/11/2023  
Replied by Nodal Officer (Orissa) on:28/11/2023  
Query raised by Nodal Officer (Orissa) on:18/01/2022  
Replied by Circle(Rourkela) on:30/12/2022  
Query raised by Nodal Officer (Orissa) on:19/04/2023  
Replied by Circle(Rourkela) on:03/08/2023  
Query raised by Circle (Rourkela) on:02/02/2021  
Replied by DFO (Sundargarh) on:21/12/2021  
Query raised by Circle (Rourkela) on:18/01/2022  
Replied by DFO (Sundargarh) on:30/12/2022  
Query raised by Circle (Rourkela) on:27/04/2023  
Replied by DFO (Sundargarh) on:01/08/2023  
Query raised by DFO (Sundargarh) on:02/12/2020  
Replied by UA on :31/12/2020  
Query raised by DFO (Sundargarh) on:11/02/2021  
Replied by UA on :21/12/2021  
Query raised by DFO (Sundargarh) on:24/01/2022  
Replied by UA on :28/12/2022  
Query raised by DFO (Sundargarh) on:27/04/2023  
Replied by UA on :27/07/2023  
NOTE:- Stage-I Approval accorded by : Head Office .