Sno. | From | Status | To | EDS Date | EDS sought/Replied | EDS Letter |
1
|
DFO (Cuttack)
|
EDS
|
User Agency (misrilallminesuk@yahoo.com)
|
04/07/2016
|
The hard copy of the diversion proposal has not been submitted by the user agency to this office.
|
|
2
|
User Agency (misrilallminesuk@yahoo.com)
|
REPLY
|
DFO (Cuttack)
|
04/07/2016
|
The correction have been made as per the instruction received
|
|
3
|
DFO (Cuttack)
|
EDS
|
User Agency (misrilallminesuk@yahoo.com)
|
05/07/2016
|
The hard copy of the diversion proposal has not been submitted by the user agency to this office.
|
|
4
|
User Agency (misrilallminesuk@yahoo.com)
|
REPLY
|
DFO (Cuttack)
|
22/07/2016
|
The correction have been made as per the instruction received
|
|
5
|
DFO (Cuttack)
|
EDS
|
User Agency (misrilallminesuk@yahoo.com)
|
26/07/2016
|
The deficiencies as noticed during the scrutiny of the proposal reqiures to be complied for processing of the proposal.
|
|
6
|
User Agency (misrilallminesuk@yahoo.com)
|
REPLY
|
DFO (Cuttack)
|
05/08/2016
|
The correction have been made as per the instruction received
|
|
7
|
Nodal Officer
|
EDS
|
CF (Angul)
|
07/09/2016
|
Hence, the diversion proposal in 4 sets is returned herewith for re-submission of the same complete in all respect.
|
|
8
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
17/10/2016
|
Compliance has been submitted by DFO Cuttack on the objections raised by Addl PCCF Nodal regarding compensatory land of Saruabil chromite mine
|
|
9
|
Nodal Officer
|
EDS
|
CF (Angul)
|
17/10/2016
|
Revised Compensatory Afforestation is to be uploaded.
|
|
10
|
CF (Angul)
|
EDS
|
DFO (Cuttack)
|
18/10/2016
|
As desired by Addl PCCF Nodal revised comp affn scheme is to be uploaded.
|
|
11
|
DFO (Cuttack)
|
EDS
|
User Agency (misrilallminesuk@yahoo.com)
|
20/10/2016
|
The corrected CA land KML file requires to be uploded
|
|
12
|
User Agency (misrilallminesuk@yahoo.com)
|
REPLY
|
DFO (Cuttack)
|
21/10/2016
|
The correction have been made as per the instruction received
|
|
13
|
DFO (Cuttack)
|
REPLY
|
CF (Angul)
|
21/10/2016
|
The revised scheme for compensatory afforestation over 7.4 ha. alongwith required map has been submitted.
|
|
14
|
CF (Angul)
|
REPLY
|
Nodal Officer
|
22/10/2016
|
Compliance has been submitted by DFO Cuttack on the objections raised by Addl PCCF Nodal regarding Comp land of Saruabil chromite mines.
|
|