Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
04/07/2016
|
Compliance
|
|
2
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
12/02/2019
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
07/03/2019
|
Please, submit the revised CA Scheme over 66.126 ha non-forest Govt. land identified Asanabahali under Dhenkanal division @Rs. 280/- per Mandays as per memo No. 1049 dated 20.09.2018 of PCCF, Odisha. Bhubaneswa
|
|
4
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
04/06/2019
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
20/07/2019
|
EDS
|
|
6
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
18/08/2021
|
The correction have been made as per the instruction received
|
|
7
|
DFO (Keonjhar)
|
EDS
|
User Agency (dipakbehera1@gmail.com)
|
04/10/2021
|
Please submit the updated KML file of the forest land proposed to be diverted.
|
|
8
|
User Agency (dipakbehera1@gmail.com)
|
REPLY
|
DFO (Keonjhar)
|
05/10/2021
|
The correction have been made as per the instruction received
|
|
9
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
04/02/2022
|
You are requested to comply the shortcomings as pointed out above at the earliest to facilitate processing of the proposal.
|
|
10
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
18/02/2022
|
You are requested to comply the shortcomings as pointed out by the PCCF Nodal at the earliest to facilitate processing of the proposal.
|
|
11
|
DFO (Keonjhar)
|
EDS
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
21/02/2022
|
Submission of compliance report
|
|
12
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
REPLY
|
DFO (Keonjhar)
|
28/05/2022
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
06/10/2022
|
Compliance report of the observations of CF(Nodal), O/o the PCCF, Odisha
|
|
14
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
07/10/2022
|
Comply the EDS
|
|
15
|
Head Office
|
EDS
|
State secretary
|
27/12/2022
|
EDS
|
|
16
|
State secretary
|
EDS
|
Nodal Officer
|
15/04/2023
|
For necessary compliance.
|
|
17
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
17/04/2023
|
Please comply the EDS vide this office Memo No. 179 dated 05.01.2023.
|
|
18
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
17/04/2023
|
Comply the EDS
|
|
19
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
03/05/2023
|
Please comply the EDS vide this office Memo No.8579 dated 03.05.2023.
|
|
20
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
09/05/2023
|
Please comply the EDS vide PCCF office Memo No.8579 dated 03.05.2023.
|
|
21
|
DFO (Keonjhar)
|
EDS
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
20/05/2023
|
Please, comply the observations of CF, Nodal
|
|
22
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
REPLY
|
DFO (Keonjhar)
|
06/10/2023
|
The correction have been made as per the instruction received
|
|
23
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
07/10/2023
|
Please find herewith the EDS reply on 03.05.2023 &13.07.2023 of PCCF, FD&NO, FC Act.
|
|
24
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
07/10/2023
|
Comply the EDS
|
|
25
|
Nodal Officer
|
REPLY
|
State secretary
|
09/10/2023
|
Compliance submitted to GoI, MoEF & CC, New Delhi vide this office Letter No. 19452 dated 30.09.2023.
|
|
26
|
State secretary
|
REPLY
|
Head Office
|
10/10/2023
|
Compliance furnished by PCCF (FD&NO) FC Act, O/o the PCCF & HoFF, Odisha vide letter dtd.30.09.2023
|
|
27
|
Head Office
|
EDS
|
State secretary
|
06/11/2023
|
EDS
|
|
28
|
State secretary
|
EDS
|
Nodal Officer
|
30/11/2023
|
For necessary compliance.
|
|
29
|
Nodal Officer
|
EDS
|
CF (Rourkela)
|
02/12/2023
|
You are requested to furnish the compliance. The EDS raised by GoI, MOEF & CC vide letter dated 06.11.2023.
|
|
30
|
CF (Rourkela)
|
EDS
|
DFO (Keonjhar)
|
15/12/2023
|
You are requested to furnish the compliance. The EDS raised by GoI, MOEF & CC vide letter dated 06.11.2023.
|
|
31
|
DFO (Keonjhar)
|
EDS
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
16/12/2023
|
Please coply the EDS raised dt. 06.11.2023 by MoEF&CC, Govt. of India
|
|
32
|
User Agency (sabyasachy_mishra@yahoo.co.in)
|
REPLY
|
DFO (Keonjhar)
|
24/01/2025
|
The correction have been made as per the instruction received
|
|
33
|
DFO (Keonjhar)
|
REPLY
|
CF (Rourkela)
|
27/01/2025
|
EDS compliance of MoEF&CC on 06.11.2023
|
|
34
|
CF (Rourkela)
|
REPLY
|
Nodal Officer
|
03/02/2025
|
Comply the EDS
|
|
35
|
Nodal Officer
|
REPLY
|
State secretary
|
21/02/2025
|
Compliance to the observations raised by MoEF&CC, New Delhi on dated 06.11.2023 is sent herewith.
|
|
36
|
State secretary
|
REPLY
|
Head Office
|
04/03/2025
|
Compliance furnished by the Addl. PCCF (FD&NO, FC Act), O/o the PCCF & HoFF, Odisha vide letter dtd.15.02.2025.
|
|